• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

What lessons have been learnt after the GWML electrification cost overruns?

Status
Not open for further replies.

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,352
Location
Nottingham
Transport minister Mark Harper claims that "We’ve learned a lot from the electrification of the Great Western line.”
Is there any evidence that this is the case? What lessons have been learnt, and where might these have been documented?
Have these been incorporated into later electrification projects?

The only concrete examples I know of are
  1. the Cardiff Intersection bridge, where it was shown that the electrical clearances used by British Rail in the 1970's could still be used today.
  2. Steventon bridge, where a district council demonstrated that it could use planning law to undermine infrastructure projects of national importance
Are there any others?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Gloster

Veteran Member
Joined
4 Sep 2020
Messages
13,047
Location
Up the creek
None, absolutely none. The mistakes will be repeated, first as tragedy and then as a never ending farce.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,760
Location
Nottingham
This came out a few years ago.


The Electrification Cost Challenge (ECC) report uses examples from the UK and internationally to show that the high costs seen on recent projects, including the Great Western Electrification Programme, can be avoided in the future. It suggests that significant increase in cost on some past projects like Great Western should be seen as a one-off, caused by an unrealistic programme of work, unpreparedness in using novel technologies resulting in poor productivity and a ‘feast and famine’ electrification policy.
 

eldomtom2

On Moderation
Joined
6 Oct 2018
Messages
2,399
Well, how much cheaper are the Huddersfield and MML electrification projects then?
 

The exile

Established Member
Joined
31 Mar 2010
Messages
9,474
Location
Somerset
Exactly!



Per mile I think they are more expensive!
Given the topography, I would expect the Leeds - Manchester section to be pretty pricey (and it’s also having a lot more done than stringing up wires). Surprised by MML if that is the case.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,563
TRU is being much more prudent with remediating old mine workings than NWEP.
One of the main lessons is being absolutely ruthless deciding what counts towards the electrification stkm price, and lumping everything else that may occur as part of the programme into enhancements (platform extensions, line speed increase etc.)
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,352
Location
Nottingham
Per mile I think they're are more expensive!
I don't think I've not seen any numbers for the Kettering-Wigston section of the MML, and certainly no BCR calculations for subsequent sections. From which I assume the business case is so bad that they they're keeping quiet about it.
 
Status
Not open for further replies.

Top