The Pretendolino didn't run to time, it used up engineering allowances on the way. It never caused delay incidents as it didn't lose enough time in a section.
The Pretendolino didn't run to time, it used up engineering allowances on the way. It never caused delay incidents as it didn't lose enough time in a section.
Also of note, Virgin have already looked into reducing the three trains an hour (between Birmingham and Euston) down to two in the middle of the day.
There are 21 5-car tilting 125mph units available. With XC.
Just give XC some power-door short HSTs in exchange and the job is done.
There is no chance of making more HSTs PRM-TSI compliant prior to 2020, there is no capacity left to do EMTs HSTs.
I will naturally be biased, travelling from Stafford a lot of the time, but the loss of London-bound fast services would be a heavy blow for Stafford. The WMT services take 50% longer at the best times of day, start much later and stop much earlier. As for getting Voyagers, I'm sure Staffordians are plenty happy with their current Pendolinos!taking the Stafford stop from Liverpool services
I will naturally be biased, travelling from Stafford a lot of the time, but the loss of London-bound fast services would be a heavy blow for Stafford. The WMT services are 50% slower at the best time of day, start much earlier and stop much later. As for getting Voyagers, I'm sure Staffordians are plenty happy with their current Pendolinos!
Not sure if this is the right discussion or if it's come up elsewhere, but Real Time Trains is showing Blackpool getting three Pendolinos a day to and from Euston in the May 18 timetable. I've not seen confirmation of this anywhere else (e.g. on Virgin's website). Are these trains approved or are they just paths for which Virgin has applied.
That is far from certain. It might be possible somewhere like EMT to allow non-compliant trains to continue in service for a limited period so people who can't access the trains will be unable to for a longer period. However I have a feeling replacing more accessible trains by less accessible ones under a derogation, even though only temporary, would go down much less well. It would effectively be denying travel to some people who have come to expect that they can use a particular service.They don't have to be PRM-TSI compliant by 2020, they can get a temporary waiver to operate pending reconstruction.
Yes 3 trains each way to/from Blackpool. But only two out of the three are Pendolinos. The other will be a Voyager as previously.
I was suggesting boosting the capacity of the London-Chester/Holyhead services. The addition of a stop at Milton Keynes and the slower speed of Voyagers means that London-Crewe is 10 minutes slower than on the non stop Manchester services. I am not convinced that more stock is needed to last until 2026 and certainly not after but switching 4-5 Voyagers from XC to WCP and reinstalling tilt mechanisms would make more financial sense than new tilting trains. I am sure Staffordians prefer Pendolinos to Voyagers but Stafford is less important than Liverpool and there are limited cheap options for increasing capacity for the latter.
Is it really beyond all possibility ro rustle up a single further set per hour ? What's currently being thought of for open access services to Blackpool, and why couldn't that solution be applied ?
:P Nice. Ha ha.What is your source for this?
I'd have thought the existing 2TPH would still be needed for journeys such as Stoke to Manchester or Birmingham. There's also the question of what happens to XC's longer distance services. Running the HS2 service to Bristol would need electrification and a classic connection in the Birmingham area, and truncating them at Birmingham means passengers would have to change stations and nullify most of the time saving from using HS2 on Birmingham-Manchester. Therefore something like the existing XC service would probably remain, to cater for the various journeys that HS2 can't provide. Hopefully HS2 would take the major flows, Manchester-Birmingham in this case, leaving space on the classic services for Stoke passengers and the like. Much the same applies to the NE-SW route in relation to the eastern leg of HS2.However as pointed out before, once Manchester gains is HS2 services there's likely to be a switch from XC to HS2 for those traveling between Birmingham and Manchester. As such if the HST's were kept until then and then withdrawn, it could then allow XC to reduce capacity on that section if required on the other (to SW) services.
I'd have thought the existing 2TPH would still be needed for journeys such as Stoke to Manchester or Birmingham. There's also the question of what happens to XC's longer distance services. Running the HS2 service to Bristol would need electrification and a classic connection in the Birmingham area, and truncating them at Birmingham means passengers would have to change stations and nullify most of the time saving from using HS2 on Birmingham-Manchester. Therefore something like the existing XC service would probably remain, to cater for the various journeys that HS2 can't provide. Hopefully HS2 would take the major flows, Manchester-Birmingham in this case, leaving space on the classic services for Stoke passengers and the like. Much the same applies to the NE-SW route in relation to the eastern leg of HS2.
That was the spin for Norton Bridge, I still don't see where two extra paths have appeared from as you are still reliant on what happens south of Rugby and nothing has changed there. The resiliance bit I am sceptical about too, if a path is compliant we would need a very good reason to say no to it.The paths Alliance / Grand Central are trying to use are off peak only. They were granted paths dependent on 125mph running but have since reapplied and want to use Mark IV sets at 110mph but they may not succeed. Since Norton Bridge work completed there has been spare off peak capacity for 2tph. 1tph will need to stay unused for timetable resiliance, which means regardless of whether or not the new Alliance application is granted there will be only a handful of paths spare each day and none at peak times between London and Crewe.
Weren't the Norton Bridge paths always going to be West Midlands -> NW paths? I don't think it ever specified there was capacity from the London direction. Wasn't a cross-Rugeley Manc/Brum service mentioned, for instance? Or maybe a Euston/Brum terminator can be extended to Manchester?
The paths Alliance / Grand Central are trying to use are off peak only. They were granted paths dependent on 125mph running but have since reapplied and want to use Mark IV sets at 110mph but they may not succeed. Since Norton Bridge work completed there has been spare off peak capacity for 2tph. 1tph will need to stay unused for timetable resiliance, which means regardless of whether or not the new Alliance application is granted there will be only a handful of paths spare each day and none at peak times between London and Crewe.
There is no cost effective solution to the problem as things stand. It seems to be a matter of making do until 2026. Some extra Voyagers might be the least bad idea for extra stock but even then there are not that many extra services they could run. I doubt WCP could make use of more than another 10-12.
I'd have thought the existing 2TPH would still be needed for journeys such as Stoke to Manchester or Birmingham. There's also the question of what happens to XC's longer distance services. Running the HS2 service to Bristol would need electrification and a classic connection in the Birmingham area, and truncating them at Birmingham means passengers would have to change stations and nullify most of the time saving from using HS2 on Birmingham-Manchester. Therefore something like the existing XC service would probably remain, to cater for the various journeys that HS2 can't provide. Hopefully HS2 would take the major flows, Manchester-Birmingham in this case, leaving space on the classic services for Stoke passengers and the like. Much the same applies to the NE-SW route in relation to the eastern leg of HS2.
Ah, the joys of 'no growth' (whether expressly stated or not) franchises.
At the risk of plunging into desperatio , have any Pendolino-like trains whixb would fit our gauge become available overseas ?
Weren't the Norton Bridge paths always going to be West Midlands -> NW paths? I don't think it ever specified there was capacity from the London direction. Wasn't a cross-Rugeley Manc/Brum service mentioned, for instance? Or maybe a Euston/Brum terminator can be extended to Manchester?
What we got was one retimed XC service and (importantly) a significantly more punctual WCML.A fast line, standard off-peak hour timetable to deliver this has been developed by Network Rail and agreed by DfT in August 2009.
The project will deliver the capability for two additional, off peak, fast line paths from London to the North West (each direction), one additional path per hour on the Birmingham-Manchester axis (each direction) and one additional freight path per hour through Stafford, again in each direction.
I was thinking more along the lines of longer trains (i.e. a pair of Voyagers) Exeter to Manchester pre HS2 to Manchester and then truncate that to Exeter to Birmingham there after. As such it would mean that less units were needed, but two trains per hour would still exist.
That was the spin for Norton Bridge, I still don't see where two extra paths have appeared from as you are still reliant on what happens south of Rugby and nothing has changed there. The resiliance bit I am sceptical about too, if a path is compliant we would need a very good reason to say no to it.
There isn't room to put platforms there on the gradient and with the tunnel and Proof House junction nearby, there also is no connection between HS2 and the existing network either.With XC services extended from New Street to some westbound platforms attached to Curzon Street? If the underlying plan was to replace XC to Manchester with HS2 (and, dare I say it, to provide a fast Brum connection to Liverpool, and points further north, via HS2 as well), and if HS2's eastern leg is going to replace XC towards the East Midlands (from Toton northwards), Yorkshire and the north east, would this provide an opportunity ro send HS2 services from the south west and south coast to Brum to existing or new destinations in (say) the rest of the East Midlands and East Anglia ?
If the Pretendolino could make section times then what's to stop one of the Birmingham's being planned in at 110mph?
I am guessing that the Pretendolino was quick enough to not hold any following trains up, but ended up failing it's performance at its destination due to being tined at 125mph?
Answer: time it at 110mph to it's destination and if the stock can still make section times it's a solution isn't it?
Acquire some of the class 360s which are coming off lease soon and ask siemens to do the mods required for 110 as on the 350s.
Or what about the 350/2s which are going off lease with LNR? Many are being converted to 110 at the moment so all that'd be needed would be refitted 444 style long distance interiors.
Or use 225 sets if they could make section times?
With XC services extended from New Street to some westbound platforms attached to Curzon Street? If the underlying plan was to replace XC to Manchester with HS2 (and, dare I say it, to provide a fast Brum connection to Liverpool, and points further north, via HS2 as well), and if HS2's eastern leg is going to replace XC towards the East Midlands (from Toton northwards), Yorkshire and the north east, would this provide an opportunity ro send HS2 services from the south west and south coast to Brum to existing or new destinations in (say) the rest of the East Midlands and East Anglia ?
Ah, the joys of 'no growth' (whether expressly stated or not) franchises.
At the risk of plunging into desperatio , have any Pendolino-like trains which would fit our gauge become available overseas ?