If Penwortham ever got built, I assume it really only helps the section (well) north of Weaver Jct - Euxton Jct etc?
Yeah not directly useful to Weaver-Crewe. However, it's presence does probably improve emergency feeding configurations regarding an outage at Willow Park, Weaver Jnc or Heyrod. But the Catterall area is probably the second worst bottleneck around, but maybe doesn't have the K11 switchgear risk being a mark III era systemIf Penwortham ever got built, I assume it really only helps the section (well) north of Weaver Jct - Euxton Jct etc?
I missed this but you're right there are a few oddities in the diagram.Many thanks - it zooms in and stays very clear. Fascinating to see the variety of transformer ratings and the clear distinction between overlap and neutral sections. Also Kings Langley and Headstone Lane adjacent neutral section TSC's with KL n/c. Were Crewe TF's 10 and 15MVA?
Let's salute the operators who memorised this diagram!
WAO
Sadly not. Declaring Congested Infrastructure is a Network Code for timetabling/sale of rights:Thats the whole point of declaring it, it means something has to be done.
That's only part of Congested Infrastructure.Sadly not. Declaring Congested Infrastructure is a Network Code for timetabling/sale of rights:
4.3.2 Section D4 of the Network Code sets out the processes that Network Rail will follow and the factors that it will consider in making decisions on the priorities for the allocation of scarce capacity; on congested infrastructure these will be applied with regard for the requirements of the regulations.
From Regulation 27:(4) Where railway infrastructure has been declared to be congested in accordance with paragraph (1) or (2), the infrastructure manager must undertake a capacity analysis of the congested infrastructure, as described in regulation 27, unless a capacity enhancement plan, as described in regulation 28, is in the process of being implemented.
From Regulation 28:(5) The infrastructure manager must complete the capacity analysis within six months from the date on which the railway infrastructure is declared to be congested in accordance with regulation 26(1) or (2) and make the findings of the analysis available to the parties described in regulation 26(3).
28.—(1) The infrastructure manager must, within six months of the publication of a capacity analysis in accordance with regulation 27, produce a capacity enhancement plan.
Which means that it is not an absolute fact that "declaration of congested infrastructure will trigger capacity upgrades", if the required upgrades do not pass a Cost-benefit analysis.(4) On the basis of a cost benefit analysis of the potential measures for action identified in the capacity enhancement plan, that plan must include—
(a)details of the action to be taken to enhance the capacity of the congested infrastructure; and
(b)a timetable for the completion of the detailed measures identified in accordance with sub-paragraph (a).