Put a note in your 2009 diaries (honestly you might need to).
Work starts towards the end of November 2009 onwards for the SWML W10 Freight Clearance scheme.
Yes I did mean to put 2009. You can just see South Today and Meridian Tonight stroking themselves over the 6 day possesion between Soton and Northam Jcn.
The information is correct at the time of writing.
Cheers
Hentis
Work starts towards the end of November 2009 onwards for the SWML W10 Freight Clearance scheme.
29th - 30th November 2009
Engineering work between:-
- Redbridge - Brockenhurst
- Track EA1002
- Track BK1008 Follow Up
- Enhancements W10 freight clearance scheme - Junction Road footbridge
5th - 11th December 2009 (168 hrs) 6 Days
Engineering work between:-
- Southampton - Northam Jcn
- Enhancements Southampton to Stafford freight route upgrade.
- Single Line Working over Down Main
Yes I did mean to put 2009. You can just see South Today and Meridian Tonight stroking themselves over the 6 day possesion between Soton and Northam Jcn.
The information is correct at the time of writing.
Cheers
Hentis