An interesting question came up at work today, which I don't know the answer to. So I've opened it up to the esteemed folk on these forums 
In the Working Timetable, allowances are added to schedules reflecting different elements of operations:
The question is, when did these allowances first come into use in developing the working timetable?
Given splitting distants existed a long while ago (Great Western Railway before First World War), I'd argue that the adjustment allowances must come from before then, but I can't really be sure.
In the Working Timetable, allowances are added to schedules reflecting different elements of operations:
- [Engineering] allowances ("Box time") - To cover the impact of planned temporary speed restrictions associated with engineering works on the network.
- <Performance> allowances ("Diamond time") - To cover anticipated time loss across sections of a journey.
- {Adjustment} allowances ("Squiggly time") - To cover situations where a train will be performing a move that means it will be unable to meet its Sectional Running Time for that section. Usually, this is because the train is not travelling on the fastest route between the two consecutive timing points, for which that particular Sectional Running Time is calculated. This could be due to needing to brake for a slow-speed junction, approach controls, or acceleration to prevailing line speed after passing through a slow-speed junction.
- (Pathing) allowances ("Circle time") - To compensate for an increase in running time in a section due to the service sighting a signal aspect that would prevent it from meeting its SRT and to meet applicable Timetable Planning Rules, such as maintaining headway or a junction margin.
The question is, when did these allowances first come into use in developing the working timetable?
Given splitting distants existed a long while ago (Great Western Railway before First World War), I'd argue that the adjustment allowances must come from before then, but I can't really be sure.