Hopefully if this were to happen, security would be seen as a necessity. I can imagine a lot of peeved passengers at a weekday closure of a core section of the system anyway, so having to run at a reduced frequency due to train vandalism wouldn't help.
Just posted a few questions on the nexus forum to see if we can can get any additional info. I'm particually interested in the answer to the second question. Although it would be no surprise for them to rely on people checking the website. Having said that they did a good job with the Wallsend to Tynemouth closure last year. In fact I'm surprised they didn't take advantage of the jubilee bank holiday. Questions below:
Huw
I've heard talk that the junction at South Gosforth is due to be replaced later on this year meaning this section of track will be out of use for 5 days and no services running from South Gosforth to Regent Centre/Longbenton. *I have a few questions regarding this.*
First can you advise when this is currently planned for? *I assume this will be before mid November in order to avoid disruption in the run up to Christmas. *In fact it's a shame this wasn't planned for the 2 day bank holiday next month.*
[
Second will Nexus be communicating with the business parks close to the affected area to give plenty of notice. By this I am mainly referring to those around Regent Centre and Four Lane Ends
Third I understand that during the disruption some services will use the depot avoiding line. Can you advise what kind of service this would be? I.e would it be a full service from coast to Airport or would it be a shuttle service between Regent Centre and somewhere like Four Lane Ends?
Finally how will trains get from the depot to the south part of the system (I.e south of the Tyne). Will trains run around the coast through the Manors curve reversing at Jesmond or will trains be stabled at either Pelaw or South Shields sidings. *This of course could leave the trains a target for vandalism, unless security was drafted in.
--- old post above --- --- new post below ---
According to http://www.twita.gov.uk/sites/default/files/agenda_document/Metro%2001-03-2012_0.pdf
it's planned for 25th October to 5th November meaning 11 days out of action. This is from the most recent meeting in March. Details are on page 14 and a map of the system is given on page 15 showing what is off where. Looking at it the dates are planned but not confirmed. Interestingly it also reveals two 54 hour possessions between Gateshead and Jarrow and one 54 hour possession between Central and Gateshead Stadium. Again these aren't confirmed. Does this mean only one platform will be used at Gateshead and 1 at Monument and Central?