Now official, TftN plan to be published for 13 week consultation next month. Business case to be submitted to DfT before End 2018.
http://www.transportforthenorth.com/leaders-unite-behind-draft-transport-plan/
30 year £2-2.3bn annual spend (up from current £1.3bn)
Things they are proposing:
Manchester to York via through Leeds NPR
Liverpool to cheshire HS2 including connection to Manchester line
Underground through Manchester Piccadilly NPR platforms alongside surface terminals.
Northern connection at Clayton between HS2 and Sheffield
Cheaper Revised Underground road tunnel between Manchester and Sheffield with shorter tunnel, improved Woodhead Pass and east of Sheffield road improvements.
Revised electrification/station priority investment list.
Shorter term investments including smart ticketing.
http://www.transportforthenorth.com/leaders-unite-behind-draft-transport-plan/
30 year £2-2.3bn annual spend (up from current £1.3bn)
Things they are proposing:
Manchester to York via through Leeds NPR
Liverpool to cheshire HS2 including connection to Manchester line
Underground through Manchester Piccadilly NPR platforms alongside surface terminals.
Northern connection at Clayton between HS2 and Sheffield
Cheaper Revised Underground road tunnel between Manchester and Sheffield with shorter tunnel, improved Woodhead Pass and east of Sheffield road improvements.
Revised electrification/station priority investment list.
Shorter term investments including smart ticketing.