Transpennine Route Upgrade and Electrification updates

Joined
31 Mar 2020
Messages
67
Location
Tiverton Parkway Railway Station
1) not seen anything recently and it's not in scope for TRU.

2) nothing confirmed at the moment only passive provision for Thorpe Park Station is planned nothing else. Outside of scope of TRU.
Thanks for that. In regard to Thorpe Park Station, I’ve found an article from their development website proposing the date of the station opening.

“That shift will be supported significantly by the arrival of the new Thorpe Park railway station, scheduled to open in 2027, providing direct access to Leeds city centre in under eight minutes.”

But as you mentioned, I think this is less of a TRU topic and more of a WYCA topic.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

YorksLad12

Established Member
Joined
5 Feb 2020
Messages
2,718
Location
Leeds
Is the proposed Thorpe Park railway station the one that originally had £20 million allocated to it in 2008 by the Yorkshire and Humber Regional Transport Board only for Governmental policy changes to obviate it?
I think the idea for the present Thorpe Park came after the suggested East Leeds Parkway (which was really just a way to clear trains away from Leeds Station by freeing up platform space) didn't happen. There wouldn't have been space in the timetable for both.
 

Spartacus

Established Member
Joined
25 Aug 2009
Messages
3,833
2) nothing confirmed at the moment only passive provision for Thorpe Park Station is planned nothing else. Outside of scope of TRU.

It's funny really as almost the whole Leeds & Selby Railway was built from the outset with passive provision for 4 track but not all ever got it. I understand most, if not all, modern structures over the line have been to the same standard.
 

Grumpy

Established Member
Joined
8 Nov 2010
Messages
1,321
Photo taken yesterday from the East Leeds Orbital Road bridge at Thorpe Park. Facing towards Leeds. I have no idea what the Orangemen were doing.
I dont know where it was intended to build a station, but the green field is the nearest to the Commercial Centre (a potential 10 minute walk uphill).
The recently erected OHLE posts suggest to me that 4 tracking isn't going to happen.
Shame.

1760083754273.jpeg
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,668
Photo taken yesterday from the East Leeds Orbital Road bridge at Thorpe Park. Facing towards Leeds. I have no idea what the Orangemen were doing.
I dont know where it was intended to build a station, but the green field is the nearest to the Commercial Centre (a potential 10 minute walk uphill).
The recently erected OHLE posts suggest to me that 4 tracking isn't going to happen.
Shame.

View attachment 190092
Four tracking definitely is not happening as part of TRU only passive provision in the construction of Thorpe Park Station. (Some bits of TRU may be passive provisioned too but not aware).
 

bengley

Established Member
Joined
18 May 2008
Messages
1,987
Photo taken yesterday from the East Leeds Orbital Road bridge at Thorpe Park. Facing towards Leeds. I have no idea what the Orangemen were doing.
I dont know where it was intended to build a station, but the green field is the nearest to the Commercial Centre (a potential 10 minute walk uphill).
The recently erected OHLE posts suggest to me that 4 tracking isn't going to happen.
Shame.

View attachment 190092

That type of Twin Track Cantilever can have another one bolted onto the other side making it a full four track portal, so it looks like they might be leaving passive provision.
 

neil65

Member
Joined
15 Jul 2022
Messages
537
Location
Huddersfield, Kirklees, United Kingdom
Very quiet at Huddersfield station Saturday 11th October 2025
Nothing happening this Saturday morning

Neil
 

Dave S 56F

Member
Joined
23 Jun 2020
Messages
235
Location
Cleckheaton west yorkshire
I went to the new huddersfield plat 3 yesterday on my way to the worth valley steam railway and noticed its quite improved only having 2 through platforms for trains to leeds newcastle eastbound plat 3 and manchester Liverpool westbound trains plat 2 although the man vic train does terminate on new plat 3 and 1 extended plat 1 for sheffield.
When does the next phase of work start to construct platforms 4 5 6 at huddersfield would anyone know?
I presume where plat 8 was will be new platform 4, and 5 6 I'm guessing is when the island platform is built near the old goods yard so at a guess the single span bridge still to go over John William St will be for the lines into plat 6 and also is plat 6 new going to be a termini plat for bradford trains Would it be from next year after new year 2026?
 

1D53

Established Member
Joined
2 Apr 2006
Messages
2,892
Work is starting now on the new platforms 4, 5 and 6 with commissioning set for January 2027.
 

Spartacus

Established Member
Joined
25 Aug 2009
Messages
3,833
It looks like the bridge lift at Jack Lane between Batley & Dewsbury’s imminent with a crane in position this morning.
 

Monkeyhead

Member
Joined
21 Sep 2016
Messages
90
Photo taken yesterday from the East Leeds Orbital Road bridge at Thorpe Park. Facing towards Leeds. I have no idea what the Orangemen were doing.
I dont know where it was intended to build a station, but the green field is the nearest to the Commercial Centre (a potential 10 minute walk uphill).
The recently erected OHLE posts suggest to me that 4 tracking isn't going to happen.
Shame.

View attachment 190092
The station and its car park is planned there and in the foreground - I noticed on the way into Leeds the other day that all the OHLE piling was aside the existing 2 tracking, so they've definitely not created any provision for expansion. Whether piling for OHLE is particularly difficult or not I don't know, but I guess it's a little surprising that you wouldn't "do it once" - I guess there's expense in creating spans for 4 tracks if you're only using 2 for a while
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,692
Location
Nottingham
The station and its car park is planned there and in the foreground - I noticed on the way into Leeds the other day that all the OHLE piling was aside the existing 2 tracking, so they've definitely not created any provision for expansion. Whether piling for OHLE is particularly difficult or not I don't know, but I guess it's a little surprising that you wouldn't "do it once" - I guess there's expense in creating spans for 4 tracks if you're only using 2 for a while
Recent schemes have electrified 4-track sections with separate twin-track cantilevers on either side of the line where they could, rather than having portals right across all tracks. So if it ever was four-tracked, and if the existing tracks were far enough to one side to be out of the way of the new ones, then they would most likely just add more twin-track structures on the other side.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,864
Location
Beeston (Notts)
That type of Twin Track Cantilever can have another one bolted onto the other side making it a full four track portal, so it looks like they might be leaving passive provision.
I will say this - the Series 1 TTCs do not have, have not had, and will not have the ability to bolt the booms together.

The portal booms are different designs of steel altogether, although similar.
 

Grumpy

Established Member
Joined
8 Nov 2010
Messages
1,321
so they've definitely not created any provision for expansion. Whether piling for OHLE is particularly difficult or not I don't know, but I guess it's a little surprising that you wouldn't "do it once" - I guess there's expense in creating spans for 4 tracks if you're only using 2 for a while
And no doubt there was extra expense in building the new road bridge to span a potential 4 tracks rather than just the 2 existing. On that occasion somebody showed some common sense.
 
Joined
1 Nov 2021
Messages
312
Location
Berwick
There appears to be a better shelter over the underpass exit now

== Doublepost prevention - post automatically merged: ==

The widened bridge offers a good vantage point.
 

Attachments

  • IMG_1903.jpeg
    IMG_1903.jpeg
    4.2 MB · Views: 270
  • IMG_1906.jpeg
    IMG_1906.jpeg
    1.8 MB · Views: 265

quantinghome

Established Member
Joined
1 Jun 2013
Messages
2,897
Recent schemes have electrified 4-track sections with separate twin-track cantilevers on either side of the line where they could, rather than having portals right across all tracks. So if it ever was four-tracked, and if the existing tracks were far enough to one side to be out of the way of the new ones, then they would most likely just add more twin-track structures on the other side.
Exactly. People are reading far too much into this. A quick look on an aerial map shows that there's space to the north (on the right side in the photo) and a housing estate to the south. Building two new tracks to one side of the current alignment has considerable efficiencies.

EDIT: Just to add, this aligns with the plans for the Thorpe Park station, where the northern platform is intended to be an interim structure.
 
Last edited:

neil65

Member
Joined
15 Jul 2022
Messages
537
Location
Huddersfield, Kirklees, United Kingdom
Is it the end of the line for the mk1 coach and 144001 at Huddersfield station?
The road alongside them is closed on the 16th possibly meaning a crane and low loader are going to move them. I heard rumours that TPX wanted them removed as they were becoming a eyesore

https://railway-photography.smugmug.com/Days-out/2025/October-2025/Tpu/i-CX3R9Wv/A

https://railway-photography.smugmug.com/Days-out/2025/October-2025/Tpu/i-KTw4N2K/A

https://railway-photography.smugmug.com/Days-out/2025/October-2025/Tpu/i-Kx4ZxQt/A

https://railway-photography.smugmug.com/Days-out/2025/October-2025/Tpu/i-SnNSbRH/A

Neil
 

LittleAH

Established Member
Joined
24 Oct 2018
Messages
1,213
Is it the end of the line for the mk1 coach and 144001 at Huddersfield station?
The road alongside them is closed on the 16th possibly meaning a crane and low loader are going to move them. I heard rumours that TPX wanted them removed as they were becoming a eyesore

https://railway-photography.smugmug.com/Days-out/2025/October-2025/Tpu/i-CX3R9Wv/A

https://railway-photography.smugmug.com/Days-out/2025/October-2025/Tpu/i-KTw4N2K/A

https://railway-photography.smugmug.com/Days-out/2025/October-2025/Tpu/i-Kx4ZxQt/A

https://railway-photography.smugmug.com/Days-out/2025/October-2025/Tpu/i-SnNSbRH/A

Neil
Nope. That end of the station is being used as a secondary means of fire escape. TRU want them gone too.
 

Mcr Warrior

Veteran Member
Joined
8 Jan 2009
Messages
17,287
Noted that, for now, there's only the three platforms in operation at Huddersfield. Platform 1 (Bay) towards Sheffield via Barnsley. Platform 2 (Through) for services towards Manchester and beyond and Platform 3 (Through) towards Leeds and York. Presume there's been some platform re-numbering going on here?! Also, are any of the other platforms at Huddersfield going to be brought back into use? If so, when? Or have they now gone?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,618
Location
Northampton
Noted that, for now, there's only the three platforms in operation at Huddersfield. Platform 1 (Bay) towards Sheffield via Barnsley. Platform 2 (Through) for services towards Manchester and beyond and Platform 3 (Through) towards Leeds and York. Presume there's been some platform re-numbering going on here?! Also, are any of the other platforms at Huddersfield going to be brought back into use? If so, when? Or have they now gone?
The plans are upthread, but I think the island platform is being slightly modified and there'll be 3 additional platforms (2 through and 1 Leeds-facing slow line bay) behind the current P3.

I'm slightly, but pleasantly, surprised they have taken the opportunity to renumber the platforms.

(Edited to correct the platform details)
 
Last edited:

Mcr Warrior

Veteran Member
Joined
8 Jan 2009
Messages
17,287
The plans are upthread...
No doubt, but we are almost up to 10,000 posts on this particular thread and use of the 'search' function didn't immediately yield anything promising. So, where best to head off to?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,618
Location
Northampton
No doubt, but we are almost up to 10,000 posts on this particular thread and use of the 'search' function didn't immediately yield anything promising. So, where best to head off to?
I'm looking for them, but that's also why I outlined the headline changes.

I have now dug out the following PDF: https://gat04-live-1517c8a4486c4160...field_station_design_and_access_statement.pdf

That has the following image:
1760785036981.png
Showing that the platforms are effectively being 'pushed' towards the leeds end, and that there will be 4 through platforms at Huddersfield with the existing Island narrowed (so my earlier post was wrong), with a leeds-facing bay for the slow lines.

Assuming all movements are signalled, platforms 3 and 4 will be fully bi-directional, and trains from Leeds/bradford could terminate in any of 2-6 to return. It would also be possible for trains from Manchester to use any available platform and still be able to choose either fast or slow lines for maintenance or disruptions reasons if required.
 
Last edited:

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,341
Location
Nottingham
No doubt, but we are almost up to 10,000 posts on this particular thread and use of the 'search' function didn't immediately yield anything promising. So, where best to head off to?
Searching for "plan" in this thread gave me post #9532:

 

Mcr Warrior

Veteran Member
Joined
8 Jan 2009
Messages
17,287
Searching for "plan" in this thread gave me post #9532:

I'm obliged. That's helpful. Fairly recent also!
 

noddingdonkey

Member
Joined
2 Nov 2012
Messages
924
Is the above plan correct, with no connection from the Penistone Line to any of the through platforms? RTT suggests that the last train of the night uses Platform 2 and then goes ECS to Hillhouse at present.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,618
Location
Northampton
Is the above plan correct, with no connection from the Penistone Line to any of the through platforms? RTT suggests that the last train of the night uses Platform 2 and then goes ECS to Hillhouse at present.
There is a crossover at the far end of the tunnel between the Branch and the westbound main line, so the Penistone Line will be able to use any of 1-4, assuming no further changes are made to the tracks further out.
 

neil65

Member
Joined
15 Jul 2022
Messages
537
Location
Huddersfield, Kirklees, United Kingdom
Is the above plan correct, with no connection from the Penistone Line to any of the through platforms? RTT suggests that the last train of the night uses Platform 2 and then goes ECS to Hillhouse at present.


Obviously there has to be way for units to get from Hillhouse to Platform 1 and the Penistone line, remember RHTT still come this way into the main line station, this was from Friday https://www.realtimetrains.co.uk/service/gb-nr:H02371/2025-10-17/detailed
 

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,640
Location
Rochdale
Springwood junction so far as I know was always the point where trains accessed the far platforms in the past. There was (still is) not much room between the tunnel at the station end and the platforms to access the higher number platforms from the Sheffield bay side.

See this lovely painting that shows how trains from Sheffield could access every platform with the aid of an additional diamond crossing at Springwood Junction

:)
 

Attachments

  • 4be4c69328e65a784eb22752e2d44dbe.jpg
    4be4c69328e65a784eb22752e2d44dbe.jpg
    61.2 KB · Views: 183
Last edited: