Transpennine Route Upgrade and Electrification updates

Legolash2o

Member
Joined
27 Sep 2018
Messages
687
5 years 5 months!!!


I assume because of the massive -14 weeks iirc- closure and diversions with Leeds Neville Hill? Also all the level crossings being closed.
Is Leeds Neville Hill a big change? I always think back to the videos where they blitz a place in a 48-72 hour run when I think about timeframes. Just have to remember that not all projects are like that.

Hopefully someone somewhere has been doing some supply chain planning and has noticed that there's 140 miles of HS2 that will need electrification resource in the not too distant future.
Ooo, good point!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,525
Location
Preston Lancs
W3 – Huddersfield to Ravensthorpe
- Significant works to provide a four-track railway providing additional capacity, linespeed improvements and removing conflicting train movements.
- New stations at Ravensthorpe, Mirfield, Deighton.
- Major enhancement to Huddersfield Station
- Resignalling works (Digital ready)
-Track & drainage renewals
-Electrification between Huddersfield and Ravensthorpe
-New Power supply
-Major bridge strengthening, bridge renewals, retaining walls and earth works.
- Mining remediation
- Creation of new sidings at Hillhouse and temporary station to support disruption
Discharge of consents associated with TWAO.
EIS Infrastructure Authorised Feb-30 n/a – project is on target On target

So some (but not all ) of the difficult bits.
 

class26

Member
Joined
4 May 2011
Messages
1,199
Hopefully someone somewhere has been doing some supply chain planning and has noticed that there's 140 miles of HS2 that will need electrification resource in the not too distant future.
The difference being HS2 will not have trains running, the benefit of new build
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,341
Location
Nottingham
The difference being HS2 will not have trains running, the benefit of new build
It will relieve some constraints, but not others.
  • If the factor limiting construction is the number of hours in possession, then sure, you can work 24 hours a day on HS2.
  • If the limiting factor is the number of qualified and experienced staff available, then they can still only work 8 hour shifts - during the day on HS2 instead of during the night on TRU. Same for design engineering expertise.
  • Similarly, if the constraint is the capacity to manufacture the steelwork and the fittings, especially if there is a requirement for them to be made in the UK.
  • Or, even more likely, the rate at which the Treasury is willing to spend the money. HS2 have been told to slow down spending on phase 1 and push it back into later financial years wherever they can.
 

Geogregor

Member
Joined
16 Sep 2016
Messages
458
Location
London
About works at Huddersfield:


Huddersfield-station-roof-upgrade.jpg
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,605
It will relieve some constraints, but not others.
  • If the factor limiting construction is the number of hours in possession, then sure, you can work 24 hours a day on HS2.
  • If the limiting factor is the number of qualified and experienced staff available, then they can still only work 8 hour shifts - during the day on HS2 instead of during the night on TRU. Same for design engineering expertise.
  • Similarly, if the constraint is the capacity to manufacture the steelwork and the fittings, especially if there is a requirement for them to be made in the UK.
  • Or, even more likely, the rate at which the Treasury is willing to spend the money. HS2 have been told to slow down spending on phase 1 and push it back into later financial years wherever they can.
On your second point, it does mean that they can work a) without having to spend time getting the equipment out and putting it back every time and b) can work during the day as you say, which is both more productive as it's light and doesn't put people off doing the job!
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
On your second point, it does mean that they can work a) without having to spend time getting the equipment out and putting it back every time and b) can work during the day as you say, which is both more productive as it's light and doesn't put people off doing the job!
Must be a risk to NR electrification that HS2 will be offering daytime work which will be more attractive
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,264
Must be a risk to NR electrification that HS2 will be offering daytime work which will be more attractive
The HS2 work won't be on a live railway hence opening much of the work (mast bases and mast erecting with no track in place) to much larger pool of people who don't have to have training to work on a live railway or be able to use RRVs. This was useful cost reducer in French, German and Austrian HS new build.
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
The HS2 work won't be on a live railway hence opening much of the work (mast bases and mast erecting with no track in place) to much larger pool of people who don't have to have training to work on a live railway or be able to use RRVs. This was useful cost reducer in French, German and Austrian HS new build.
Does that apply under a blockade, or does the existence of track mean RRVs and therefore live railway?
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,929
Location
Mold, Clwyd
Must be a risk to NR electrification that HS2 will be offering daytime work which will be more attractive
For what it's worth the HS2 electrification contract has gone to Colas, which doesn't clash with the current NR contracts.
But the project work force is probably quite mobile, of course.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,692
Location
Nottingham
None of this is esoteric work and be interesting if we had some bold leadership to put down a challenge to accelerate by 12-24mths how much money would actually be saved by avoiding all the overheads.
The workforce and equipment hours on the ground will be about the same in real terms whether it's done quickly or slowly. Going quickly avoids all the prolongation costs of keeping the management and admin running for a longer period, but incurs extra costs to mobilise more crews, more plant and more or larger bases for them to work from.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
8,029
Location
Surrey
The workforce and equipment hours on the ground will be about the same in real terms whether it's done quickly or slowly. Going quickly avoids all the prolongation costs of keeping the management and admin running for a longer period, but incurs extra costs to mobilise more crews, more plant and more or larger bases for them to work from.
Depends on the utilisation of those resources though and i do wonder whether we strike the right balance on access on a job of this scale. I know they have some blockades you do have to wonder though given the investment in getting route knowledge built up for diversionary routes the use of more blockades would see the project delivered quicker without having to overload the supply chain.
 

darylyates17

Member
Joined
8 Nov 2015
Messages
489
Location
St Helens
I’ve not checked this for a while so I don’t know if anything has changed but will the NLW platform extensions be complete for the December time table change? (will the software be finally updated for LEG to allow all doors to open as well?) Also will the 802s run on Electric in between MCV and SYB from the 15th too.
 
Joined
8 Feb 2021
Messages
1,060
Location
Manchester
I’ve not checked this for a while so I don’t know if anything has changed but will the NLW platform extensions be complete for the December time table change? (will the software be finally updated for LEG to allow all doors to open as well?) Also will the 802s run on Electric in between MCV and SYB from the 15th too.
Yes NLW extensions finished now just awaiting approval

Lea Green opens all 5 as of last Sunday

APCO will occur at Clayton Viaduct from December 1st
 

childwallblues

Established Member
Joined
3 Jul 2014
Messages
3,863
Location
Liverpool, UK
I’ve not checked this for a while so I don’t know if anything has changed but will the NLW platform extensions be complete for the December time table change? (will the software be finally updated for LEG to allow all doors to open as well?) Also will the 802s run on Electric in between MCV and SYB from the 15th too.
As far as I am aware the Liverpool to Newcastle services will except for the odd service no longer call at Stalybridge from the new timetable so will remain on diesel from Manchester to York. Some Liverpool to Hull services will be operated by Class 802s so there is a possibility that these services will operate on electric power from Liverpool to Stalybridge.
 
Joined
8 Feb 2021
Messages
1,060
Location
Manchester
As far as I am aware the Liverpool to Newcastle services will except for the odd service no longer call at Stalybridge from the new timetable so will remain on diesel from Manchester to York. Some Liverpool to Hull services will be operated by Class 802s so there is a possibility that these services will operate on electric power from Liverpool to Stalybridge.
APCO at Clayton Viaduct for all 802s via Mainline, at Victoria for services via Calder Valley
 

WAO

Established Member
Joined
10 Mar 2019
Messages
1,230
As changeover either side of the Pennines is to be temporary, does it really matter?

WAO
 

richard_S

Member
Joined
15 Oct 2018
Messages
140
On any of the transpennine routes if there is a large blockade O/H line equipment should be put in after a few years it will all join up. Hope valley comes to mind!
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,525
Location
Preston Lancs
Yes, January 2027 on the face of it seems quite a longtime, but they are making better progress than I originally thought. Great stuff.
 