The lines quoted are at least approximately "ready" in that they are close to new auto transformer grid supply points with some spare capacity. They are the most expensive and long lead items. The lines are short so even full GRIP planning should be in months not years. Finally, NR, for all it's problems, has been on a painful learning curve so is now able to manage projects and technical problems (such as clearances and ROCS) much better.
Didn't Railtrack do Crewe Alsager (8 miles) in 10 months?
Can do or can't do?
WAO
Crewe - Alsager was easier to electrify as 3 miles of it was (and still is) single track, so there were less structures to install.
And vis-a-vis the grid supply points (and autotransformers), most new commuter corridors have been
boosterless classic (e.g. EGIP, SDA, Reading - Newbury, Walsall - Rugeley, Barnt Green - Bromsgrove, Preston - Blackpool, Roby - Wigan NW), more often than not due to the fact that ATF isn't required for the service levels - AT electrified systems require less feeder stations overall, but they also need AT sites at regular intervals, which can add to the cost.
(The Berks & Hants Line was originally due to get ATFs too, but this was descoped to boosterless classic)
GWML, South Wales, Liverpool - Manchester, Manchester - Euxton Jn have all been ATF. In the case of the Western route, the sheer number of intercity/commuter trains, plus the scope for freight in the future meant ATF was a better bet. This also applied to the North West schemes, but for them, they also used the existing WCML ATF supply between Weaver & Euxton Jns until they got Heyrod ATFS online (via the 'Great Extension Lead' - a cabled ATF supply between Heyrod & Man Vic, oft referred to in the now-closed Blackpool - Manchester electrification thread). They also have potential for intercity electric trains, rather than just commuter ones.
Although I'm not a betting man, I'll hedge my bets on TransPennine (via Huddersfield) being ATF. But York - Church Fenton remains an enigma, as the scope of Phase 2 of the ECML Power Supply Upgrade has yet to be agreed. ATF would be likely, but it isn't certain.