Good morning everybody

I've seen this job posted on several different TOC websites and wanted to know whether any members on this forum work in this field as I'm interested in learning more about this job?

From what I've read there are different types of train planning both short and long term and that they're responsible for timetable amendments for planned engineering works and disruptions, is that right? Any further information would be appreciated. I couldn't find much info from the forum search,Thanks
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

HLE

Established Member
Joined
27 Dec 2013
Messages
1,421
I believe 'The Planner' on here is one, but I could be wrong.
 

306024

Established Member
Joined
23 Jan 2013
Messages
3,974
Location
East Anglia
Looks like nobody knows ;)

There are all sorts of 'planning' tasks, either at the Network Rail HQ in Milton Keynes or in any of the TOCs.

The permanent timetable is surprisingly a small part of the work. There are far more staff employed to alter it, whether for engineering work, Bank Holidays or special events, than it takes to compile the base timetable in the first place.

So generally you cut your teeth on special traffic planning, producing altered schedules, which takes place at both NR and in the TOC, or if you are in a TOC producing altered unit and train crew diagrams. The more senior staff tend to do the permanent timing and diagramming.

How the planning task is tackled varies depending on where you are in the country. TOCs with intensive services tend to take the lead in timetabling where as long distance TOCs rely more on NR planners threading their trains across the network. At the end of the day NR are responsible for the final timetable so you don't always get exactly what you want as they have to consider all operators.

Freight planning is similar, but due to the nature of the business much of it is short term planning, Freightliner container traffic is the nearest you come to a permanent timetable.

To find out more contact your local TOC or NR if you're near MK (Mid Bedfordshire looks close enough) and see if you can arrange to visit a planning office, even if they are not advertising. All the planning offices I've ever dealt with have been most welcoming.
 
Last edited:

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,631
I am, though many may disagree! Can't add much more than above. NR don't do any diagramming at all and at some busy terminii the signallers often sort out the platforming too. It can be as quick as day A for C planning right out to LTP timetable where you have a few months to do it. Unless you are looking at the short term freight or a rolling spot bid you also tend to stick to a geographic area within NR. There is always recruitment going on in MK for planners so if you have got the aptitude for it then make contact.
 

gji

New Member
Joined
6 Aug 2015
Messages
3
I have recently started working for a long distance TOC in train planning. I'm generally new to the industry and have been enjoying the work so far.

I think what's been posted already covers it pretty well, but I'm happy to answer any specific questions if you PM me.
 