TPE Mark 5A coaching stock progress

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

VauxhallNova

Member
Joined
15 Jan 2021
Messages
191
Location
UK
The number of faults and failures occurring on a daily basis, with only 4 out of 13 sets in passenger service each day, tells a different story. I shudder to think what would be happening right now if the fleet were fully deployed.

There is a huge amount of work yet to be done by CAF, both technically and organisationally, before the entry into service can be considered complete.

I beg to differ. I assume you have not been involved in introducing a fleet of new trains...

What is needed is a good shake down which would normally occur in the first months of squadron deployment. Utilisation of a few sets per day, as has been the case since introduction in August 2019, especially only covering a small number of miles, makes this incredibly difficult.

There is somewhat of a split between TPE operational staff who want to be using the things, and some at head office who have always been much less keen.
 
Last edited:

tpjm

Member
Joined
25 Jan 2019
Messages
487
Location
The North
I don’t think that’s a fair comment to be honest. There are lots of colleagues at HQ working tirelessly on the fleet, and as indicated in my earlier post, it makes their lives easier when more sets are in traffic and clocking up more mileage.

The biggest blocker to full deployment has been competent train crew, not least because of COVID. The question back in 2019 when the resource base started to get tight was very much “which fleet is most critical to the operation?” - across the core route, it was the 802 that won as it was required for the extensions to Edinburgh.

The key thing to note is that Watershed’s comments about a lack of working sets is pure fiction.
 

185

On Moderation
Joined
29 Aug 2010
Messages
5,709
I note he does say 'some' at head office... I don't doubt the vast majority in Bridgewater House want to see these sets being used to their full potential, however there are those in the wonderful Ops Standards & Safety seemingly risk assessing the risk assessment of a risk assessment to justify their department's budget... as is the case at most other operators. The question should be asked, how did the (swift) rollout of the 185 crew training differ from the rollout with these? What extra levels of 'ops standards & safety signing stuff off' are slowing this process down?
 

Class455

Established Member
Joined
19 May 2016
Messages
1,519
The answer to this question might be a bit of a long shot at the moment, but is there any indication on when Nova 3's will start appearing on Redcar Central/Saltburn diagrams? Are they even cleared to run to Saltburn once the Redcar services extend in May?
 

Watershed

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
26 Sep 2020
Messages
16,592
Location
UK
The answer to this question might be a bit of a long shot at the moment, but is there any indication on when Nova 3's will start appearing on Redcar Central/Saltburn diagrams?
Nothing in the public domain yet. And certainly nothing planned for the Dec TT.

Are they even cleared to run to Saltburn once the Redcar services extend in May?
Yes, in fact it's the 185s that aren't cleared to Saltburn yet!

The key thing to note is that Watershed’s comments about a lack of working sets is pure fiction.
I must be imagining the number of cancellations, delays and shortforms blamed on faulty sets/locos, plus the near bottom of the table MTIN. In several cases there has apparently been no working substitute available.

It's hardly a surprise when Longsight only have 2 sets not in traffic, and until (unless?) reliability increases, it will remain a problem as there isn't the space for Longsight to store any more spares.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
The answer to this question might be a bit of a long shot at the moment, but is there any indication on when Nova 3's will start appearing on Redcar Central/Saltburn diagrams? Are they even cleared to run to Saltburn once the Redcar services extend in May?
Not currently route cleared. Requires track and platform works - tamping, coper adjustments - which are currently underway. Including at stations along the line which will not feature a passenger stop but the carriages would otherwise foul.
 

class 9

Member
Joined
18 Nov 2010
Messages
1,073
I note he does say 'some' at head office... I don't doubt the vast majority in Bridgewater House want to see these sets being used to their full potential, however there are those in the wonderful Ops Standards & Safety seemingly risk assessing the risk assessment of a risk assessment to justify their department's budget... as is the case at most other operators. The question should be asked, how did the (swift) rollout of the 185 crew training differ from the rollout with these? What extra levels of 'ops standards & safety signing stuff off' are slowing this process down?
The swift roll out of 185 would of happened as it's a DMU, the training would just be a conversion course, as these are loco hauled, a completely different type of train, it would be a full training course.
 

tpjm

Member
Joined
25 Jan 2019
Messages
487
Location
The North
I must be imagining the number of cancellations, delays and shortforms blamed on faulty sets/locos, plus the near bottom of the table MTIN. In several cases there has apparently been no working substitute available.

That is not the same as your earlier comment which implied that there are rakes of coaches sitting at Longsight or some questionable siding awaiting CAF attention before they can be used. If that were the case, sets would not be travelling backwards and forwards across the Pennines behind a Class 37 as part of their maintenance cycles.

From recent experience, I would be inclined to suggest that the Mk5a/68 have seen no more technical/unit faults in the past few weeks than the Class 185 fleet. The key difference is that Class 185 failures can be mitigated relatively easily whilst the current Mk5a diagrams make it incredibly difficult. The primary objective of the control office is to keep some form of service running and if that means short forming a Redcar circuit, then so be it; running 3x6 and 3x5 is better than a cancellation. The attention then turns to exploring what can be done for later in the day, but being able to find a Driver, prepping a unit and tripping it across the country as an ECS in order to slot it back into diagram is just not realistic.
 
Last edited:

AM9

Veteran Member
Joined
13 May 2014
Messages
16,022
Location
St Albans
From recent experience, I would be inclined to suggest that the Mk5a/68 have seen no more technical/unit faults in the past few weeks than the Class 185 fleet.
That's a terrible endightment of a new design of hauled coaches, justifying their poor number of faults by comparing them with self-powered multiple units.
 

PennineSuperb

Member
Joined
8 Jun 2018
Messages
97
Not currently route cleared. Requires track and platform works - tamping, coper adjustments - which are currently underway. Including at stations along the line which will not feature a passenger stop but the carriages would otherwise foul.
This is unfortunately incorrectly. The work that has been underway (completed 14/11/21) was to make the necessary adjustments for Class 185 traction. Class 68’s & Mk5A are route cleared and have already completed the internal station verification works. Class 185’s have not, and this can not be completed until the correct paperwork is agreed between NR & TPE.
 

tpjm

Member
Joined
25 Jan 2019
Messages
487
Location
The North
That's a terrible endightment of a new design of hauled coaches, justifying their poor number of faults by comparing them with self-powered multiple units.
As you’ll note, I was referring to the loco AND coaches. You’ll also know that the Mk5a are not “just” coaches as they have plenty of technical complexity. They might as well be a MU, if not for the lack of a power train.

I was also not comparing them like for like, merely highlighting that their failure is more difficult to mask than that of a Class 185. It’s not a question of the rolling stock, it’s a statement about the current operational constraints of both fleets.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
This is unfortunately incorrectly. The work that has been underway (completed 14/11/21) was to make the necessary adjustments for Class 185 traction. Class 68’s & Mk5A are route cleared and have already completed the internal station verification works. Class 185’s have not, and this can not be completed until the correct paperwork is agreed between NR & TPE.
Apologies if I've misunderstood.
Mark 5a's, according to the sectional appendix, are not fully route cleared. There are 4 listed restrictions relating to deflated suspension (Redcar East Up, Longbeck Down, Markse Down and Saltburn P2). Equally the 185s are restricted here too.
Volker were tamping at Redcar East and Longbeck earlier this month.
It seems like a slight misunderstanding since the work completion and corresponding update to SA.
 

37424

Member
Joined
10 Apr 2020
Messages
1,064
Location
Leeds
The answer to this question might be a bit of a long shot at the moment, but is there any indication on when Nova 3's will start appearing on Redcar Central/Saltburn diagrams? Are they even cleared to run to Saltburn once the Redcar services extend in May?
I thought the view now was they wern't going to be used on Redcar services but on South Transpennine Services instead, in any case if they do get there I'm sure the local's will love the noise not!
 
Last edited:

matacaster

On Moderation
Joined
19 Jan 2013
Messages
1,646
Location
Huddersfield
I thought the view now was they wern't going to be used on Redcar services but on South Transpennine Services instead, in any case if they do get there I'm sure the local's will love the noise not!
I have often wondered if the incredible noise level from these beasts was intended to make the placing of lookouts on possessions umnecessary. Is there a maximum DB limit for locos?
 

47827

Member
Joined
3 Mar 2020
Messages
591
Location
Middleport
I have often wondered if the incredible noise level from these beasts was intended to make the placing of lookouts on possessions umnecessary. Is there a maximum DB limit for locos?

The team who were signing them off at DRS when they were about to be built were satisfied with the noise aspects of the design, although better silencing could have been considered as per other classes that were built in the decades before. At the time it certainly wasn't an issue but the TPE lease work thrown a few spanners in the works following complaints at Scarborough.
 

Greybeard33

Established Member
Joined
18 Feb 2012
Messages
4,335
Location
Greater Manchester
As you’ll note, I was referring to the loco AND coaches. You’ll also know that the Mk5a are not “just” coaches as they have plenty of technical complexity. They might as well be a MU, if not for the lack of a power train.
Which begs the question, what proportion of the failures are attributed to the loco? I have not seen any complaints about the reliability of 68s hauling Mk2 or Mk3 coaches, e.g. at Chiltern.
 

matacaster

On Moderation
Joined
19 Jan 2013
Messages
1,646
Location
Huddersfield
The team who were signing them off at DRS when they were about to be built were satisfied with the noise aspects of the design, although better silencing could have been considered as per other classes that were built in the decades before. At the time it certainly wasn't an issue but the TPE lease work thrown a few spanners in the works following complaints at Scarborough.
Perhaps DRS team had hearing impairment or listening to iTunes?
 

47827

Member
Joined
3 Mar 2020
Messages
591
Location
Middleport
Perhaps DRS team had hearing impairment or listening to iTunes?

Some of the engineering guys had a great liking of noisy English Electric traction so I doubt drowning out noise would have been high on the list of concerns. Although I would never chase the things it's certainly noticeable they sound a little more lively than most stuff built since the 1980s.
 

Mollman

Established Member
Joined
21 Sep 2016
Messages
1,701
Location
Preston
I thought the view now was they wern't going to be used on Redcar services but on South Transpennine Services instead, in any case if they do get there I'm sure the local's will love the noise not!
That was only if TPE took over Liverpool - Nottingham services I believe
 

47827

Member
Joined
3 Mar 2020
Messages
591
Location
Middleport
That was only if TPE took over Liverpool - Nottingham services I believe

There was a recent press announcement suggesting the new Liverpool to Cleethorpes route would eventually share the sets with Scarborough diagrams so that no sets would overnight at Scarborough any longer. Both routes would also retain 185 diagrams. What happens before that, if anything, I'm not aware of. Don't think there is any significant change in use from December though other than an extra couple of trains running between Scarborough and Liverpool plus the rest predominantly running to Manchester or Stalybridge instead of simply forming shuttles to York (Sundays unchanged from now).
 

CHAPS2034

Member
Joined
13 Mar 2018
Messages
644
That's not long ago passed me at Leeds. 2x sets being hauled by 37611 in europhoenix livery and coupled to the blunt end of the first rake. So answers that question.....
Reported as sets TP06 and TP10

In another empty stock move today 68029 is moving TP08 from Longsight to Gascoigne Wood

 

Fokx

Established Member
Joined
19 Jul 2019
Messages
1,598
Location
Liverpool
That was only if TPE took over Liverpool - Nottingham services I believe
Nope.

2x Liverpool to Cleethropes diagrams from May 2022
6x Liverpool to Cleethorpes diagrams from Dec 2022

== Doublepost prevention - post automatically merged: ==
 

xotGD

Established Member
Joined
4 Feb 2017
Messages
7,827
Nope.

2x Liverpool to Cleethropes diagrams from May 2022
6x Liverpool to Cleethorpes diagrams from Dec 2022

== Doublepost prevention - post automatically merged: ==
Do you also happen to know how many Scarborough diagrams from those dates?
 