TPE Mark 5A coaching stock progress

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Ben Bow

Member
Joined
20 Sep 2018
Messages
342
Given that the fault free running hasn't started yet, and that testing is still ongoing, any entry to service dates given are "aspirational" rather than set in stone. The whole project has seen target dates come and go regularly. Building work on the depot at Scarborough has barely started, for example.
 

coxxy

Member
Joined
16 Aug 2013
Messages
375
Today’s update:

New brake valves have cured the sudden stop issue below 8mph.

CAF are happy with this but more testing is required just to be sure, hence the test runs back on in earnest.

Should be some test runs on the North route ‘soon’ to see how the full sets perform over the hills (shouldn’t be any issues with that compared to a 185 either).

Can’t say more even though I have more info about other stuff (current planned further crew training and then fleet coming into service dates were talked about but it’s not my job to disclose and certainly not on here).

Sounds like a very promising update!
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
Given that the fault free running hasn't started yet, and that testing is still ongoing, any entry to service dates given are "aspirational" rather than set in stone. The whole project has seen target dates come and go regularly. Building work on the depot at Scarborough has barely started, for example.

The first set reportedly has to do 4500 miles fault free before it is accepted. Considering a major fault was discovered before fault free running even commenced I share your scepticism.
 

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
4500 mike's? That's a lot longer than I have read for other new trains. I'm sure I read for the 385s it was 2500 km.
 

Jonny

Established Member
Joined
10 Feb 2011
Messages
2,577
Given that the fault free running hasn't started yet, and that testing is still ongoing, any entry to service dates given are "aspirational" rather than set in stone. The whole project has seen target dates come and go regularly. Building work on the depot at Scarborough has barely started, for example.

The first set reportedly has to do 4500 miles fault free before it is accepted. Considering a major fault was discovered before fault free running even commenced I share your scepticism.

A couple of questions:

What is the difference between testing and designated fault-free running (other than the need to accumulate fault-free mileage in the latter)?

Could a test run count towards fault-free mileage if the train operates properly over the required distance?
 

BMIFlyer

Member
Joined
13 Mar 2017
Messages
723
Office of Road and Rail has now approved the MK5A sets for use, meaning test runs on the core route can begin.
 

mikemcniven

Member
Joined
13 Aug 2016
Messages
381
Location
Manchester
Last edited:

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,855
Location
Beeston (Notts)
Indirectly related to the Mk5a stock: TPE no. 68030 has now been named "Black Douglas" without ceremony at Crewe Gresty Bridge, continuing the trend of 68s bearing the same nameplate as their "numbersake" (if you'll pardon the vernacular) in the Class 87 range; 87030 last carried the name.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
19,347
Location
Yorkshire
Indirectly related to the Mk5a stock: TPE no. 68030 has now been named "Black Douglas" without ceremony at Crewe Gresty Bridge, continuing the trend of 68s bearing the same nameplate as their "numbersake" (if you'll pardon the vernacular) in the Class 87 range; 87030 last carried the name.
The vernacular is fine! I'd like to see 68034 as "Pride in Huddersfield" (previously carried by 47434).
 

TRAX

Established Member
Joined
2 Dec 2015
Messages
1,811
Location
France
A couple of questions:

What is the difference between testing and designated fault-free running (other than the need to accumulate fault-free mileage in the latter)?

Could a test run count towards fault-free mileage if the train operates properly over the required distance?

Testing involves much more than just running. One aspect of testing can be voluntarily ´creating’ issues on the train, which in itself is the complete opposite of ‘fault-free running’.
 

Dunnyrail

Member
Joined
26 Oct 2017
Messages
151
Good to see that testing for Fault Free has started, but with those limited distances except for the Liverpool run 4500 miles will take a while. But I expect that there will soon be a Scarborough and return or two which should start to ramp up the miles nicely.
 

SP Man

Member
Joined
26 Aug 2018
Messages
146
Good to see that testing for Fault Free has started, but with those limited distances except for the Liverpool run 4500 miles will take a while. But I expect that there will soon be a Scarborough and return or two which should start to ramp up the miles nicely.
Fault free testing has not started, these are Customer specific testing aimed to check stop boards, stepping heights, ramp heights, etc.
 

Dunnyrail

Member
Joined
26 Oct 2017
Messages
151
Fault free testing has not started, these are Customer specific testing aimed to check stop boards, stepping heights, ramp heights, etc.
Oh my mistake, I took post 1869 and the turns listed in the next post to mean that these would be the start of such testing. Perhaps someone ‘in the know’ can say when that particular clock is running?
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
7,321
The first set reportedly has to do 4500 miles fault free before it is accepted.

Fault free testing has not started...
I reckon that Manchester - Bletchley - Carlisle -Bletchley- Manchester is about 840 miles, so 4500 miles is a bit more than 5 of those trips... Doing one a night could almost get it sorted in a week, that's if drivers are available. I suppose as they are ECS then freight drivers could be hired, also no guards would be needed, but I imagine someone technical or otherwise able to report on the customer experience will be needed. Being optimistic, can we hope for one in service within a couple of months (assuming the technical glitches have been sorted now)?
How much pre-service running will the subsequent sets have to do?
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
I reckon that Manchester - Bletchley - Carlisle -Bletchley- Manchester is about 840 miles, so 4500 miles is a bit more than 5 of those trips... Doing one a night could almost get it sorted in a week, that's if drivers are available.
They could but that is no guarantee they will. There is a huge amount of rose tinted specs stuff on this forum. This could happen or that could happen. Could doesn’t mean will.

I wouldn’t expect any of the people who are involved in the project who contribute to this thread to comment but I expect they were pretty surprised that a train that has undergone months of testing at Velim had braking problems when tested over here. That isn’t a good omen but we can only hope it is an isolated issue and others don’t crop up.
 

Greybeard33

Established Member
Joined
18 Feb 2012
Messages
4,335
Location
Greater Manchester
There's now going to be longer turnarounds at the Airport too, also enabling services not be be terminated at Victoria or Pic - although PPM will still struggle given the Oxford Road corridor.
A temporary fix as they are mixing the Middlesbrough and Newcastle diagrams up, which of course once the new trains come in can’t happen as 68s aren’t going to Newcastle and 802s aren’t going to Middlesbrough.
Looking at Manchester Airport platform allocations since the timetable change (see e.g. http://www.realtimetrains.co.uk/search/advanced/MIA/2018/12/14/0600-2000?stp=WVS&show=all&order=wtt), it can be seen that the 40 minute turnrounds are being squeezed in by platform double occupancy. Another train comes in behind the 185 and departs first. But the Airport platforms are only 200m long, so a Mk5A set or 802 will need a whole platform to itself. This means it will be necessary to go back to 10 minute turnrounds as and when the new trains are introduced on the Airport services.

It appears TPE is "between a rock and a hard place". Either keep using overcrowded 3-car 185s with long turnrounds, or risk PPM nosediving again when the Mk5As start running to the Airport.
 

BMIFlyer

Member
Joined
13 Mar 2017
Messages
723
Looking at Manchester Airport platform allocations since the timetable change (see e.g. http://www.realtimetrains.co.uk/search/advanced/MIA/2018/12/14/0600-2000?stp=WVS&show=all&order=wtt), it can be seen that the 40 minute turnrounds are being squeezed in by platform double occupancy. Another train comes in behind the 185 and departs first. But the Airport platforms are only 200m long, so a Mk5A set or 802 will need a whole platform to itself. This means it will be necessary to go back to 10 minute turnrounds as and when the new trains are introduced on the Airport services.

It appears TPE is "between a rock and a hard place". Either keep using overcrowded 3-car 185s with long turnrounds, or risk PPM nosediving again when the Mk5As start running to the Airport.

You could have a Mk5A set and a class 156 on platform 4 if necessary.
 

driver9000

Established Member
Joined
13 Jan 2008
Messages
4,557
You could have a Mk5A set and a class 156 on platform 4 if necessary.

The Local instruction for the Airport says that if a train more than 4 vehicles in length is in the platform then another train can't be signalled into it. It doesn't say platform 4 is exempt from that.
 

SP Man

Member
Joined
26 Aug 2018
Messages
146
Oh my mistake, I took post 1869 and the turns listed in the next post to mean that these would be the start of such testing. Perhaps someone ‘in the know’ can say when that particular clock is running?
It's not started on any of the sets yet, a couple of issues being sorted. Some tests at Velim would not show up issues becsuaexof what it does there (A lot of slow speed is done by being dragged around and the running and braking doesn't fully show up actual braking). I doubt it will not be long before a couple of the sets (6+9) will be ready to start FFR. Only the first 1 or 2 need the 4500 miles.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
With a uniform fleet, TPE could at least interwork the diagrams to optimise the layover at the Airport.
But with 3 different types of route-specific 5-car stock using it, plus probably 6-car TP South workings with 185s, there's no chance of doing that.
 