RTT is still showing a regular through service from Paddington at Bedwyn in the May timetable. Take it that isn't right?
RTT is still showing a regular through service from Paddington at Bedwyn in the May timetable. Take it that isn't right?
I have heard that from two independent GWR sources on the basis that DfT want the HSTs withdrawn ASAP.
Are the HSTs actually unsafe / 'unrailworthy' ?
But that's the very idea. Replaced by 5-car IETs cascaded due to service cuts elsewhere. That's what's proposed.Is it really a good idea to recommend withdrawal of stock when there is nothing to replace them without poaching stock from other lines?
And the DfT is demanding significant savings this year.No, but they are incredibly expensive to run.
But that's the very idea. Replaced by 5-car IETs cascaded due to service cuts elsewhere. That's what's proposed.
== Doublepost prevention - post automatically merged: ==
And the DfT is demanding significant savings this year.
Apart from staffing, which is obviously best avoided, the only other way is to withdraw whole batches of the rolling stock. That's where the HSTs come in.
Yes, all day through services to Bedwyn since 1993, not every hour at first though and they ran semi-fast east of Reading.But if the price of removing the HSTs is cutting services like the Bedwyn, which has been going since the early (?) 90s...
With respect, it doesn't have a "sole purpose", seeing as it provides the only regular rail link that the residents of Bedwyn, Hungerford & Kintbury have, and is a substantial part of the regular daytime service that Newbury, Thatcham & Theale have. That's a good few people, and they don't all want to go to London every time!Given that the sole purpose of this train is to connect towards London (literally nobody is going to be doing Bedwyn-Hungerford, they'll just drive) then clearly it should be treated as one train for connection purposes, i.e. always held.
I think we all hope that. Question is what does the Treasury want? It could very want a permanently slimmed down railway with passenger demand tempered through high fares and infrequent services, BR-style.I guess the hope is that these are all temporary arrangements for this economically-tight period and things will improve again in a few years.
Presumably whatever it thinks will cost it the least overallI think we all hope that. Question is what does the Treasury want? It could very want a permanently slimmed down railway with passenger demand tempered through high fares and infrequent services, BR-style.
What an absolute mess. Having just visited the GWR coffee shop portal there is a very informative report from the Bedwyn users group of their meeting with GWR. It seems the new bi mode 800s are being relocated to a non electrified part of the network you couldn’t make it up.Presumably whatever it thinks will cost it the least overall![]()
Hardly. They are just allocating expensive resources to another part of the network to remove traction that is expensive to operate, and making more all day use of the Turbo allocated to peak time workings west of Newbury.What an absolute mess.
Well, if they're used on the Cardiff-Taunton route then i would have thought they will pan up between somewhere around Pilning through to Cardiff?What an absolute mess. Having just visited the GWR coffee shop portal there is a very informative report from the Bedwyn users group of their meeting with GWR. It seems the new bi mode 800s are being relocated to a non electrified part of the network you couldn’t make it up.
The IETs cost a lot more to lease but they are locked into them through a 27.5yr lease agreement whereas the HSTs will be on a lease matched to current agreement at worse. Presumably a whole load more driver training will be required if they move West and given they don't like the sea at Dawlish not exactly a smart move.But that's the very idea. Replaced by 5-car IETs cascaded due to service cuts elsewhere. That's what's proposed.
== Doublepost prevention - post automatically merged: ==
And the DfT is demanding significant savings this year.
Apart from staffing, which is obviously best avoided, the only other way is to withdraw whole batches of the rolling stock. That's where the HSTs come in.
Not sure about driver training. A lot of drivers already drive both.The IETs cost a lot more to lease but they are locked into them through a 27.5yr lease agreement whereas the HSTs will be on a lease matched to current agreement at worse. Presumably a whole load more driver training will be required if they move West and given they don't like the sea at Dawlish not exactly a smart move.
I have heard that from two independent GWR sources on the basis that DfT want the HSTs withdrawn ASAP.
Thanks for the clarification. That makes sense.They're not going ASAP, but certainly yes, the DfT are accelerating their plans to look at options for withdrawing HSTs / Castle Class 255s perhaps sooner than anticipated. As stated above, they're getting quite expensive and are approaching the other half of a "U" shaped curve as they start to reach areas of obsolescence.
These haven't gone yet for SWR - the timetable for my local line (Weymouth - London) is still showing the connections to stations where the train doesn't stop, e.g. a connection to Woking from the semi-fast, to Basingstoke and Clapham Junction from the last, or to Woking and London Waterloo from an XC service.Remember when connecting times were shown in the timetable in italic type? Those have gone too.
Having just visited the GWR coffee shop portal there is a very informative report from the Bedwyn users group of their meeting with GWR. It seems the new bi mode 800s are being relocated to a non electrified part of the network you couldn’t make it up.
I think the issue is GWR don’t really have enough stock to extend the service due to the 769s being delayed and therefore the Turbos are stuck at Reading. Also Westbury is congested at the best of times, a fourth platform would probably be required - there is space for it but it would be quite expensive for probably little reward.Perhaps even a Westbury-Reading 1tp2h service might be useful for maintaining connectivity on either end - yes many fast London services to jump onto, but to other places and for Reading access itself - and Westbury as a mini-hub westward. Plus local journeys between the towns, and either side of Newbury too.
I’m quite surprised they didn’t just wire to Bedwyn the first time round, to be honest!
I'm no expert, but that's the pertinent question in my mind as well.
== Doublepost prevention - post automatically merged: ==
**Edit** Having just read the "Bedwyn Trains Passenger Group" notes, they haven't exactly done themselves and favours in the NIMBY stakes. Shades of Steventon:
"1. Extend electrification to Bedwyn: This was something we didn’t champion. BTPG have always been very cautious about bringing the ugly overhead wires and gantries through the Kennet Valley.
2. The bi-mode IET solution: This was the one that was implemented and we thought would be with us for many years.
3. Kitting the Class 387 trains with batteries so they could run onto Bedwyn. GWR were seriously considering this before going for option 2."
My bold.
You could copy and paste #1 and replace Bedwyn with "Bath" and Kennet Valley with "Avon Valley"...
This is something on the lines (no pun intended) that I had in mind further up the thread, using as little as possible and getting the best use out of it whilst providing some sort of service.Perhaps even a Westbury-Reading 1tp2h service might be useful for maintaining connectivity on either end - yes many fast London services to jump onto, but to other places and for Reading access itself - and Westbury as a mini-hub westward. Plus local journeys between the towns, and either side of Newbury too.
There's overhead wires going up the Aire Valley (well as far as Skipton) which is equally picturesque, so why can't overheads go through the Kennet Valley? The attitude of the Bedwyn Trains Passenger Group regarding the installation of the overheads comes across to me as a group whose intent on stagnating their own rail service who'll then complain to GWR that they've lost their rail service entirely because there's no suitable stock to run it. I think they, the BTPG, would have a melt down if rail replacement buses / peasant wagons were ever to be suggested.Having just read the "Bedwyn Trains Passenger Group" notes, they haven't exactly done themselves and favours in the NIMBY stakes. Shades of Steventon:
"1. Extend electrification to Bedwyn: This was something we didn’t champion. BTPG have always been very cautious about bringing the ugly overhead wires and gantries through the Kennet Valley.
With hindsight, perhaps the terminus of the Paddington outer suburban service should have been Marlborough!
Although unlike the situation in both Bristol and Oxford, I am unaware of a major Bedwyn remodelling project which is far more sensibly done before electrification than immediately after.Indeed, indeed.