Thameslink/ Class 700 Progress

Status
Not open for further replies.

APUK002

Member
Joined
26 Dec 2016
Messages
315
They're being delivered through the Chunnel.



I think it got to either Fréthun or Dollands but no further - nothing that I saw on the Yahoogroup answers that; there has been a higher rate of deliveries recently so two in a week is not unusual.
Ok then,Chunnel? U mean channel tunnel?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

BRX

Established Member
Joined
20 Oct 2008
Messages
4,477
Regarding the earlier post in relation to the number of diagrams for each route, how many are required for the Wimbledon and Sutton loop?

Also, if I was a local resident along the loop, I would be happy with the original plan to curtail it to Blackfriars with the compromise that the frequency would be doubled to from every 30 minutes to every 15 minutes in both directions around the loop.
As a loop resident - yes I would prefer that! Also if the loop service were independent of the rest of thameslink we might get a more reliable service.
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,264
Something like
Units in UK - 700001-46/101-26/8-32/4/6-45
Units to come 700047-60/127/33/35/46-55

Used in service so far - 700001-46/101-25/8/39/40/3

Currently part of testing / training fleet 700015/19/110/37

In store
Horsham 700102/24/32/6/8/45
Peterborough 700111/16/40
Hove 700129

Leaving the following at Three Bridges or Hornsey
700130/1/4/5/41/2/4

Presumably a few of the units at Horsham enter service on Monday.
 

APUK002

Member
Joined
26 Dec 2016
Messages
315
Something like
Units in UK - 700001-46/101-26/8-32/4/6-45
Units to come 700047-60/127/33/35/46-55

Used in service so far - 700001-46/101-25/8/39/40/3

Currently part of testing / training fleet 700015/19/110/37

In store
Horsham 700102/24/32/6/8/45
Peterborough 700111/16/40
Hove 700129

Leaving the following at Three Bridges or Hornsey
700130/1/4/5/41/2/4

Presumably a few of the units at Horsham enter service on Monday.
Oo,thanks for posting this
 

samogers

Member
Joined
20 Feb 2014
Messages
173
Location
Swansea
Am I right in thinking some diagrams start tomorrow on some London Bridge - West Coastway and London Bridge - Horsham services?
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,264
Am I right in thinking some diagrams start tomorrow on some London Bridge - West Coastway and London Bridge - Horsham services?

Yes, first workings are

1H80 0552 Littlehampton to London Bridge
2C78 0633 Horsham to London Bridge
1H82 0629 Littlehampton to London Bridge

1H80 feeds into one of the existing Brighton off-peak diagrams, the other two work to Horsham off peak and then go back to Littlehampton in the evening peak.

1H91 1657 London Bridge to Littlehampton
1H95 1741 London Bridge to Littlehampton


There is a balancing empty stock working from Three Bridges to Horsham later.

 

Fincra5

Established Member
Joined
6 Jun 2009
Messages
2,636
Yes, first workings are

1H80 0552 Littlehampton to London Bridge
2C78 0633 Horsham to London Bridge
1H82 0629 Littlehampton to London Bridge

1H80 feeds into one of the existing Brighton off-peak diagrams, the other two work to Horsham off peak and then go back to Littlehampton in the evening peak.

1H91 1657 London Bridge to Littlehampton
1H95 1741 London Bridge to Littlehampton


There is a balancing empty stock working from Three Bridges to Horsham later.
I do wonder if both 1st Class sections will be in use, given how popular 1st is on the what was the 3x4car 377s.
 

samogers

Member
Joined
20 Feb 2014
Messages
173
Location
Swansea
Yes, first workings are

1H80 0552 Littlehampton to London Bridge
2C78 0633 Horsham to London Bridge
1H82 0629 Littlehampton to London Bridge

1H80 feeds into one of the existing Brighton off-peak diagrams, the other two work to Horsham off peak and then go back to Littlehampton in the evening peak.

1H91 1657 London Bridge to Littlehampton
1H95 1741 London Bridge to Littlehampton


There is a balancing empty stock working from Three Bridges to Horsham later.

Interesting, thanks. I did notice that 1H99 the 1810 London Bridge to Littlehampton service is still a Southern service (and presumably still 12-377). I wonder if any people unhappy with the new trains and change in 'operator' may migrate temporarily to this service rather than the two before.
 

Stew998

Member
Joined
17 Jan 2014
Messages
98
Location
Mid Sussex
Am I right in thinking some diagrams start tomorrow on some London Bridge - West Coastway and London Bridge - Horsham services?
Judging by some unhappy tweets today from some quite understandably hacked off customers this appears to be the case.
 

RUFJAN15

Member
Joined
1 Jan 2015
Messages
49
Something like
Units in UK - 700001-46/101-26/8-32/4/6-45
Units to come 700047-60/127/33/35/46-55

Used in service so far - 700001-46/101-25/8/39/40/3

Currently part of testing / training fleet 700015/19/110/37

In store
Horsham 700102/24/32/6/8/45
Peterborough 700111/16/40
Hove 700129

Leaving the following at Three Bridges or Hornsey
700130/1/4/5/41/2/4

Presumably a few of the units at Horsham enter service on Monday.

I ventured out early this morning to see the first TL departure (in passenger service) from Horsham. 700145 did the honours on the 06.33 to London Bridge, so that's another FLU in use.

Timekeeping today has been pretty dire; the best TL service on the London Bridge - Horsham route arrived 8m late, with others 10m-20m down and one curtailed at Three Bridges 27m late. Mind you, to be fair the Southern 377 services on the route have been equally bad today.
 

tsr

Established Member
Joined
15 Nov 2011
Messages
7,400
Location
Between the parallel lines
Services were severely disrupted due to fourteen coaches of 377 stock managing to get stranded on a dead section of track at Bricklayers Arms Junction near London Bridge (partly owing to NR not investigating power supply issues and only testing the third rail once the rescue train also got stuck...). In fact, the trains have had to have a driver babysitting them all day, until repairs are done tonight.

This was basically nothing to do with the 700 rollout - indeed GTR Control spent some time working out ways to protect the evening 700 diagrams on the Littlehampton route from being cancelled...
 

physics34

Established Member
Joined
1 Dec 2013
Messages
4,082
Services were severely disrupted due to fourteen coaches of 377 stock managing to get stranded on a dead section of track at Bricklayers Arms Junction near London Bridge (partly owing to NR not investigating power supply issues and only testing the third rail once the rescue train also got stuck...). In fact, the trains have had to have a driver babysitting them all day, until repairs are done tonight.

This was basically nothing to do with the 700 rollout - indeed GTR Control spent some time working out ways to protect the evening 700 diagrams on the Littlehampton route from being cancelled...
!
Thank goodness it was a set of empties!
 

RichJF

Member
Joined
2 Nov 2012
Messages
1,199
Location
South London
I've noticed that once again the London Bridge - Horsham stoppers are delayed and behind time today. There's one 17 minutes down, one 14 minutes down and a LIttlehampton was 10 down when it arrived at London Bridge.

I hope this is not going to be the new norm & the 700's bed down on these new routes.

If these services are intended to be integrated into the Core to link up with the Great Northern services, then the reliability/timekeeping must improve.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,013
Location
St Albans
I've noticed that once again the London Bridge - Horsham stoppers are delayed and behind time today. There's one 17 minutes down, one 14 minutes down and a LIttlehampton was 10 down when it arrived at London Bridge.

I hope this is not going to be the new norm & the 700's bed down on these new routes.

If these services are intended to be integrated into the Core to link up with the Great Northern services, then the reliability/timekeeping must improve.

So have the services operated by class 700s that have suffered delays this week, been caused by failures of the trains themselves or have other train types/infrastructure been causing the problems?
 

Bishopstone

Established Member
Joined
24 Jun 2010
Messages
1,685
Location
Seaford
Anecdotally - ie through looking at the departure boards when I pass through Gatwick twice daily, and also when I’ve had need to use these services - the London Bridge-Horsham runs have suffered very poor punctuality and a high cancellation rate going back years.

These Horsham services are amongst the first to be binned in the event of network disruption, so commiserations to friends in Great Northern land.
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,264
Anecdotally - ie through looking at the departure boards when I pass through Gatwick twice daily, and also when I’ve had need to use these services - the London Bridge-Horsham runs have suffered very poor punctuality and a high cancellation rate going back years.

These Horsham services are amongst the first to be binned in the event of network disruption, so commiserations to friends in Great Northern land.

I think they suffer disproportionately from the congestion on the slow side of East Croydon from Purley through to Norwood Junction, tight turnarounds at London Bridge and generally because of the number of stops over a reasonable length journey. Delays to Arun Valley services can also knock them out of course.
 

387star

On Moderation
Joined
16 Nov 2009
Messages
6,665
Travelled on the 1657 London Bridge to Littlehampton

The train was very hot perhaps the heating was a tad generous!
Tables were welcome and saw a lot of use
Announcements giving the coach number may be helpful on services where once these were announced as the norm however there were staff making sure passengers were aware of the short platforms
The screen was not displaying journey information till around Three Bridges although this is more a PIS design issue

The tables make a massive difference to the feel of the train and I can't say I felt uncomfortable other than on account of the heat!

The train was near dead after around Worthing which I guess is the norm on this service although perhaps quieter on the run up to christmas
 

superalbs

Verified Rep - Superalbs Travels
Joined
3 Jul 2014
Messages
2,826
Location
Kraków
What seats are used in 700 first class?
More Fainsa seats, ideally what should be used in standard, they're not particularly good, but a huge step up from the disaster of a seat otherwise used lol.

Unless if the extra padding ironing-board is any good, but I'm not aware of anything in service that actually has them.
 

tsr

Established Member
Joined
15 Nov 2011
Messages
7,400
Location
Between the parallel lines
On the subject of Horsham services, these typically suffer at the end of the morning peak and during the evening for a fair few different reasons.

The stock diagrams and stopping patterns are very complex, some of which has been temporarily further complicated rather than made better by the arrival of 700s; the crew diagrams being complex and there being few or no spare crew at the small depot at Horsham (drivers and former conductors, now OBSs, have all been affected for years by this); impenetrable working of the sidings at Horsham caused by the station staff being allowed to dictate what they want to Control, rather than a centralised plan; numerous junction conflicts en-route; needless passenger confusion by the way stopping services are advertised at Gatwick; local traffic causing overcrowding between London Bridge and Purley... you name it really.

Everything which can go wrong inevitably does and there are so many factors which affect them. Busy commuter routes such as these could actually do better under Thameslink, as there should be more focus on good service recovery, new crew workings and only 2 stock formations (8 & 12 car 700s), but there will still be parallel Southern services which will not get the same service delivery focus and that will make life harder.

I wouldn’t agree that these trains get binned unduly frequently, but they tend to miss a lot of local stops if they are delayed, which completely defeats the point of running them at all. Adding stops on other trains also tends to fail PPM on those services.
 