Sorry, but the work in that document in not committed or funded until ORR signs off the CP5 plans in March next year. It is currently just an ongoing part of the NR response to the DfT's HLOS, following similar timescales to what they did for CP4.
I don't mean to go on about this, or dispute your knowledge, but Virginia Water - Reading platform extensions appears in a tabled headed CP5 Schemes Committed and Funded.
--- old post above --- --- new post below ---
But SWT announced the extra peak Reading services as part of the internal cascade allowed for by the 458/5s coming into service, so 6 months before the 456s were first mentioned. Maybe it's achieved as a knock on effect of there being 36 x 458/5s? (The two services in each peak are mentioned in those lists in my first reply to this thread.)
The 28 450/5s are currently supplemented by a number of 450/0s and at least one pair of 455s on a late AM peak Hounslow loop working. Maybe they've been able to squeeze another couple of 455s out of current diagrams to give the 4 extras units that the Reading line will need.
).