Whilst I fully agree with your second sentence, I think "in any rail-related context" is unfair. For example we used the Florida Sunrail services earlier this year. The stations are well thought out with good parking, dedicated bus connections and platform facilities (e.g. seating, weather protection) far superior to anything between Leeds and Goole. Similarly the seats on the push-pull double decker sets are much more comfortable than recent UK examples(although the ride is CAF standard or worse).Indeed - I hardly think that the word “advanced” can be applied to the USA in any rail-related context. That said, I would also consider our standards to have gone too far in terms of recognition of realities - cost of providing fully compliant rail facilities meaning they don’t happen- forcing people onto much more unsafe roads.
I don't have inside knowledge, but from what I can gather on Railcar diagrams, Goole signals locally to just beyond the junction and Glassworks, then it looks like York ROC signals the rest.Has anyone considered the signalling infrastructure for this line? Is it controlled by part time local boxes or is it remotely controlled from the ROC?
Historically the Goole trains all ran to Wakefield as it was ex L&Y - there's probably more demand for Goole-Wakefield than -Castleford but it's 10min slower to Leeds.In terms of the service pattern its worth considering what the situation would be if both these improvements and the Askern service were to come off, principle calls only shown:
Option 1
Leeds - Castleford - Knottingley - Goole
Leeds - Wakefield - Knottingley - Doncaster
Option 2
Leeds - Castleford - Knottingley - Doncaster
Leeds - Wakefield - Knottingley - Goole
Quite. The only efficient way I can see (1 unit, 2 hourly both routes) involves trains going out via Castleford but returning via Wakefield (or v.v.) - tight turnround at Goole but longer at Doncaster which is wise! But all this is rather academic.However there are certain issues of unit diagramming which add cost to either (but not necessarily both) schemes. At Knottingley the unit which has arrived via Castleford departs via Wakefield and vice versa. If you wanted one of those to be extended to either Goole or Doncaster, then the other suddenly needs around 35 minutes at Knottingley (unless you want to find new paths in and out of Leeds). The current diagrams mean that there are 3 services on the move at any given time on the "hourly each way Knottingley service", the moment one of them is extended not only does that need another unit and traincrew, the rump of the other service does too.
I think you've got that right.In terms of the service pattern its worth considering what the situation would be if both these improvements and the Askern service were to come off, principle calls only shown:
Option 2
Leeds - Castleford - Knottingley - Doncaster
Leeds - Wakefield - Knottingley - Goole
Yes, you would. If it's an additional service, then it's fine to bypass Knottingley (Grand Central already do that). Otherwise, Knottingley's service gets cut in half and cuts the link to either of Wakefield or Knottingley depending on which service you extend.I think you've got that right.
With respect to Knottingley-Doncaster would you really need to spend anything at Knottingley or Askern? Simply run Pontefract-Doncaster direct and see if the service looks viable before trying to justify incremental spend. And if an otherwise necessary T&S renewals requirement came along at Knottingley , then just move the pointwork to the east of the station.
You're absolutely right. Cant believe I missed that.Yes, you would. If it's an additional service, then it's fine to bypass Knottingley (Grand Central already do that). Otherwise, Knottingley's service gets cut in half and cuts the link to either of Wakefield or Knottingley depending on which service you extend.
I think that's correct time-wise, although the service from Wakefield Kirkgate via Featherstone didn't initially run through to Knottingley. It terminated at Pontefract Monkhill as this allowed the service to be operated with a single unit (usually a class 141 in the early days) shuttling back & forth.My recollection may be faulty but I think the old Goole-Leeds service was slashed in 1991 , just as plans were being made to reintroduce the Knottingley-Wakefield service the following year. One might have fed some traffic into the other. In the days of one controlling mind, services for the benefit of the public not shareholders etc which we are now moving back into
BBC said:Rail passengers travelling between Goole and Leeds want more direct regular train services so they can get to and from work, while also being able to get home for childcare.
Currently, there are only two direct trains from Goole to Leeds a day, with only one returning from Leeds at the end of the working day.
Goole rail users can get home by using a longer route through South Yorkshire and changing at Doncaster, but commuters from Snaith and Rawcliffe have no alternative trains........
I must say I did chuckle at councillor Anne Handley adding 2 and 2 together to get 5 via moaning about how Siemens Rail are based in Goole so why can’t we have more train services![]()
Perhaps I'm being cynical, but I'm awaiting the feasibility studies and business cases that cite millions of needed upgrade work before any service increase can be contemplated......
Depends on the terms of reference, but any outline study worth its salt would askAs I see it:
- this route is currently used by passenger services (to a very limited extent) and is therefore considered suitable for this purpose
- the route is single track and heavily rationalised between Drax junction and Goole and double track elsewhere
- the current passenger service takes 16/17 minutes to travel between Drax Junction and Goole.
- the rationalised part of the route is hardly routinely used by anything else
I conclude (perhaps erroneously) that a train therefore needs only occupy the single track section for, say, 45-50 minutes in order to make a round trip (allowing for the reversal at Goole if that is where it terminates) and that therefore with nothing more than rolling stock and personnel resource, i.e. with absolutely no capital investment, this route could support an hourly frequency in both directions.
Perhaps I'm being cynical, but I'm awaiting the feasibility studies and business cases that cite millions of needed upgrade work before any service increase can be contemplated......
Are there level crossings that might need attention before significantly increasing the service?
Ideally the sensible approach would be to look at the increased risk of level crossing accidents from a more frequent service and compare it to the reduced risk of road accidents from drivers switching to the train.Are there level crossings that might need attention before significantly increasing the service?
The most obvious one is just to the east of Whitley Bridge, which is also the closest to an M62 junction if you're trying to encourage modal shift (you'd need a bigger car park, of course). There's a bridge over the canal to the south but no landing area north of the station if you were to fund an extension to it to cover the railway.It does have level crossings (can't remember how many as have only been along it a couple of times). I think they're protected with barriers etc.
I assumed (charitably?) that she thought there might be potential commuter traffic to Goole - rather than Leeds, which has been the prevailing theme.I must say I did chuckle at councillor Anne Handley adding 2 and 2 together to get 5 via moaning about how Siemens Rail are based in Goole so why can’t we have more train services![]()
There are loads, a mixture of full and half barriers (and even one unbarriered, if Googlemaps is up-to-date - in Gowdall), but I would guess that the roads aren't massively busy.Are there level crossings that might need attention before significantly increasing the service?
Nothing at all realistic1. What could you do using existing infrastructure and trains (direct operating costs only)?
An hourly service, if you didn't mind using one route out and another back; realistically, 2 hourly with one extra unit and crews.2. What could you do with existing infrastructure and one (or more) additional train requirement?
Apart from necessary level crossing upgrades, I think we would be far too deep into fantasy-land3. Beyond that, what would require new infrastructure?

Goole does have a reasonable amount of industry, though if we're going crayon mad then eastward commuting might be more of a thing if the train carried on to Hull.I assumed (charitably?) that she thought there might be potential commuter traffic to Goole - rather than Leeds, which has been the prevailing theme
Depends on where those cars have come from, though.Look at the thousands of parked cars at Glasshoughton each weekend and compare that to the hourly trains it gets - all two coach 1980s DMUs - it's no wonder rail isn't attractive
That's what I'd personally be focusing resources on, rather than the hamlets east of Knottingley
I'd presume that they'll mostly be fairly local, because if you're coming from further afield you wouldn't choose Glasshoughton as your railhead. There are other stations not too far away with double the frequency, if you've already got onto the motorway network.Depends on where those cars have come from, though.
I imagine that most of them are visiting the local facilities (leisure centre or whatever it is) rather than using the station.I'd presume that they'll mostly be fairly local, because if you're coming from further afield you wouldn't choose Glasshoughton as your railhead. There are other stations not too far away with double the frequency, if you've already got onto the motorway network.
But if Northern are imminently ordering new trains which will improve the service west of Knottingley, then isn't they the time to figure out if a couple of extra units could provide a better service to Goole, Snaith and the various other places that the train would serve?That's what I'd personally be focusing resources on, rather than the hamlets east of Knottingley
People driving to Xscape or the Outlet will park at the vast parking area at the outlet, not at the 100-space station car park.I imagine that most of them are visiting the local facilities (leisure centre or whatever it is) rather than using the station.