A thread to cover the topic of faults at stations and the seemingly huge time it takes to have them fixed.
I am aware of many serious faults at various stations I use or pass through regularly and am amazed at the length of time it takes to have even simple remedial action undertaken. Some examples (all Southern-'managed'):
Redhill - several adjacent lighting tubes out on platform 1 for at least five months, resulting in a large and very dark area under the canopy where there is much passenger movement in all directions. After several reports by me of the failures over the months with no action, it was miraculously fixed last week immediately after I wrote to ASLEF about it and suggested that they might want to review their members operating trains through the platform at night, given the hugely sub-standard lighting levels!
Dorking - the subway from platforms 2/3 to 1 has at least three stair treads missing, leaving the crumbling sub-strate exposed and acting as the stair treads, presenting a significant hazard. Again, I've reported it several times over the many months it has been like that - nothing done. Very simple remedy - provide three stair nosings to match the rest - cheap, quick and easy to do, but apparently beyond Southern's abilities. If/when someone falls on the stairs it will be interesting to see the outcome.
Purley - the recently-installed Thameslink (class 700) 'PLU' sign and post on platform 4 came loose in strong winds at least two months ago. I reported it then. It still stands there with the fixing bolts loose at the base and the whole post assembly is tied back to the fence behind it with yellow hazard tape! Simple and quick solution - re-fix the bolts properly in the platform. Nothing done again.
One also from my local station - Betchworth (GWR). The platform train indicator on platform 1 has been broken for at least eight months, and repeated reports of its unreliability over the last five years have yielded no action. I wrote to my MP about it as GWR were of no use (most recently claiming that their local manager had visited and found nothing wrong!!), and he replied that he had had other complaints about the failure. GWR subsequently informed me, well before Christmas, that they were having a part specially made to repair it and it should be working again soon. It still is not.
I am aware of many serious faults at various stations I use or pass through regularly and am amazed at the length of time it takes to have even simple remedial action undertaken. Some examples (all Southern-'managed'):
Redhill - several adjacent lighting tubes out on platform 1 for at least five months, resulting in a large and very dark area under the canopy where there is much passenger movement in all directions. After several reports by me of the failures over the months with no action, it was miraculously fixed last week immediately after I wrote to ASLEF about it and suggested that they might want to review their members operating trains through the platform at night, given the hugely sub-standard lighting levels!
Dorking - the subway from platforms 2/3 to 1 has at least three stair treads missing, leaving the crumbling sub-strate exposed and acting as the stair treads, presenting a significant hazard. Again, I've reported it several times over the many months it has been like that - nothing done. Very simple remedy - provide three stair nosings to match the rest - cheap, quick and easy to do, but apparently beyond Southern's abilities. If/when someone falls on the stairs it will be interesting to see the outcome.
Purley - the recently-installed Thameslink (class 700) 'PLU' sign and post on platform 4 came loose in strong winds at least two months ago. I reported it then. It still stands there with the fixing bolts loose at the base and the whole post assembly is tied back to the fence behind it with yellow hazard tape! Simple and quick solution - re-fix the bolts properly in the platform. Nothing done again.
One also from my local station - Betchworth (GWR). The platform train indicator on platform 1 has been broken for at least eight months, and repeated reports of its unreliability over the last five years have yielded no action. I wrote to my MP about it as GWR were of no use (most recently claiming that their local manager had visited and found nothing wrong!!), and he replied that he had had other complaints about the failure. GWR subsequently informed me, well before Christmas, that they were having a part specially made to repair it and it should be working again soon. It still is not.
Last edited: