Staffordshire resignalling

Status
Not open for further replies.

QueensCurve

Established Member
Joined
22 Dec 2014
Messages
2,196
Even though the work seems to be substantially complete, information on the details of the Stafford resignalling seems hard to come be - being limited to the scant information in NR press releases.

Does anyone have access to the as-completed track diagram or details of the changes to turnout speeds etc?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

rdeez

Member
Joined
7 Apr 2013
Messages
354
There's some information in this thread:

http://www.railforums.co.uk/showthread.php?t=109588

This mentions that Doxey turnout speeds are remaining unchanged.

There's no track diagram I know of, but the only change really is the lengthening of the postal siding southwards to become a goods loop, and the removal of the old sidings south of the station
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,656
Nothing exciting is happening, platforms go bi-di if they arent already, Stafford No.1 junction goes from 30 to 40 on the slows and there is a new 775m loop on the down slow which feeds into the old mail platform. The old Universal Grinding siding gets ripped out too.
--- old post above --- --- new post below ---
and the removal of the old sidings south of the station

The sidings on the down are meant to be put back in.
 

Ash Bridge

Established Member
Joined
17 Mar 2014
Messages
4,214
Location
Stockport
Apologies if this has been asked before, but what sort of speeds will be allowed, for services (e.g. XC) coming off/ joining the Stone branch when the flyover is operational? Thanks!
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,682
That will be quite an improvement on the current setup then, perhaps a 4/5 min time reduction possible on Manchester- Birmingham XC services?

More like 2 or 3, it only costs a 125mph 5 mins to have a station stop.
 

driver_m

Established Member
Joined
8 Nov 2011
Messages
2,248
Do they have the acceleration to be doing 100mph by the time they reach the viaduct given that they crawl through Stone?

A 220 should do, the pendo that goes that way in the morning will definitely manage it from stone.
 

The Snap

Established Member
Joined
10 Jun 2005
Messages
3,156
Nothing exciting is happening, platforms go bi-di if they arent already, Stafford No.1 junction goes from 30 to 40 on the slows and there is a new 775m loop on the down slow which feeds into the old mail platform. The old Universal Grinding siding gets ripped out too.
--- old post above --- --- new post below ---


The sidings on the down are meant to be put back in.

Sidings 1 and 2 are going back in, adjacent to the new Down Goods loop which runs into the former Royal Mail road.

As well as what The Planner has mentioned, there's a few signal gantries going up throughout the area (10 IIRC) and a few OLE structures which are being relocated/replaced to account for sighting of new signals.

Network Rail are also getting a new £3million maintenance depot where the Down sidings were. The existing monstrosity is being demolished.

As said in other thread, Stafford No. 4 and No. 5 boxes are also being demolished with control going to Rugby ROC.
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,571
Location
Lancashire
Are they putting the track back to the OTM shed as well? Not seen it used since Jarvis went bust
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,656
Norton Bridge has a very good chance of allowing the northbound XCs to speed up as it can get them ahead of the Pendo at Stone. Im not sure how we could hide that many "performance" minutes...
 

The Snap

Established Member
Joined
10 Jun 2005
Messages
3,156
The building that looks similar to Wolverhampton PSB?

The building that looks like Wolves PSB will be demolished, and the new building will look very similar to Stockport MDU.
 

brick60000

Member
Joined
18 Apr 2013
Messages
461
Network Rail are also getting a new £3million maintenance depot where the Down sidings were.

Sorry to post in an old thread, but does this potentially mean that Network Rail will have some of their locomotives / various track testing / measurement trains based here? :D
 