St Pancras before HS1

Status
Not open for further replies.

YorksLad12

Established Member
Joined
5 Feb 2020
Messages
2,699
Location
Leeds
It's a nice place to wander around, but I wouldn't go there to catch a train...

If the circulation area for the MML trains was larger (buy not having such a big hole cut in the floor, and the escalators moved back 10 feet away from the trains, say (I'm going from memory)) it might be more bearable, but the queuing system to board looks like an angry mob when you arrive off an incoming set and try to get past them!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Joe Paxton

Established Member
Joined
12 Jan 2017
Messages
2,958
It's a nice place to wander around, but I wouldn't go there to catch a train...

If the circulation area for the MML trains was larger (buy not having such a big hole cut in the floor, and the escalators moved back 10 feet away from the trains, say (I'm going from memory)) it might be more bearable, but the queuing system to board looks like an angry mob when you arrive off an incoming set and try to get past them!


I recall hearing something along the lines of when the design specs for the 'new' St Pancras were being finalised, it ultimately came down to one senior railway manager (in which organisation I'm not sure) who decided that the Midland main line only needed four high-level platforms rather than six. I've no idea whether there's anything in this, but given passenger growth on the MML one can't help but conclude this was a suboptimal choice.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,648
I've no idea whether there's anything in this, but given passenger growth on the MML one can't help but conclude this was a suboptimal choice.

This comes up repeatedly. 4 platforms is sufficient. There is no capacity on the MML for more than 6tph ‘EMR’ services, as now, and no prospect of the very significant capital investment that would be required to increase it. 6tph (2 of which are EMUs with short turnround) off 4 platforms is simple.
 

TheBigD

Established Member
Joined
19 Nov 2008
Messages
2,043
This comes up repeatedly. 4 platforms is sufficient. There is no capacity on the MML for more than 6tph ‘EMR’ services, as now, and no prospect of the very significant capital investment that would be required to increase it. 6tph (2 of which are EMUs with short turnround) off 4 platforms is simple.

The EMUs on the Corby services generally have around 23 minutes turnaround at St Pancras.

The Meridians on the Nottingham and Sheffeild have as low as 10 minutes (1255 arrival forms the 1305 departure), but usually have around 40 minutes for the Nottinghams, and 23 minutes for the Sheffields, though it does vary a fair bit during the day.
 