fwsmVor
On Moderation
Has there ever, on some obscure isolated branch or tramway, been a speed-signalled railway in GB? (and did the ECML flashing greens count?)
It was replaced by standard signalling in May 1970.One sole installation of speed signalling was made in Yorkshire by the LMS in 1932. This was installed on a three-mile stretch of quadruple line between Heaton Lodge Junction and Thornhill LNW Junction which included a junction and station at Mirfield. The scheme was for the signals alone, and whilst a little sensible thinning-out of signal boxes occurred, the control remained from mechanical frames and the Absolute Block system continued in use.
Recent thread at https://www.railforums.co.uk/threads/mirfield-resignalling.253043/ with more information than in my post above.Mirfield and covered on a recent thread on here
jfollows above beat me to it
There is the current installation of TVM-430 on HS1.Has there ever, on some obscure isolated branch or tramway, been a speed-signalled railway in GB? (and did the ECML flashing greens count?)
So when flashing greens were used, you could theoretically pass a double yellow at 140mph as long as you could stop in time?The ECML Flashing Greens are not speed signalling - the flashing green indicates only that the signal ahead is showing a steady or flashing green and conveys no information about the permitted speed specifically.
No, or at least not designed as such.So when flashing greens were used, you could theoretically pass a double yellow at 140mph as long as you could stop in time?
No, because the signal spacing is almost certainly not going to allow the service braking to stop a train from after the double yellow in time. Although not tied to a specific speed (unlike in the Netherlands, where single yellow = 40kph), it is still required that drivers control their train and approach cautionary aspects appropriately. It's just that Double Yellows might be passed at a range of speeds because they mean 'expect to find next signal at Yellow' rather than 'reduce speed to Xmph'. But any driver who went through a Steady green at 140mph has already broken the rule by not reducing the speed of their train when receiving a 'expect to find next signal at preliminary caution' aspect (which would be the meaning if receiving a Green on a 5-aspect section).So when flashing greens were used, you could theoretically pass a double yellow at 140mph as long as you could stop in time?
Given this is ATO does it count as either Speed or Route Signalling?Jubilee line/DLR moving block? The speed is what is controlled, to ensure the train can stop at the end of the block (stationary or moving...)
Depends on your definition. To me the essence of speed signalling is about transmitting the speed information to the driver visually. Electronic transmission as part of a CBTC system is a different thing. No doubt others will disagree, though.Jubilee line/DLR moving block? The speed is what is controlled, to ensure the train can stop at the end of the block (stationary or moving...)
It's arguable whether the Mirfield installation gave any indication of speed. It was given that designation by the LMS, and by its USA manufacturer, but did little new. On open line it was similar to UK 4-aspect signals, with two lights just telling how many signals ahead were clear. For junctions an additional light, and combinations of colours, showed whether it was clear to the main line (termed "high speed") or any turnout (termed "medium speed"). No indication of actual speed was given. There was advance signal indication given of a turnout, compared to UK practice of only showing the feather at the actual junction signal, but that was a marginal difference.Yes, at Mirfield, see https://signalbox.org/signals/lms-speed-signalling/
It was replaced by standard signalling in May 1970.
Reading through the website, although it must have seemed foreign at the time, it doesn't look like speed signalling. It seems like it's more "what if the ECML in the 90s had splitting distants".It's arguable whether the Mirfield installation gave any indication of speed. It was given that designation by the LMS, and by its USA manufacturer, but did little new. On open line it was similar to UK 4-aspect signals, with two lights just telling how many signals ahead were clear. For junctions an additional light, and combinations of colours, showed whether it was clear to the main line (termed "high speed") or any turnout (termed "medium speed"). No indication of actual speed was given. There was advance signal indication given of a turnout, compared to UK practice of only showing the feather at the actual junction signal, but that was a marginal difference.
There's another in the NRM at York (unless it's the same one moved around).One of the Mirfield speed signals is preserved in the museum at Oxenhope on the Keighley & Worth Valley Railway, should anyone wish to examine it in close-up.
The question is whether or not "medium speed" and "low speed" actually had defined speeds. The Signal Box website does not say they did, but American practice would definitely be to define "medium speed" and "low speed" as specific speeds - see this diagram of aspects on their Southern Railway for an example:It's arguable whether the Mirfield installation gave any indication of speed. It was given that designation by the LMS, and by its USA manufacturer, but did little new. On open line it was similar to UK 4-aspect signals, with two lights just telling how many signals ahead were clear. For junctions an additional light, and combinations of colours, showed whether it was clear to the main line (termed "high speed") or any turnout (termed "medium speed"). No indication of actual speed was given.

Were there feather indicators in use in the 1930s?There was advance signal indication given of a turnout, compared to UK practice of only showing the feather at the actual junction signal, but that was a marginal difference.
There was an element of speed signalling in the flashing green in so far as the maximum speed was 125mph on green and 140mph on flashing green.The ECML Flashing Greens are not speed signalling - the flashing green indicates only that the signal ahead is showing a steady or flashing green and conveys no information about the permitted speed specifically.
Well that's inherent to the concept of speed signalling at junctions. The question is whether precise speeds were defined - there certainly were plenty of definite speed limits around in the 1930s despite the lack of speedometers.Regarding "speed", I understood the LMS interpretation was high = through line, medium = turnout, slow = siding. Bear in mind when installed at Mirfield, hardly any (possibly no) locomotives had speedometers.
It's inevitable given the relationship between speed and safe stopping distances that as systems get more sophisticated they will take on elements of speed signalling. As the line becomes blurred it's harder to say something is definitely not speed signalling.There was an element of speed signalling in the flashing green in so far as the maximum speed was 125mph on green and 140mph on flashing green.
These are the definitions I personally use:As the line becomes blurred it's harder to say something is definitely not speed signalling.
The first use of three lamp directional route indicators ('feathers') by the Southern Railway was in the Waterloo-Hampton Court Junction resignalling in 1936. However the LNER used five lamp feather route indicators in the Thirsk resignalling - the first British route-setting panel installation - in 1933.I think the Southern were the first users of a feather - 3 lights instead of five.
The Thirsk resignalling of 1933 contained not a single feather. There was however a trial at Thirsk that year where a signal was fitted with neon-tube type feathers (including one in the vertical position for the straight route). The LNER's 5-lamp feathers didn't appear until about 1938.However the LNER used five lamp feather route indicators in the Thirsk resignalling - the first British route-setting panel installation - in 1933.
Ah yes....further research shows that to be true. Slightly OT, but would I be correct in thinking that the first LNER five lamp 'feathers' were actually installed at Northallerton?The Thirsk resignalling of 1933 contained not a single feather. There was however a trial at Thirsk that year where a signal was fitted with neon-tube type feathers (including one in the vertical position for the straight route). The LNER's 5-lamp feathers didn't appear until about 1938.
I am following this thread with interest. I have always been interested in signalling and more recently in braking techniques to avoid SPADs. In my current part time role I calculate theoretical stopping distances for rolling stock to confirm compliance with GM/RT2045. My understanding is that there aren’t any lines with speed signalling on NR infrastructure. The definition of signals as indicating the limits of movement authority confirms that their purpose is the instruct the driver the point that they must not pass. It is therefore the driver’s role to ensure that the train is brought to a stand before the limit of authorised movement is passed. Understanding the braking technique drivers use to stop their train within the signal spacing has been an area where I didn’t have any experience. My understanding is that the minimum signal spacing for the applicable line speed is about 15 or 20% longer than maximum Full Service stopping distance mandated in GM/RT2045. As I don’t think it would be good practice to make a Full Service brake application at every restrictive signal aspect. My question is how do drivers ensure that as far as possible they don’t need to make a Full Service or Emergency brake application when encountering a restrictive signal aspect and are restrictive signal aspects in effect an indication of the maximum speed that the signal should be passed at I.e. a ‘speed signal’. they in effect read the preceding am interested in the real situation and how drivers would not be desirable braking techniques would and therefore the driving technique to stop within the minimum signal spacing distance for the maximum line speed has been an interest
These are the definitions I personally use:
Progressive speed signalling - signals warning of an upcoming stop signal impose speed limits on trains passing them
If there's a specific speed listed in the rules that drivers must always be under when passing all single yellow signals, I would call that progressive speed signalling.Some TOCs have their own specific rules about what speed their drivers should attain by the time they pass a single yellow signal in four-aspect signalling sections for example, but that does not mean that there is speed signalling in operation.
What are you defining as speed signalling?You could claim that any signal fitted with TPWS OSS does that, but that does not make it speed signalling.
Speed signalling is where the signalling system conveys authority to the driver to proceed at a specified speed. Progressive Speed signalling sounds like another name for just 'driving properly'. The only 'true' speed signalling system in the UK is TVM-430. All other signalling systems indicate whether or not a track ahead is occupied and the driver is expected to modify their speed accordingly, but the signalling itself does not change the authority to move at a specified speed.If there's a specific speed listed in the rules that drivers must always be under when passing all single yellow signals, I would call that progressive speed signalling.
What are you defining as speed signalling?