The Eridge Run-around project is a little while off yet, please don't think anything will happen this year.
The Signalling Design work was signed off by our Independent Competent Person last Summer along with the Spa's S&T Manager. This design is reliant on Groombridge's Signalling Scheme reaching the stage where the Eridge end Ground Frame can be decommissioned. This is required at Eridge for the interlocking, points and shunt signals related to protecting the Swing Bridge.
The Swing Bridge is to be acquired from Brockenhurst, we are very grateful to Network Rail for allowing this to happen. However this won't be decommissioned from its current home until the Spring of this year. Even when acquired the correct ramp is required at Eridge to allow the bridge to be installed and the public right of way retained.
We do own a point of the correct curvature for installation the Crowborough side of Eridge station which was sourced and purchased in 2011.
The operating instructions have been prepared by the Ops department however further discussions with other parties must take place before infrastructure work can take place along with S&T modifications to the current Eridge Ground Frame.
Part of the project will incorporate the reinstating of some of the former Down Siding 1.
Work is currently focused on the TWW Landslip however some other high priority track renewals are likely to take place before Eridge RR along with reaching the relevant stage with GBR Signalling.