In the winter of 1988, quite a lot of tunnels were pointed and around Huddersfield.
For this job, BR had a bogie bolster kitted out with a roof, and generators to power lights and cement mixers for pointing the brick works within the the tunnels as water was dripping through the roofs of these tunnels.
At Huddersfield the down goods yard was where these trains were stabled.
This was because the siding was able to accomodate motor vehicles to bring in cement and othe such stuff.
When required to be used, the pointing train was available for road access and railway access to bring out the train for use.
In March 1988 I was booked on to go light engine upto Huddersfield Goods Yard to bring out the PT to go up onto the Penistone Line.
When on platform 4 you could run round the train and cross over onto the up main and reach Springwood Junction by a main to main Xover.(This was before the upmain was lifted and turned into a platform.)
The PT had brake vans on either end.
The engine we used was a class 31, which had the muckiest exhaust I have ever seen.
As we were proppeling this train, I rode in the leading BV and and used my bardic to signal to the driver along the route to Brockholes Station.
This was in the days where the train I had was composed of un braked rolling stock.
Once we got to Brockholes the PT train was shoved into the work site about 10 yards inside.
The PIC told me what we were going to do, and what time we would be finished. He measured the time in mixes of boggo for the tunnel roof.
As a result of the I secured the PT hooked of and sent the 31 out of the tunnel to roost on the Station Platform. The PIC said if he wanted to move the train he would come down from the tunnel and tellus where to go.
There was on big problem, the 31 was dishing out clag and engine noise on the Station so the engine went down to the Huddersfield end of the platform out of the way.
I was relieved at 03:30 by another guard, who would take this train back to Huddersfield.
This happened all week till Friday.
In all HM crews did Halifax/Standage/Cumberworth/and both tunnels at Huddersfield.
At this time, there was up and down lines on the Penistone Line right upto
Clayton West Junction , where the line went into single railway.