South Wales 'Metro' updates

MikePJ

Member
Joined
10 Dec 2015
Messages
1,012
It appears that the December timetable has been loaded up for the Treherbert line.

It is shown with 4tph Mon-Sat (2tph to Cardiff Bay, 2tph terminating at Central) and journey times are unchanged. The spacing is pretty good, with trains at alternating 14 and 16 minute intervals. Trains to the Bay take 1 hour (vs 1hr 6 mins to Central). Sunday remains as 2tph to Central.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Smwrff

Member
Joined
27 Dec 2023
Messages
254
Location
Cymru Fawr
It appears that the December timetable has been loaded up for the Treherbert line.

It is shown with 4tph Mon-Sat (2tph to Cardiff Bay, 2tph terminating at Central) and journey times are unchanged. The spacing is pretty good, with trains at alternating 14 and 16 minute intervals. Trains to the Bay take 1 hour (vs 1hr 6 mins to Central). Sunday remains as 2tph to Central.
Other way around - 1hr to Central - 1:06 to Bay.
 
Last edited:

snalty

Member
Joined
26 Mar 2017
Messages
36
Any idea what happened to 756001 today? It was supposed to be running my commute home but a Sprinter turned up.
 

MikePJ

Member
Joined
10 Dec 2015
Messages
1,012
A brief piece in Modern Railways' September issue drew my attention to the release of the April TfW board minutes which mention that part of the delay to 398 introduction was caused by electrification concerns around the Intersection Bridge just south of Queen St. Quoting the minutes:
A new issue arose with Intersection bridge between Cardiff Central and Queen Street. As a contingency, testing
confirms that operations can proceed temporarily without powered OLE on the Bay Line by extending Class 398
battery usage.
Class 398 entry into service has progressed significantly. The Board were reminded that Class 398 introduction
enables fleet cascade, with the Class 756s moving to the Rhymney line.

Modern Railways asked what the issue was, and it turned out to be precautionary checks to ensure that the CVL electrification was sufficiently isolated from the main line electrification below. This led to a delay in the Bay wires being used for 398 testing, as various people noticed.
 

5021

Member
Joined
21 Apr 2023
Messages
81
Location
Oswestry
A brief piece in Modern Railways' September issue drew my attention to the release of the April TfW board minutes which mention that part of the delay to 398 introduction was caused by electrification concerns around the Intersection Bridge just south of Queen St. Quoting the minutes:


Modern Railways asked what the issue was, and it turned out to be precautionary checks to ensure that the CVL electrification was sufficiently isolated from the main line electrification below. This led to a delay in the Bay wires being used for 398 testing, as various people noticed.
My understanding was that this was supposedly the reason for the delay in energising the OHL on the Cardiff Bay line rather than introducing 398s. Having said which that didn't entirely make sense as there's a HV cable rather than overhead on the Bay line at the Intersection Bridge and indeed all the way from Butetown stop northwards of course.
 

AdamWW

Established Member
Joined
6 Nov 2012
Messages
5,951
My understanding was that this was supposedly the reason for the delay in energising the OHL on the Cardiff Bay line rather than introducing 398s.

While they did indeed start running on battery on the Bay line, maybe there was a delay while they made sure that this was viable?
 

MikePJ

Member
Joined
10 Dec 2015
Messages
1,012
Here’s the technical explanation from Modern Railways, quoting an unnamed TfW spokesperson:
"The bridges are bonded to the main line OLE system and it was therefore necessary to separate them from the CVL electrification system from an earthing point of view, to avoid a fault on either system affecting the other.


'This has been achieved by creating a 'floating section' in the CIB [Cardiff Intersection Bridge] area for the CVL OLE system, which utilises HV cable through the area to provide the earth path for the system. This enables both OLE systems to operate independently of each other.”

== Doublepost prevention - post automatically merged: ==

We finally have some news on Butetown station: a consultation document has been published which explains that Butetown's Down platform 2 (Lloyd George Avenue side) is planned to open on December 13th 2026. The preamble to the document notes that the deadline for completion of certain European-funded elements of the Metro is 27th February 2027.

This Entry into Service event will bring the newly constructed Down Platform 2 at Butetown Station into operational use.
The new platform has an overall constructed length of approximately 125 metres and an
operational stopping length of approximately 123 metres, this EIS will bring into use a
reduced operational use of 80mtrs, for the 3 car CityLink 398s limited services that
will run from December 2026.
Note: The final state operational length will be brought into use during the main CAR
commissioning April 2027.

It's not clear to me if "398s limited services" means that the services will only be operated by 398s, or if only certain trains will stop at Butetown (i.e. providing a "parliamentary" service so that they can say that the station was opened on time). I hope it means the former.
The down platform has a fixed distant signal signboard on it at the moment, which I presume is the reason why the full platform length won't be used initially - this will be removed when the line is converted to tramway rules during a future resignalling in April 2027 (that's what "main CAR commissioning" means).

There is a big shutdown on the Bay line programmed for the week of 24th-30th October, which is shown in the project plan as for installing the second track.
 

Attachments

  • Consultation Document CVL G1 Network Change Proposal CVLNC025 Butetown Station Interim Arrange...pdf
    367.4 KB · Views: 14
Last edited:

Markdvdman

Member
Joined
14 Aug 2011
Messages
499
Location
Merthyr Tydfil / Gorslas
Well what a shower today was! After yesterdays broken down train, a defective rail between Abercynon and Merthyr meant every other train was stopping at quakers Yard. I was on one of them, and saw TFW put on Teulu buses for xx:45 the hour from Abercynon and xx:15 the hour from Merthyr. However, the driver would not leave until 6pm which was insane it was for the interim service. I should complain to TFW as they are (we are) paying for this but will not get a reply so pointless. I have been getting home over half an hour late (not through any fault of my own) and no fun when you get up at 4am for a long walk before the first train in the morning!
 

Smwrff

Member
Joined
27 Dec 2023
Messages
254
Location
Cymru Fawr
Butetown Station will officially open on 13 December - but with very limited service (1 train per week?). Can not open for full service until the Queen Street modifications have been completed - but had to open in 2026 or else EU funding had to be returned.

Still.... small steps...
 

positron

Member
Joined
18 Oct 2022
Messages
704
Location
Cardiff
Parliamentary service for a brand new station for funding reasons is about as British as it gets I fear .

Surely the lack of 4 trains per hour will lead to money being given back?
 

Coleridge

Member
Joined
14 Mar 2023
Messages
180
Location
Penarth
Operating one service per week from Butetown (if that is indeed what is planned) might meet the letter of TfW's funding arrangement with the EU, but not the spirit.

You really have to wonder what is going on at TfW. Everything they touch turns to dust ('dust' is not the word I was originally going to use) at the moment, and it's difficult to get a straight - or even honest - answer out of them. No doubt they will trumpet the so-called opening of Butetown station as a great success, and probably not even acknowledge the less-than-ideal service frequency.

The entire Metro project is a very long way from what TfW has repeatedly promised us.
 

The exile

Established Member
Joined
31 Mar 2010
Messages
9,395
Location
Somerset
Operating one service per week from Butetown (if that is indeed what is planned) might meet the letter of TfW's funding arrangement with the EU, but not the spirit.

You really have to wonder what is going on at TfW. Everything they touch turns to dust ('dust' is not the word I was originally going to use) at the moment, and it's difficult to get a straight - or even honest - answer out of them. No doubt they will trumpet the so-called opening of Butetown station as a great success, and probably not even acknowledge the less-than-ideal service frequency.

The entire Metro project is a very long way from what TfW has repeatedly promised us.
Contractually (ie pay back the money or not) it’s the letter that counts.
 
Joined
15 Mar 2026
Messages
12
Location
Cardiff
It seems like what's happening down in the bay is slowing down progress in other areas of Cardiff too, like the opening of crwys road station for example, which I'm guessing isn't constrained by the same funding deadlines. If I were TFW I would've focused on that sooner as that would serve way more people than a station 200m up the line from an existing one
 
Joined
22 Jun 2013
Messages
601
It seems like what's happening down in the bay is slowing down progress in other areas of Cardiff too, like the opening of crwys road station for example, which I'm guessing isn't constrained by the same funding deadlines. If I were TFW I would've focused on that sooner as that would serve way more people than a station 200m up the line from an existing one
I think Crwys Rd would be busier than Butetown is expected to be initially, but maybe the construction is inextricably linked to the whole Bay line project. I think it'll become more relevant once Crossrail has been developed further, and once the 398s are going to all of the TAM lines (fingers crossed). Construction is supposed to begin at Crwys Rd once Butetown is finished next year.
 