Here's a summary of what's supposed to happen this year:
- 31st January: Aberdare toilet completion
- 9th Feb: Merthyr Vale and Treorchy toilet completion
- End Feb: Merthyr Tyfil, Abercynon & Tonypandy toilet completion
- March 23rd: Cardiff Bay branch wires to go live
- March 31st: Ty-Glas platform extension entry into service; Cwmbach and Llwynypia toilet completion
- April to mid-June: 398s enter service on Cardiff Bay - Pontypridd services
- July - September: 398s replace 756s on the TAM lines and 756s replace 231s and 150s on Rhymney/Bargoed <> Barry Island services
- August - high voltage connection of Ninian Park Feeder station to core valley lines overhead line network
- October - Bute Town station (note that it's written as two words) Platform 2 opening.
- Dec 13th: No 150s on the TAM lines, new faster timetable. (Note that 150s on Rhymney will still be around because they're still needed for the Vale of Glamorgan service)
- Various unspecified level boarding works are also listed, as are various signalling and track works that I don't understand from the relatively cryptic notes.
These project plans are intended to notify other industry bodies of the planned works, so TfW don't necessarily have to stick to them. But the plan and dates do capture a snapshot of what's expected at the time it was drawn up, so its fair to say that 398 introduction is definitely still on the agenda.