There was a story doing the rounds that they were planning to use Pacers with side plates to cover the wheels and engines. They reckoned they could run these at street level.
Now that I would have liked to see!There was a story doing the rounds that they were planning to use Pacers with side plates to cover the wheels and engines. They reckoned they could run these at street level.
Wouldn't have fancied hearing them going round tight corners on the on-street sections thoughNow that I would have liked to see!
Interesting that it says Treforest Station when there's no wires from there to Ponty? Do they just not acknowledge the gaps when it comes to the sections they consider live?Spotted yesterday morning at Penrhiwceiber station.
View attachment 143410
No wires up in Aberdare yet or there certainly wasn’t Sunday.Interesting that it says Treforest Station when there's no wires from there to Ponty? Do they just not acknowledge the gaps when it comes to the sections they consider live?
Pretty big milestone to get to. Merthyr branch is complete, aberdare branch is mostly (wonder why it's not energised north of Cwmbach yet?), so now it's just Treherbert, Rhymney (+ coryton) and the Bay branches left.
Well that would certainly explain it . Guess they must be keen to get something running under the wires sooner rather than later even if it's not all ready.No wires up in Aberdare yet or there certainly wasn’t Sunday.
Back in July the date given for the Treherbert line was December 29 and I haven't heard of any change.Well that would certainly explain it . Guess they must be keen to get something running under the wires sooner rather than later even if it's not all ready.
Does anyone know the go live date for the Rhonda wires?
I haven't seen any earlier expected reopening date than Feb. It is of course a good idea to switch the juice on as soon as the wires are ready to ensure that they stay there!A quick google comes up with late Jan/early Feb as the expected timeline for reopening of the line. Whether the line will be electrified at that point is of course a different question.
Presumably they'll have the 756s out asap, keep the 231s on Rhymney, and someone else (Cheltenham?) will lose out and get the 150s? Assuming the 170s and 175s will be gone too soon.
Coming up on that 7th October date any updates on if the Cwmbach to Aberdare section is finished yet?First document - "Consultation Document CVL G1 Network Change Proposal CVLNCCP01-G1-03-V1 for the Transformation Programme 19 06 2023"
Some key quotes (emphasis mine):
- The energisation of the OLE system Commissioning from Pontypridd to Aberdare has now changed from 24 June 2023 to 07 October 2023
- The energisation of the OLE system Commissioning from Abercynon to Merthyr Tydfil has now from 11 August 2023 to 07 October 2023
There is a week blockade starting Saturday closing Ponty-Merthyr & Aberdare so I wonder if that is related to finishing it off.Coming up on that 7th October date any updates on if the Cwmbach to Aberdare section is finished yet?

I thought it was from Sunday (to Merthyr anyway).There is a week blockade starting Saturday closing Ponty-Merthyr & Aberdare so I wonder if that is related to finishing it off.
So it is. Apologies, I thought it included the Saturday.I thought it was from Sunday (to Merthyr anyway).
Indeed they are with the locals, my grandfather an ex member of br staff loves them for being silent and smooth. Likewise most my family have commented on them.It's been suggested that the 231s will move to their intended route and the Rhymney Line will be downgraded back to 150s.
I don't know if that's true and I can't see it going down very well.
They haven't publicised the 231s being a stopgap but a change to 756s wouldn't be very noticable. A change back to 150s certainly would. From what I've heard from non enthusiasts the 231s are quite popular.
The report said a further application for prior approval was necessary to consider the use of this neighbouring land on a temporary basis to facilitate construction.
The temporary use of the land would include laydown, car parking, modular cabins and welfare buildings as well as vehicle manoeuvring, general construction areas and internal haul road (outwith Lloyd George Avenue).
Cardiff Council has granted prior approval subject to conditions under delegated powers.
https://x.com/SW_MetroUpdates/status/1711760973034291544?s=20There seem to be plenty of overnight closures on the Rhymney line now. Anyone know how work is progressing? Thanks.
Lots of vegetation clearance on the coryton line at least.The line is looking a lot more open after vegetation clearance prior to electrification works.