Twice yes, South of Cathays.There’s been an incident of theft with the wiring already?
Twice yes, South of Cathays.There’s been an incident of theft with the wiring already?
Surely that'd be north of Cathays as the wires don't even reach there, unless it was the ground level cables they nicked...Twice yes, South of Cathays.
Is it wishful thinking that the impeding Euro 2028 bid which will see Cardiff probably hold somewhere in the region of 6 games lead to lots of the inner city stations receiving upgrades and perhaps the speeding up of the development of Central?
The one I know of was south of Radyr and north of Llandaf - and not recent; the power's been on since May 20th!Surely that'd be north of Cathays as the wires don't even reach there, unless it was the ground level cables they nicked...
Surely that'd be north of Cathays as the wires don't even reach there, unless it was the ground level cables they nicked...
Another post on LinkedIn has confirmed the mast ID as "CAR/33/415", and that 1100 masts total are due to be installed over the Rhymney lines.
"According to Transport for Wales (TfW) the new £100m Taff’s Well depot where they were unveiled is currently being constructed and will become the home of the South Wales Metro (which TfW is delivering) providing electrical controls and signalling for the network as well as a maintenance depot for the new tram trains."
That equates to 22 m 65 ch which is Pontlottyn Station and two masts are indeed in place there. According to the 2020 plans north of Bargoed is non electrified.Another post on LinkedIn has confirmed the mast ID as "CAR/33/415", and that 1100 masts total are due to be installed over the Rhymney lines.
There is, somewhere in the 164 pages!That equates to 22 m 65 ch which is Pontlottyn Station and two masts are indeed in place there. According to the 2020 plans north of Bargoed is non electrified.
Is there an updated plan?
This equates to 22 m 65 ch which is Pontlottyn Station and two masts are indeed in place there. According to the 2020 plans north of Bargoed is non electrified.
Pre-2020 north of Ystrad Mynach was to be non-electrified - apart from Rhymney station area and sidings for charging up - so even Bargoed was an advance! However the November 2022 version attached shows the whole line electrified north of Ystrad - although as we know that almost certainly won't be strictly true....Is there an updated plan?
Objections have been raised by local residents on the Taff Vale Estate with regard to the scale of the bridge and ramp structure.
Technically improvements within the railway boundary do not require planning permission but a planning application was submitted in May.
There are various measures being proposed to mitigate the residents objections and of course our ecology friends.
The station will therefore probably be closed until these matters are resolved.
Both Quaker's Yard and Pentrebach loops are now signalled and operational. Had a northbound train passing ours at Quaker's Yard on Saturday as we were held there southbound following a disorder incident at Abercynon.
Sounds like it could be a while.
What a waste of time. They didn't need planning permission (aside from I think potentially a prior approval) and now this is all dragging on because of some NIMBYs. Bet the same people are complaining about bus replacements too.I notice Quakers Yard is now closed until September...
Of the current development, nothing. Some street running south of Cardiff Bay is likely in the future, along with a proposal to run a line to Cardiff Central via Callaghan Square off the Bay branch, which appears to have a lot of momentum in terms of funding. If you define tram operation as line of sight instead of being signalled then the Bay branch will move to that at some point in the current project.This all looks rather fab!
Which sections are envisaged as a tram (street running) if any.
It could be that the shoulders of the original two track formation have deteriorated in the 50 years or so since the lines were singled, so a more central position was simpler. Given cost overruns, I’m just happy to see the three branches north of Pontypridd still regaining a good proportion of the double tracking that was lost two generations ago.Taking a long term view, should further double tracking be needed on single track sections in a decade or two in order to uphold service levels, some of the masts may need to be moved, whereas had they positioned them slightly further back from where they are, it’s would be one thing less to do
Presumably it’s no more costly to sink a pile 2 metres further away from trackside although a wider mast arm will, but it then leaves room for an additional track at some later date, rather than to move everything
"Moving everything" probably isn't that difficult in this case. Following any necessary remediation works, new masts could be constructed at the edge of the formation where they don't interfere with anything that's there now, so although it's an extra task it shouldn't (in theory!) extend the timescales for any future double-tracking.Taking a long term view, should further double tracking be needed on single track sections in a decade or two in order to uphold service levels, some of the masts may need to be moved, whereas had they positioned them slightly further back from where they are, it’s would be one thing less to do
Presumably it’s no more costly to sink a pile 2 metres further away from trackside although a wider mast arm will, but it then leaves room for an additional track at some later date, rather than to move everything
Leta not fall into the trap of looking into the future, once this program is complete that’ll be it for our lifetime. Their not calling this a once in a generation upgrade for nothing, without the nasty, dirty EU this wouldn’t of happened funny how Wales then shots itself in the foot by voting leaveTaking a long term view, should further double tracking be needed on single track sections in a decade or two in order to uphold service levels, some of the masts may need to be moved, whereas had they positioned them slightly further back from where they are, it’s would be one thing less to do
Presumably it’s no more costly to sink a pile 2 metres further away from trackside although a wider mast arm will, but it then leaves room for an additional track at some later date, rather than to move everything
"Moving everything" probably isn't that difficult in this case. Following any necessary remediation works, new masts could be constructed at the edge of the formation where they don't interfere with anything that's there now, so although it's an extra task it shouldn't (in theory!) extend the timescales for any future double-tracking.
Agreed; just a gentle reminder to all that if anyone wants to discuss what might happen (and/or alternatives, such as why they aren't doing anything in the way they are doing), please can this be posted in a separate thread in the Speculative Discussion section. This thread is exclusively for updates. ThanksLeta not fall into the trap of looking into the future..

A pity Merthyr lost its second platform in (I think) 1996. Short-sighted given the arrangements now being put in place - but only with hindsight!Just to reinforce the quantum of the change here, back in the 80s the Merthyr Line north of Abercynon was completely single following removal of the loop at Black Lion. That was a total of 8.2 miles and meant that only an hourly service was possible. The Merthyr Vale loop restored 23% (1.9 miles) of that to double track, and thus enabled a half hourly service. The further enhancements which are now in operation means that 42% of the previous single line has now been redoubled, and of course the intent is a 15 minute frequency.
The remaining single track sections will each be around 1.5 miles in length, so even if trains present themselves at both ends simultaneously (the worst case) the delay should be minimal. And given the single track section just south of Merthyr implies reasonable turn around times there, holding the northbound train is unlikely to result in a knock on delay to the next southbound departure from Merthyr.
And at the same time lets not make perfection the enemy of progress.Leta not fall into the trap of looking into the future