1 This question relates to an automatic signalled section of track. Going
through this section the train passes signal 1 then 2 then 3 etc in that
order. All signals are currently displaying green. Under normal situations:

a) when would signal 1 turn to red?
b) when would signal 1 turn to single yellow?
c) when would signal 1 turn to double yellow?
d) when would signal 1 turn to green?

2 This question relates to a controlled signalled section of track. Going
through this section the train passes signal 1 then 2 then 3 etc in that
order. Under normal situations:

a) when would signal 1 display a proceed aspect?
b) when would signal 1 revert back to red.
c) When the overlap of number 2 signal became clear what would happen to number 1 signal?

Answers tomorrow night!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Tomnick

Established Member
Joined
10 Jun 2005
Messages
5,930
Unless I've missed something...

1a) (Normally?) When the train occupies the next track circuit in advance of the signal (which might not be until the far end of the overlap).

1b) When the train clears signal 2's overlap and signal 2 is proved to be at Danger.

1c) When the train clears signal 3's overlap, subject to the above.

1d) Assuming signal 4 is automatic: when the train clears that signal's overlap, again subject to the above.

2a) When the route has been set, all track circuits in the route clear, all points in the route and required for flank protection detected, any level crossings proved clear, next signal proved alight, approach control conditions satisfied.

2b) Depends on the installation, but often when the train occupies the next track circuit in advance.

2c) Normally nothing, unless the facility was provided to allow that signal to be worked automatically.
 

strange6

Established Member
Joined
9 Jan 2011
Messages
1,920
Location
Wigan, Greater manchester
Answers to the quiz!

This question relates to an automatic signalled section of track. Going
through this section the train passes signal 1 then 2 then 3 etc in that
order. All signals are currently displaying green. Under normal situations:

a) when would signal 1 turn to red? When the front wheels occupy the track
circuit beyond signal 1 overlap.
b) when would signal 1 turn to single yellow? When the rear wheels of the train
clear the overlap of signal 2
c) when would signal 1 turn to double yellow? When the rear wheels of the
train clear the overlap of signal 3
d) when would signal 1 turn to green? When the rear wheels of the train
clear the overlap of signal 4

This question relates to a controlled signalled section of track. Going
through this section the train passes signal 1 then 2 then 3 etc in that
order. Under normal situations:

a) when would signal 1 display a proceed aspect? If the conditions were
proven correct and the signaller had taken action to set the route.
b) when would signal 1 revert back to red. When the front wheels occupy the
track circuit beyond signal 1 overlap.
c) When the overlap of number 2 signal became clear what would happen to
number 1 signal? It would remain red until the signaller re-set the route.
--- old post above --- --- new post below ---
Unless I've missed something...

1a) (Normally?) When the train occupies the next track circuit in advance of the signal (which might not be until the far end of the overlap).

1b) When the train clears signal 2's overlap and signal 2 is proved to be at Danger.

1c) When the train clears signal 3's overlap, subject to the above.

1d) Assuming signal 4 is automatic: when the train clears that signal's overlap, again subject to the above.

2a) When the route has been set, all track circuits in the route clear, all points in the route and required for flank protection detected, any level crossings proved clear, next signal proved alight, approach control conditions satisfied.

2b) Depends on the installation, but often when the train occupies the next track circuit in advance.

2c) Normally nothing, unless the facility was provided to allow that signal to be worked automatically.

Not bad at all Tomnick! well done!
 