Signalling problems between Blackburn and Bolton resulted in there being delays of an hour or more during this morning's rush hour and no trains at all since soon after 10am. NRE doesn't go into any detail but is saying the problem won't be fixed until 1730.

Real Time Trains seems to be suggesting a track circuit failure may be the issue, although I know that isn't necessarily the case. However track circuit failures don't normally take so long to sort out, so I just wondered if anyone knows the nature of the problem. The issue seems to be at the Bromley Cross end, so I'm assuming that the recent upgrade and resignalling at Darwen isn't involved.

Apologies, I don't generally start 'why was I late for work' threads, but I wondered what the problem is!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

ComUtoR

Established Member
Joined
13 Dec 2013
Messages
9,562
Location
UK
Real Time Trains seems to be suggesting a track circuit failure may be the issue, although I know that isn't necessarily the case. However track circuit failures don't normally take so long to sort out

The track circuit failure the other day at St Johns took some time to sort out. They had to take a block to fix it.

How long to you believe track circuit failures "normally take" ?
 

Darren R

Established Member
Joined
26 Jan 2013
Messages
1,252
Location
Lancashire
The track circuit failure the other day at St Johns took some time to sort out. They had to take a block to fix it.

How long to you believe track circuit failures "normally take" ?

How long's a piece of string! :lol:

I can appreciate that the length of time to fix a track circuit failure varies enormously depending on as many variables as you can think of, but (in this neck of the woods at least! ;)) a couple of hours seems to do the trick. Nine hours seemed an inordinately long time, which is why I wondered what the problem was. Ordinarily I wouldn't think twice about it - sometimes stuff just goes wrong! :D
 

dnisbet

New Member
Joined
11 Feb 2015
Messages
2
This seems to still be going on most Monday mornings. First train through this morning was cancelled (but still came through platform) with the second train delayed by >30 mins.
There was a rail cleaner waiting at Bromley Cross to go up to Darwen also.
 