Annetts key
Established Member
For the LCP or 'emergency ' local panels that were on the area where I worked, the actual facilities varied, depending on the design. The rest of this post describes the two that I knew about. Both now removed.Based of locations I formerly worked the scope of the LCP was limited. Whilst in 'normal' operating mode they had control of signals protecting level crossings, the routes could be overridden by the respective controlling PSB.
However, when 'local control' was taken, it gave the signaller at that location control of loops and crossovers, without any intervention by the controlling PSB, though you then signalled trains at their direction. The usual instruction, when switched-in, was to work straight up and down unless advised. Each location was eexpected to take 'local control' for an hour or so each Saturday, for knowledge retention. You could be asked to switch-in at other times too.
Normal operation was that the main PSB controlled everything, the only thing that worked on the local panel was the indications and the on/off switch for the indications.
When in local mode, the main PSB had no control over any of the signalling controlled by the local panel. But the main PSB would continue to have valid indications if the remote control system (TDM) was operational.
On these local panels, only minimal circuitry was provided to try to avoid conflicting routes from being set. Unlike the far more complex circuitry at the main PSB which was designed to prevent stupid mistakes. So the signaller operating the local panel had to be more careful. The interlocking in any case would not allow a signal to show a proceed aspect unless it was safe.
On one emergency panel (W-s-M), a telephone concentrator and handset was provided so that all the SPTs and other lineside direct phones could be switched over.
One of these was at Weston-super-Mare, the other was at Filton Abbey Wood.
The W-s-M panel actually took control from the mechanical signal boxes in the area that were being replaced, before Bristol PSB A panel was ready. Only at a later stage of the resignalling did the PSB take control (I think it was only a couple of weeks).