As a follow up to this thread
Construction is now starting. First phase is to construct a compound, then to build a temporary alignment for the busy foot and cycle path. The bridge will assembled in the compound and craned into place, apparently using an overnight possession.
The accommodation crossing will remain, however this will become a POGO and will be secured using a keypad.