Scottish Electrification updates & discussion

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Strathclyder

Established Member
Joined
12 Jun 2013
Messages
3,819
Location
Clydebank
Prior to the operation of the Borders Railway what will the cascaded 156s and 158s be used for?

Also, what were the 'spare' 318s doing prior to their redeployment?
I think the 156s/158s will be used for strengthening other services on the network.

Same for the 318s as well, I think.
 
Last edited:

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
That is correct.

The Whifflet services do strange things from December, according to realtimetrains.
Both the Carmyle line services run to Milngavie via Central LL (replacing Lanark services which run to HL instead), with one starting back from Motherwell.
But the current local Cumbernauld-Motherwell service extends to Dalmuir via LL.
So Whifflet gets 3tph to LL via two different routes.
http://www.realtimetrains.co.uk/search/advanced/WFF/2014/12/15/0000-2359?stp=WVSC&show=all&order=wtt
 

thealexweb

Member
Joined
5 Jan 2014
Messages
1,106
I think the 156s/158s will be used for strengthening other services on the network.

Same for the 318s as well, I think.

Can anyone suggest any Scotrail routes that currently use sprinters that require a permanent capacity boost at this time?
 

thealexweb

Member
Joined
5 Jan 2014
Messages
1,106
Manchester Vic-Todmorden-Burnley?

There are dozens upon dozens of routes throughout England that deserve strengthening far more than most Scotrail routes but cascading is not an option till the franchise ends sadly :(
 

clc

Established Member
Joined
31 Oct 2011
Messages
1,326
Network Rail has been tweeting about the redevelopment of Queen St station and mentioned that the expansion of the concourse was necessary partly because of scope to increase service frequency on the low level line. I was wondering how many more trains could potentially run through QS LL (currently 8tph) if a turn back was built east of Partick - any thoughts?
 

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,424
Location
Salt & Vinegar
The Whifflet services do strange things from December, according to realtimetrains.
Both the Carmyle line services run to Milngavie via Central LL (replacing Lanark services which run to HL instead), with one starting back from Motherwell.
But the current local Cumbernauld-Motherwell service extends to Dalmuir via LL.
So Whifflet gets 3tph to LL via two different routes.
http://www.realtimetrains.co.uk/search/advanced/WFF/2014/12/15/0000-2359?stp=WVSC&show=all&order=wtt

All these changes look good, faster times from Lanark, Carluke and Wishaw to Glasgow are excellent news.

Whifflet and Cumbernauld services become integrated into the Argyle line / Hamilton circle properly and again new connections are created.

However one place which loses out is Holytown which loses its hourly connection to Motherwell and Hamilton. Given the way it was timed, Glasgow passengers will have caught the following Shotts line train anyway but it is a loss of service and connections compared to previous service.

Presumably someone has done some passenger travel pattern analysis and most Holytown passengers are travelling to Glasgow? I guess for Motherwell you'd get the bus anyway.

This gives us a new daily parliamentary to cover the Wishaw - Holytown route using the peak Carstairs extra service:
http://www.realtimetrains.co.uk/train/G50280/2014/12/15/advanced
http://www.realtimetrains.co.uk/train/G97152/2014/12/15/advanced

The Mossend South - Mossend East junction passenger service is also reduced from 1tph to 1tpd with the passenger service being the existing Motherwell - Edinburgh via Shotts peak time only service:
http://www.realtimetrains.co.uk/train/G98787/2014/12/15/advanced
http://www.realtimetrains.co.uk/train/G98785/2014/12/15/advanced
 

clc

Established Member
Joined
31 Oct 2011
Messages
1,326
The Scottish Government's draft budget for 2015-16 gives an indication that it's rolling programme of electrification will continue into CP6.

It's analysis of liabilities at Annex A confirms that the Scot Govt is allowing for RAB borrowing for network electrification to at least 2022. RAB will also fund other projects beyond those included in the 2012 HLOS, specifically Aberdeen to Central Belt, further phases of Aberdeen to Inverness and Highland Mainline.

It's pleasing to see a commitment to significant investment beyond 2019.

http://www.scotland.gov.uk/Resource/0046/00460440.pdf
 

matchmaker

Established Member
Joined
8 Mar 2009
Messages
1,868
Location
Central Scotland
Network Rail has been tweeting about the redevelopment of Queen St station and mentioned that the expansion of the concourse was necessary partly because of scope to increase service frequency on the low level line. I was wondering how many more trains could potentially run through QS LL (currently 8tph) if a turn back was built east of Partick - any thoughts?

Did QS LL not have 4 platforms in steam days?
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,896
Location
North
The Scottish Government's draft budget for 2015-16 gives an indication that it's rolling programme of electrification will continue into CP6.

It's analysis of liabilities at Annex A confirms that the Scot Govt is allowing for RAB borrowing for network electrification to at least 2022. RAB will also fund other projects beyond those included in the 2012 HLOS, specifically Aberdeen to Central Belt, further phases of Aberdeen to Inverness and Highland Mainline.

It's pleasing to see a commitment to significant investment beyond 2019.

http://www.scotland.gov.uk/Resource/0046/00460440.pdf

It is interesting to see the commitment to Whifflett electrification in the 2015/16 budget. Even the English know overheads are complete now.
 

ScotGG

Established Member
Joined
3 Apr 2013
Messages
1,585
Totally agree- now lets hope Westminster follows.

So everyone must go begging to Whitehall again and wait for their whims, dictates and interference. The sooner every region of England gets what the Scots get the better. Good on 'em for taking their chance and improving transport.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
It is interesting to see the commitment to Whifflett electrification in the 2015/16 budget. Even the English know overheads are complete now.

That's a little odd because NR has just finished wiring Rutherglen-Whifflet!
Electric trains start running in December.
 

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,424
Location
Salt & Vinegar
The Scottish Government's draft budget for 2015-16 gives an indication that it's rolling programme of electrification will continue into CP6.

It's analysis of liabilities at Annex A confirms that the Scot Govt is allowing for RAB borrowing for network electrification to at least 2022. RAB will also fund other projects beyond those included in the 2012 HLOS, specifically Aberdeen to Central Belt, further phases of Aberdeen to Inverness and Highland Mainline.

It's pleasing to see a commitment to significant investment beyond 2019.

http://www.scotland.gov.uk/Resource/0046/00460440.pdf

Good news. I think this now definitely secures the Shotts electrification for Dec 2019 as it's specifically mentioned in the CP5 plans.

Hopefully means the East Kilbride, Barrhead and Maryhill lines follow on smoothly in the period 2019-2022.

Will be interesting to see if the new franchise's depot and rolling stock strategy impacts on the plans. Specifically I wonder if we might see the City Union and Edinburgh South Suburban lines back on the agenda in order to assist with empty stock movements. South Sub especially may help with Edinburgh Waverley capacity if the new electric stock is confirmed as being based at Millerhill.

While the South Suburban electrification was removed from Network Rail plans by ORR a scheme to increase capacity at Waverley is included for CP5 so South Sub electrification scheme could be advanced under that funding stream if capacity benefits can be shown.
 

Photohunter71

Member
Joined
17 Jan 2012
Messages
576
Location
In a flat beside Niddrie West junction
I'd imagine electrification of the South sub loop line is going to happen very soon,after all,they are in the midst of gauge clearance on the sub for deep sea containers,(when will we start seeing this service?) I suspect those will be hauled by electric locomotives,so makes sense to electrify the afforementioned line.
 

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,424
Location
Salt & Vinegar
I'd imagine electrification of the South sub loop line is going to happen very soon,after all,they are in the midst of gauge clearance on the sub for deep sea containers,(when will we start seeing this service?) I suspect those will be hauled by electric locomotives,so makes sense to electrify the afforementioned line.

The ORR Periodic Review specifically excluded funding for South Sub electrification in CP5:
http://orr.gov.uk/__data/assets/pdf_file/0019/496/fd-annexes.pdf

ORR said:
The proposed list of projects in Network Rail's SBP, except for Carstairs and Edinburgh South Suburban electrification, meet the requirements of the HLOSs. These two projects, along with others that are not required by the HLOSs, could be funded through other sources and taken forward through our investment framework.

So if it is to be funded either Transport Scotland have to agree for it to be paid for from the ongoing electrification fund, or another funding source. There is money agreed in the HLOS for improving capacity at Waverley so this could be one route to progress happening.

At present though Network Rail does not have funding to electrify the route, only to gauge clear it. I'm sure alll gauge clearing work they do will have future electrification in mind but there may be some borderline structures that do not need work to gauge clear but would for electrification.
 

clc

Established Member
Joined
31 Oct 2011
Messages
1,326
The ORR Periodic Review specifically excluded funding for South Sub electrification in CP5:
http://orr.gov.uk/__data/assets/pdf_file/0019/496/fd-annexes.pdf



So if it is to be funded either Transport Scotland have to agree for it to be paid for from the ongoing electrification fund, or another funding source. There is money agreed in the HLOS for improving capacity at Waverley so this could be one route to progress happening.

At present though Network Rail does not have funding to electrify the route, only to gauge clear it. I'm sure alll gauge clearing work they do will have future electrification in mind but there may be some borderline structures that do not need work to gauge clear but would for electrification.

The CP5 Delivery Plan contains some encouraging info re Edinburgh Suburban Electrification: http://www.networkrail.co.uk/cp5-delivery-plan/cp5-enhancements-delivery-plan.pdf

Page 8 states:
"Network Rail is currently progressing the development of two projects contained in the Strategic Business Plan not specifically required to deliver the HLOS or included in the Final Determination. However, Carstairs Junction remodel and the Edinburgh Suburban Electrification projects will contribute to improving journey times and reducing carbon emissions as required by the Scottish Ministers HLOS and are therefore subject to further discussions with funders to determine how they will be funded for implementation in CP5."

Page 166 states:
"The Works have synergy with the planned electrification of the Edinburgh suburban lines early in CP5."

The Delivery Plan also states that Edinburgh suburban electrification is being considered for funding in CP5 from the Scottish Strategic Rail Freight Investment Fund (page 142) and from theScottish Network Improvement Fund (page 143).

From the above it does seem there is a good chance it will go ahead in CP5.
 
Last edited:

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
Costain and Morgan Sindall have been awarded the £250M contract to electrify the main railway line between Glasgow and Edinburgh.
http://www.nce.co.uk/news/transport...dinburgh-rail-electrification/8672144.article

And yet Carillion Powerlines was awarded the regional electrification framework contract for Scotland and the North East last year.
Carillion has just completed the Cumbernauld/Whifflet electrification.

The NR announcement talks about "core physical works".
Maybe it relates to route clearance and station upgrades rather then the wiring.
http://www.networkrailmediacentre.c...ded-as-main-engineering-works-begin-21b9.aspx
 

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,424
Location
Salt & Vinegar
And yet Carillion Powerlines was awarded the regional electrification framework contract for Scotland and the North East last year.
Carillion has just completed the Cumbernauld/Whifflet electrification.

The NR announcement talks about "core physical works".
Maybe it relates to route clearance and station upgrades rather then the wiring.
http://www.networkrailmediacentre.c...ded-as-main-engineering-works-begin-21b9.aspx

I believe they are entirely separate works contracts and Carillon will be starting advance works on the Shotts line electrification under the regional framework next year while EGIP is delivered by Costain separately.
 

NotATrainspott

Established Member
Joined
2 Feb 2013
Messages
3,304
https://twitter.com/NetworkRailEGIP/status/548915198883815424/photo/1

Providing electrification clearance at Carmuirs, adjacent to the Falkirk Wheel on the Grahamston line.

Before:

B54jdrqCUAAwDS3.jpg


After:

B54jdnDCMAAIYrY.jpg
 