Central Belt to Inverness Enhancement
Building on the outputs delivered in CP5 as part of Highland Main Line Phase 2 (hourly service to Glasgow/Edinburgh, around 10 minute journey time reduction and more efficient freight operations). This option supports 2043 Conditional Outputs for capacity, connectivity, and freight.
Purpose - To provide packages of timetable and infrastructure enhancement options to deliver incremental outputs, including
journey time reduction and improved connectivity, at a corridor level, working towards the 2043 Conditional Outputs.
Technical Description - The following interventions should be considered:
- Greenhill Upper Junction Grade Separation to increase the flexibility of the timetable by reducing the conflicts between Edinburgh/Glasgow and Stirling services at this location (£££)
- Fife Enhancements including a Dunfermline Bypass, Cowdenbeath to Thornton Line Improvements and pre-works for electrification (£££)
- Hilton Junction to Ladybank partial double tracking to increase capacity (£££)
- Ladybank Station remodel to four platforms beyond Ladybank junction (£)
- Dunblane to Perth Capacity Enhancement to increase signalling capacity and relocate signalling control to Edinburgh (£££)
- Dunblane turnback to install a crossover to the south of the station to reduce the time required to turn services (£)
- Stanley Junction remodel for a higher linespeed (£)
- Operational Acceptance Improvements to allow simultaneous acceptance of trains into both platforms at Highland Main Line stations (£)
- Inverness layout flexibility revisions to the existing track and platform layout to improve operational efficiency and flexibility, including introduction of new rolling stock (££).
Strategic Link - Central Belt to Aberdeen Enhancement, Perth Station Remodel, Rolling Programme of Electrification, Winchburgh Junction and Almond Chord.
Prioritisation assessment - Key junctions, such as Greenhill Upper and Haymarket, currently constrain the interurban and commuter timetables
and are crucial to creating a more flexible network that delivers shorter interurban journeys without reducing local connectivity.
Notes - Further timetable development will be undertaken prior to final publication.
Estimated cost range key:- £ = less than £50m; ££ = £50-100m; £££ = £100-250m; ££££ = more than £250m