• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Revised SWT Timetable due to bad Weather

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Stigy

Established Member
Joined
6 Nov 2009
Messages
4,964
Cant believe that SWT are running a better train service/timetable, revised snow/ice service now has 2 trains an hour going to Bournemouth/Weymouth from Totton (Southampton) instead of the 1 an hour. So the answer is if you want a better train service you need bad weather !:shock:


It's there for all to see,still cant belive it :|

http://www.southwesttrains.co.uk/uploads/table1-bournemouthandweymouth.pdf
Unless you live in Guildford, Farnborough, Aldershot, Ash, Ash Vale, Frimley, Camberley, Bagshot, Chertsey, Addlestone, Hampton Court, Thames Ditton, Bookham, Shepperton, Sunbury, Hampton, Upper Halliford or Kempton Park. :p
 

ralphchadkirk

Established Member
Joined
20 Oct 2008
Messages
5,754
Location
Essex
Unless you live in Guildford, Farnborough, Aldershot, Ash, Ash Vale, Frimley, Camberley, Bagshot, Chertsey, Addlestone, Hampton Court, Thames Ditton, Bookham, Shepperton, Sunbury, Hampton, Upper Halliford or Kempton Park. :p

Farnham, Bentley, Alton, Wanborough....
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,248
I think the standard NR snow plan in the area leaves the Guildford - Wokingham service to FGW. It means that the points at Aldershot South and North Jns don't have to be worked. Similarly, the FGW service then terminates at Redhill, so that less points at that junction have to be worked.
 

ajdunlop

Member
Joined
25 Jan 2009
Messages
218
It seems like a well thought out timetable on terms of keeping a good level of service but minimising delays my one gripe with it is why did they not put it on force on Thursday? So is this a NR timetable rather than one come up with by SWT? Is it up to SWT to decide of a nd when to run it and do all the operators also have one?
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,248
It seems like a well thought out timetable on terms of keeping a good level of service but minimising delays my one gripe with it is why did they not put it on force on Thursday? So is this a NR timetable rather than one come up with by SWT? Is it up to SWT to decide of a nd when to run it and do all the operators also have one?

NR are always responsible for the timetable, that's why the national online electronic version is NR's. I think though this is a joint plan, managed between NR and all the various TOCs in an NR area, Wessex in this case.
On the SWT site there was a reference to them running 'snow service table 6' so I guess there may be a range of plan, clearly with a network covering as far as Exeter there's a possibilty of totally different conditions at the extremities. There are similar sets of alternate timetables for engineering work etc, and spare paths in certain routes for long distance diversions - so that they can run the odd Waterloo to Weymouth via Havant for instance, there's space for it in the normal timetable...

The suburban branches that are cut all seem, AFAICT, to reduce the junction operation as mentioned earlier.

Maybe the weather forecast for Thursday didn't predict the conditions too well - you can imagine the grief they'd get if they closed routes too early?
 

wibble

Member
Joined
23 Jun 2010
Messages
636
NR are always responsible for the timetable, that's why the national online electronic version is NR's. I think though this is a joint plan, managed between NR and all the various TOCs in an NR area, Wessex in this case.

It would've been up to SWT to decise whether they use their snow plan on Thursday, not Network Rail.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,248
It would've been up to SWT to decise whether they use their snow plan on Thursday, not Network Rail.

I don't think I actually suggested that NR alone made the decision.

But I strongly suspect the decision gets made in the Wessex 'Integrated' Control Centre in practice, doesn't it?
 
Status
Not open for further replies.

Top