The thread title talks of re-starting HS2a, but has ever HS2a ever physically started in the first place?
Yes, in terms of buying land, erecting fencing, moving utilities and doing ground surveys - you can see some of the work on Google Maps.
As it had parliamentary approval and government go-ahead, there was a lot of detailed design and planning work done, with some enabling contracts let.
Network Rail had HS2-related work at Crewe in hand and there is a now-empty Balfour Beatty work site at Crewe (next to the Manchester junction).
No major civils contracts were let, although perversely the one railway contract to be let for Phase 1, for switches and crossings, was also scoped to include Phase 2a.
The aim was for all railway contracts to cover Phase 1 and 2a, but apart from this none have been let yet.
BBC R4 has just had Andy Burnham and Lord Berkeley on, discussing the National Audit Office report* that HS2 trains will be "slower than now" to Manchester.
Burnham wants his/Andy Street's lower cost line built, and is hopeful of the new government progressing this idea.
Berkeley (a long-time opponent of the HS2 design and project) wants the trains reconfigured and Chris Gibb's plan adopted (ie Pendolinos on HS2) before any new line is built.
But really, no-one has a clue how to get out of the current abject state of the project.
The government is not ready to say anything positive about HS2, until it has reviewed all the costs and its other priorities.
Reading Modern Railways (Aug), it says the old DfT/Treasury had approved the construction of the OOC-Euston tunnels, but election purdah meant it could not be announced.
The new government will take its time to review all HS2 work before making a decision.
*
Government must reset the HS2 programme successfully to avoid repeating past failures and to maximise value for money.
www.nao.org.uk
Key Facts:
October 2023 the government announced decisions on the High Speed Two (HS2) programme to:
• complete Phase 1 (London to Birmingham);
• cancel the rest of the railway (Phase 2); and
• revise how it will fund and deliver the London terminus station at Euston
Between 2029 and 2033 when the Department for Transport (DfT) expects Phase 1 of the programme to start running between Birmingham and Old Oak Common, as the interim London terminus. DfT has not yet set a revised date for when it expects HS2 services to run from London Euston
£30.1 billion (2019 prices) DfT’s and High Speed Two Limited’s (HS2 Ltd’s) total spend on the programme as at the end of March 2024 (£27.8 billion on Phase 1)
£44.6 billion (2019 prices) current funding envelope for Phase 1, which both HS2 Ltd and DfT estimate will not be sufficient
£45 billion to £54 billion (2019 prices) DfT’s range for the estimated total cost to complete Phase 1 (prior to the October 2023 decisions). HS2 Ltd’s estimate is £49 billion to £57 billion (2019 prices)
£592 million programme spend on land and property along the Phase 2 route as at the end of March 2024, that is no longer needed for HS2
179 parcels of agricultural land, across 63 farms, that HS2 Ltd will potentially dispose of in its first phase of disposals
Up to £100 million (2024 prices) HS2 Ltd’s estimate of the cost of remediation to close down sites where early works had already begun on Phase 2.
Edit:
There's this summary on page 21 of HS2 Ltd spend on land/property purchases (to March 2024):
Phase 1: £3075 million, 700 properties, land 59 sq km
Phase 2 (west and east): £592m 1001 properties, land 17 sq km
Of which Phase 2a was £224m, 251 properties, and all 17 sq km of land
Phase 2b west (ie Crewe-Manchester) was £205m, 195 properties, no land
Phase 2b east (ie Water Orton-Leeds) was £164m, 555 properties, no land
So that's £369m spent on property on Phase 2b (west and east) before any parliamentary approval for the project.
On the west side, that probably includes land for Piccadilly HS2 station (the BT/old post office building, I think).
What can they have possibly bought on the eastern leg for £164 million, when the route was not even properly defined?