Because the current service has a 4 minute turnround time at Colne. Going any further is going to need an extra unit.
Thats pretty much expected, my point was about the 45 minute layover!
No chance - Barnoldswick doesn't even meet Altnabraec's reopening criteria - that's a starter for 10.
My suggestion of opening a line to Barnoldswick was primarily somewhere to extend services to instead of running every service to Skipton and back since commuter flows are stronger in the opposite direction! Isn't SELRAP proposing a new station at Earby anyway that has a population of 4,387 ?
There is also the problem of what services serve the line if reopened. SELRAP want it double tracking but also aspire for existing Skipton services to be extended to Rose Grove (20KM) which will require electrification unless the 333's on the Aire Valley are replaced! Having a rail head where electric services could terminate at Barnoldswick means that could effectively half that whilst still providing cross boundary services, if it was single track from there to Skipton you could bring the costs down further although SELRAP want it double tracking throughout!
Personally I don't see why it needs to be double track throughout to achieve a half hourly frequency in line with SELRAPs ambitions! Although I think it would be beneficial to double track the existing line from Rose Grove to Colne or Barnoldswick if extended.
If it was extended then I think the whole project would be better off broken down into 3 stages.
1) Extension (to B) and double tracking
2) Eastern half to Skipton to facilitate freight
3) Electrification Westwards to (B) facilitate electric services.