When a Rail Crane is in use, not a road railer, and a copy of the Lift Duty chart is fitted to the exterior of the crane as a reminder for the controller.
Is there a requirement for this chart to be fully visible?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Old Timer

Established Member
Joined
24 Aug 2009
Messages
3,702
Location
On a plane somewhere at 35,000
When a Rail Crane is in use, not a road railer, and a copy of the Lift Duty chart is fitted to the exterior of the crane as a reminder for the controller.
Is there a requirement for this chart to be fully visible?
The Duty Chart must be available for the Crane Controller / Crane Supervisor to confirm any lift plans and jib settings.

It is not necessary for this to be displayed on the outside of the crane, it can be held as a separate document within the cab, or indeed can be within the cab.

The most important thing is that the information is available.

Presumably someone is arguing differently ?
 

Ploughman

Established Member
Joined
15 Jan 2010
Messages
3,099
Location
Near where the 3 ridings meet
No
I realise about the lift plan and details being available for the CC.
However I am part of a team looking after a 45 ton steam crane.
Somebody has installed a fitting that partially obscures the fitted duty plate on the side of the crane. We are of the opinion that this fitting needs relocating and may contravene PUWER.
 