It does - be useful for the North Wales Coast and an extension of some services to Shotton and Flint (though I was called a lying ******* when I suggested this was looked at as part of the business case for the North Wales Coast electrification).

Well you certainly weren't a liar.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

urbophile

Established Member
Joined
26 Nov 2015
Messages
2,474
Location
Liverpool
In view of the aspiration to re-open the Wapping and/or Waterloo tunnels and link St Helens, Wigan etc into Merseyrail, dual voltage trains would be essential. Even if that proposal has slipped down the priority list somewhat.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,657
More big delays yesterday - 3rd rail out of alignment at Preston Park.

More big delays today - flooding at Clapham Jn (Sussex side) where the lines are fit to be opened but the presence of the live third rail is preventing it. (Acknowledging that there are lots of flood related delays today for other reasons too).
 

Deepgreen

Established Member
Joined
12 Jun 2013
Messages
7,461
Location
Gomshall, Surrey
Also flooded fast lines at Wimbledon - I suspect exacerbated by possible drainage leaks from the multi-storey car park above. The down Victoria slow at Clapham Junction was a river flowing towards the already submerged junction with the WLL. More torrential storms expected this afternoon - joy (much though I love a thunderstorm).
 

A0

On Moderation
Joined
19 Jan 2008
Messages
7,751
More big delays yesterday - 3rd rail out of alignment at Preston Park.

More big delays today - flooding at Clapham Jn (Sussex side) where the lines are fit to be opened but the presence of the live third rail is preventing it. (Acknowledging that there are lots of flood related delays today for other reasons too).

You mean third rail infrastructure is liable to failure ? Surely not, after all there are so many,ahem, armchair experts here who keep telling us that third rail isn't susceptible to the kind of problems OHLE is. Particularly after the lightning strike around MK last week - where such storm conditions could only affect OHLE equipped lines........
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,657
All power off Greenwich due to people on the tracks.... Can't happen with OLE.

(Bored already of doing this)
 

A0

On Moderation
Joined
19 Jan 2008
Messages
7,751
All power off Greenwich due to people on the tracks.... Can't happen with OLE.

(Bored already of doing this)

Now to be fair you *could* leave the power on and just hope they don't stumble over the conductor rail.

Clearly if they do it makes an unpleasant mess which someone has to clear up, but again, our armchair experts don't believe that to be a problem.

Just to be clear - I have found a dead body, though not one which had suffered a major trauma - and I can assure any poster here who hasn't been through that, finding any dead body is traumatic enough.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,657
However, if people are on the tracks, even with OHLE, it must expected that no trains would move.

They would be moving, albeit at caution. And as soon as it is reported that no one is on the lineside, normal working is resumed (and there is no need to go through the process of recharging the power).
 

DY444

Member
Joined
16 Sep 2012
Messages
138
All power off Greenwich due to people on the tracks.... Can't happen with OLE.

(Bored already of doing this)

Remind me. Was it last week or the week before that the ole between Farringdon and Elstree was isolated in the evening peak due to an individual found riding on a freight train?

I appreciate the technical advantages of ole but it is not wholly free from its own reliability, weather and trespass issues either :)
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,610
Location
Nottingham
Remind me. Was it last week or the week before that the ole between Farringdon and Elstree was isolated in the evening peak due to an individual found riding on a freight train?

I appreciate the technical advantages of ole but it is not wholly free from its own reliability, weather and trespass issues either :)

I think the point here is that the OLE only needs to be isolated in the fairly rare event of someone climbing onto a train or some other place where they are putting themselves at risk.

Third rail needs to be isolated whenever unauthorised people are reported on or near the track, which is much more frequent. And has the possible consequence of people in stranded trains pulling the emergency handles and going out onto the track. Then other bits of third rail may have to be isolated, so more trains are stranded, so more people pull the emergency handles and go out onto the track...
 

XDM

Member
Joined
9 Apr 2016
Messages
483
And the terrible delays continue at Paddington due to the 25kv gantry damage. Of course earlier,trains were stopped for hours because of OHL damage near Didcot, pain without any pleasure as not yet in service.
 

A0

On Moderation
Joined
19 Jan 2008
Messages
7,751
Of course earlier,trains were stopped for hours because of OHL damage near Didcot, pain without any pleasure as not yet in service.

What was the root cause? If it was the inclement weather then the 3rd rail network has been impacted at least as much.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,242
What was the root cause? If it was the inclement weather then the 3rd rail network has been impacted at least as much.

Installation issue, I think this happened before the overnight weather issues. Probably something accidentally hanging down into the path of trains. It had been mentioned yesterday in the GW electrification thread.
 

jadmor

Member
Joined
26 Nov 2013
Messages
154
I see that scotrail are attributing overhead supply damage at Newton to bird strikes. I have never heard of this happening before, has anyone any comments on this?
 

Deepgreen

Established Member
Joined
12 Jun 2013
Messages
7,461
Location
Gomshall, Surrey
I see that scotrail are attributing overhead supply damage at Newton to bird strikes. I have never heard of this happening before, has anyone any comments on this?

I've not heard of this on the railway before, but I had the misfortune many years ago to witness a swan flying into a national grid line strung between pylons. A horrible sight.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,657
I see that scotrail are attributing overhead supply damage at Newton to bird strikes. I have never heard of this happening before, has anyone any comments on this?

Happens all the time; seen it happen myself. Rarely does it cause OLE damage though - this happens either with a high speed bird, or something bigger than a pigeon somehow bridging an insulator.
 

childwallblues

Established Member
Joined
3 Jul 2014
Messages
3,814
Location
Liverpool, UK
Not if Merseyrail are told to procure dual power EMUs like every other operator on NR track.

Edit: I've just checked and find that Bidston to Wrexham is about 50Km so 3rd rail wouldn't even stand up to a fairly equivocal comparison with OLE. Add in the safety issues and it would be turned around at the door. Looking at the local geography, it wouldn't be unreasonable to expect the line south from Wrexham to be electrified at some point in the future so the case for electrifying from scratch a long 50Km stretch with an obsolete system when the rest of the network south as far as the Thames would be OLE only would just be rejected outright.

Quite a few years ago Merseyside PTE asked Network Rail for a quote to electrify from Bidston to Wrexham. I understand that it was £80M for OHLE and a whopping £207M for 3rd rail!
 

XDM

Member
Joined
9 Apr 2016
Messages
483
It's well known among electricians that if you do not want to do a job you never say no,you quote a price five times more than you normally would. Very occasionally a mug falls for it & it pays for a shooting lodge in Scotland.
In the past Network Rail/Railtrack wanted to do very little. But the mug,ultimately our children on the NR credit card,fell for it. The benefit,though, is more electrification but at staggering prices re the past & the world.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Quite a few years ago Merseyside PTE asked Network Rail for a quote to electrify from Bidston to Wrexham. I understand that it was £80M for OHLE and a whopping £207M for 3rd rail!

Didn't steel sleepers play a part in that? How much does replacing all the sleepers cost?
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,610
Location
Nottingham
It's well known among electricians that if you do not want to do a job you never say no,you quote a price five times more than you normally would. Very occasionally a mug falls for it & it pays for a shooting lodge in Scotland.
In the past Network Rail/Railtrack wanted to do very little. But the mug,ultimately our children on the NR credit card,fell for it. The benefit,though, is more electrification but at staggering prices re the past & the world.

If third rail is such as good idea why do you think all the experts at NR, ORR etc are dead against it? I really don't see what they would have to gain by not putting forward a system that is better, cheaper or whatever.
 

Domh245

Established Member
Joined
6 Apr 2013
Messages
8,426
Location
nowhere
If third rail is such as good idea why do you think all the experts at NR, ORR etc are dead against it? I really don't see what they would have to gain by not putting forward a system that is better, cheaper or whatever.

Ignoring experts seems to be the flavour of the month.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,021
Location
St Albans
There seems to be a little resistance to 3rd rail not having a future with regard to new builds

On an 8000amp low(er) voltage circuit, it only takes a very little resistance to make it very expensive and financially unjustifiable. :)
 