This is a frequent and frustrating occurance on a Sunday evening:
http://www.realtimetrains.co.uk/train/P07147/2013/07/14/advanced
http://www.realtimetrains.co.uk/train/P05693/2013/07/14/advanced
Essentially, 1W08 is, as usual about 10 late and as a result 2E46 is held at Norton Junction for about 10 minutes in order to let 1W08 pass.
Is this done because of a lack of platform space or something?
Also, given that this train is 10 minutes late into Worcester probably about as often as its on time, would it not make sense to re-time it? This would have other benefits - during the week, 2E46 (or a train in the same path!) actually runs to Great Malvern. On Sundays it goes only as far as Worcester and instead 1W08 runs through to Hereford.
But there is no connection from 2E46 to 1W08 meaning that if you are travelling from Cheltenham and stations South to Malvern and Hereford you face a 1 hour 20 minute wait at Worcester on a Sunday - make the same journey on the same train on a weekday and you get straight through.
It seems to be that re-timing 1W08 would:
a) Stop it being late, constantly
b) Stop it holding up an on-time 2E46
c) Remove the 1 hour 20 minute gap for people travelling to Malvern and Hereford by allowing 2E46 to connect with 1W08.
I'm sure there is a fairly simple explanation for why none of this is possible, but I fancied a rant. Sunday connections to and from the Malverns to the South West are fairly terrible in both directions with lengthy (1 hour plus) waits at Worcester (The other direction there are no longer any connections since the re-jig of the LM Hereford services broke all the connections at Worcs with the FGW Bristol services).
http://www.realtimetrains.co.uk/train/P07147/2013/07/14/advanced
http://www.realtimetrains.co.uk/train/P05693/2013/07/14/advanced
Essentially, 1W08 is, as usual about 10 late and as a result 2E46 is held at Norton Junction for about 10 minutes in order to let 1W08 pass.
Is this done because of a lack of platform space or something?
Also, given that this train is 10 minutes late into Worcester probably about as often as its on time, would it not make sense to re-time it? This would have other benefits - during the week, 2E46 (or a train in the same path!) actually runs to Great Malvern. On Sundays it goes only as far as Worcester and instead 1W08 runs through to Hereford.
But there is no connection from 2E46 to 1W08 meaning that if you are travelling from Cheltenham and stations South to Malvern and Hereford you face a 1 hour 20 minute wait at Worcester on a Sunday - make the same journey on the same train on a weekday and you get straight through.
It seems to be that re-timing 1W08 would:
a) Stop it being late, constantly
b) Stop it holding up an on-time 2E46
c) Remove the 1 hour 20 minute gap for people travelling to Malvern and Hereford by allowing 2E46 to connect with 1W08.
I'm sure there is a fairly simple explanation for why none of this is possible, but I fancied a rant. Sunday connections to and from the Malverns to the South West are fairly terrible in both directions with lengthy (1 hour plus) waits at Worcester (The other direction there are no longer any connections since the re-jig of the LM Hereford services broke all the connections at Worcs with the FGW Bristol services).