Recently these sidings have been cleared of all the redundant DB wagons, anyone know what's in the pipeline, if anything?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Could it be anything to do with the proposal to realign the Leeds-York line at Neville Hill to increase the linespeed as part of the TRU?l
 

CrickUK

Member
Joined
23 Aug 2017
Messages
31
Site investigation works are progressing in this area, there is a drilling rig undertaking bore hole work
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,380
Could it be anything to do with the proposal to realign the Leeds-York line at Neville Hill to increase the linespeed as part of the TRU?l
Correct. The mainline will be moved over to where the old wagons were stored. The ‘old’ mainline will then eventually become part of Neville Hill depot, where the depot will also at same time under go redevelopment.

Lead to believe that as part of all this, the Depot will be completely closed.

This Christmas the Road bridge at east end of depot will be replaced, and will be 4 tracks wide
 

Mag_seven

Forum Staff
Staff Member
Global Moderator
Joined
1 Sep 2014
Messages
12,010
Location
here to eternity
As stated above this is part of the Transennine Route Upgrade (TRU) the thread for which can be found here:

 