The problem with temporary facilities is that they’re expensive as all the function of a permanent facility has to be provided at most of the cost of the permanent facility. It’d probably be more cost effective to just build a permanent one rather than trying to meet fire regs etc with a flimsy, life limited structure.I'm not sure how attractive it would be on that side, almost all of Oxford, plus the car park and bus stops are on the eastern side. No doubt people will use a Western entrance, but most footfall will continue to be via the existing entrance.
I'd have thought that space for a coffee cart would probably meet the likely demand on the western side. Which doesn't need a huge amount of space, and could even be outside.
If it becomes the main entrance during a rebuild of the existing then temporary facilities could probably be provided.
Thanks for finding that. Probably first time I've looked at that in 'depth'.Previously platform 4 had a coffee shop/newsagent, which seems the minimum set you’d want for passengers coming through that entrance.
https://gat04-live-1517c8a4486c4160...5_-_design_and_access_statement80251547_1.pdf Is the current design which is presumably what they’re reconsidering.
A tunnel to the other side would be running under the live railway and you’d have to at least partially rebuild the main station building to have a subway entrance on that side. That’s a considerably more complex piece of work than a subway under an unbuilt track.Also a strange choice: not building the tunnel through to the other side - meaning it's of no value for the southbound platforms and the bridge remains at capacity. Looks like they've already done one pass of cost-cutting! They do say that it's a possible future addition.
It has also been discussed earlier in the thread, around March 2023, post #182 onwards.Thanks for finding that. Probably first time I've looked at that in 'depth'.
It looks like one retail unit only, in that design (july 2021) - and it has the living roof - so this is prior to 'value engineering'. Soon enough there'll be a little shed / porta-horse-box selling coffees out the front, and no retail, but hey, it works.. they'll just need to put it in their artist visualization (plus add a few rough sleepers, also curiously omitted), and it's job done!
Also a strange choice: not building the tunnel through to the other side - meaning it's of no value for the southbound platforms and the bridge remains at capacity. Looks like they've already done one pass of cost-cutting! They do say that it's a possible future addition.
I suspect a three island layout (plus bays) just cannot be built on the existing footprint, assuming the position of the six tracks over Botley Road is now settled, so the two through tracks in the middle of the layout will never gain platform faces.In the longer term a decent entrance there would make the job of replacing the existing (and extending P2 over the bridge) much easier. I would imagine the ultimate crayon creation would be something with most of the facilities on a Reading style transfer deck with 3 Island platforms (1 becoming 2 north facing bays for EWR).
The extra through line would go over the footbridge span and straight through the middle of the existing station building. The through lines are unaffectedI suspect a three island layout (plus bays) just cannot be built on the existing footprint, assuming the position of the six tracks over Botley Road is now settled, so the two through tracks in the middle of the layout will never gain platform faces.
I know that, but that still only produces a two island station. The suggestion I was referring to was for a three island layout with additional bays… I was assuming a third ‘island’ being suggested meant another pair of through platforms.The extra through line would go over the footbridge span and straight through the middle of the existing station building. The through lines are unaffected
Oh right, got you. For an updates thread this is going in some weird directionsI know that, but that still only produces a two island station. The suggestion I was referring to was for a three island layout with additional bays… I was assuming a third ‘island’ being suggested meant another pair of through platforms.
The Cowley plan includes putting back the up relief between north Hinksey and south Hinksey, and reversible signalling. Therefore, Cowley > Marylebone trains can use platform 3. And Milton Keynes <> Oxford trains (whether or not trading under the absurd brand name East West Rail) can use platforms 1 and 2. Platform 5 would be Nice to Have for hourly Oxford <> Bristol.Given that Cowley and EWR will effectively need P5 how informed are Paul Clifton's comments?
The line speeds (there’s a drawing way back in this thread), confirm that Platform 5 will be the primary northbound through platform.The Cowley plan includes putting back the up relief between north Hinksey and south Hinksey, and reversible signalling. Therefore, Cowley > Marylebone trains can use platform 3. And Milton Keynes <> Oxford trains (whether or not trading under the absurd brand name East West Rail) can use platforms 1 and 2. Platform 5 would be Nice to Have for hourly Oxford <> Bristol.
I see your Oxford and I raise you Sunderland...Given how many outlets currently sit empty in recently rebuilt/refurbished stations I'm not exactly surprised that retail is being reconsidered.
I think p4 is for terminating from south, and p5 for through northbound services (excluding to Parkway)The Cowley plan includes putting back the up relief between north Hinksey and south Hinksey, and reversible signalling. Therefore, Cowley > Marylebone trains can use platform 3. And Milton Keynes <> Oxford trains (whether or not trading under the absurd brand name East West Rail) can use platforms 1 and 2. Platform 5 would be Nice to Have for hourly Oxford <> Bristol.
I see your Oxford and I raise you Sunderland...
Hawkins\Brown wins £2.6m job to design Oxford station masterplan
By Tom Lowe7 September 2026
Oxford station
Scheme to include offices, life sciences and housing
Hawkins\Brown has been awarded a £2.6m job to design the redevelopment of Oxford station and the surrounding area.
Or, in fact, of everything except the station. But it's getting very confusing, all this masterplanning...I just spotted this one from last week. A redesign of the current station
Network Rail is seeking to appoint a suitably qualified and experienced architectural practice to lead the design and planning application for the redevelopment of Oxford Station and its surrounding area. This commission forms a critical part of the Oxford Station Masterplan, which aims to deliver a new vision for the station environment, supporting Oxford’s growth as a national rail hub and global innovation centre.
Scope of Services:
• Masterplanning: Develop and evolve previous scheme proposals to create a new, mixed-use masterplan that maximises value, integrates operational railway requirements, and aligns with Oxford City’s development and regeneration aspirations.
• Design Leadership: Act as lead architect for the masterplan, coordinating with specialist consultants and stakeholders to deliver a comprehensive design solution, including station entrances, public realm, multi-storey car park, cycle hub, offices, life sciences, hotel, and residential elements.
• Planning Application: Prepare and submit a detailed planning application for Phase 1, including all necessary supporting documents, reports, and stakeholder engagement as required by the local planning authority.
• Stakeholder Engagement: Collaborate with Oxford City Council, Oxfordshire County Council, Network Rail, train operating companies, and other key stakeholders throughout the design and planning process.
• Sustainability: Embed best practice in environmental, social, and governance (ESG) objectives, targeting high levels of certification (e.g., BREEAM, WELL, NABERS, BNG, embodied carbon).
Key Deliverables:
• A new illustrative masterplan for the Oxford Station area, including phasing and delivery strategy.
• RIBA Stage 2+ design report for the first phase of development.
• Full planning application for Phase 1, including all required technical and supporting documentation.
• Coordination and integration of specialist inputs (e.g., transport, sustainability, heritage, engineering).
• Ongoing design and technical support through the planning determination period.
The contract will be let under the NR26 NEC4 Professional Service Short Contract (PSSC).
The scope of this procurement covers the development of the Oxford Station Masterplan and the delivery of a detailed planning application for Phase 1. Phase 2 services are entirely optional and may not be instructed. Any extension to include Phase 2 will be subject to separate approval and explicit instruction by Network Rail. The estimated total value and contract term stated in this notice is inclusive of both Phase 1 and the optional Phase 2.
Full details of the scope, deliverables, and requirements are provided in the procurement documents within the tender Pack.
Award Detail
1 Hawkins Brown Architecture (London)
Reference: 1
Value: £2,150,000
Oxford is slightly more popular with tourists and visitors than Sunderland, I suspectApart from the buffet on Platform 4, which was possibly shut due to the impending station rebuild as much as due to lack of custom, are there any empty retail units at Oxford station? There are certainly, still, WH Smith, Greggs, M&S, Upper Crust, Costa and Pret a Manger, all of which look busy whenever I pass through.
Oxford is slightly more popular with tourists and visitors than Sunderland, I suspect