Oxford Corridor Phase 2 & Platform 5 updates

djox

Member
Joined
25 Jan 2025
Messages
78
Location
Oxford
According to the latest Network Rail update firstly good news NR and Kier confirmed that the new pedestrian walkway will be opening this weekend, so actually hitting target of 31 August, which is a surprise but welcome.

The other main update is there will be planned reductions in service of GWR and Cross Country around Oxford travelling on the through railway lines on Sundays over September and October and full closure on 2 Sundays in November, as well as the better publicised closure in February.

Can anyone see details of this as GWR and Cross Country websites don't seem to be mentioning it, planner websites seem to have it though. Plan of reduction and closures of Oxford through lines
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

davetheguard

Established Member
Joined
10 Apr 2013
Messages
1,938
The new platform canopy has been scrapped

In terms of additional railway infrastructure, given the cost & time overruns, what exactly will now be delivered by this scheme other than a wider decked Botley bridge allowing space for an extra track to a planned new down platform?

The new downside entrance has been dropped, hasn't it?

Will the new down (northbound) platform & track still be delivered as part of the present works?
 

djox

Member
Joined
25 Jan 2025
Messages
78
Location
Oxford
In terms of additional railway infrastructure, given the cost & time overruns, what exactly will now be delivered by this scheme other than a wider decked Botley bridge allowing space for an extra track to a planned new down platform?

The new downside entrance has been dropped, hasn't it?

Will the new down (northbound) platform & track still be delivered as part of the present works?
At the moment the plan is a new walkway under bridge (open by this weekend), replace railway bridge adding new spans (Feb 2026) open Botley Road(Aug 2026?) then redevelopment of station up to 2029, which should include a new Western entrance and 5th platform, but don't hold your breath as the money may have run out by then.
 

davetheguard

Established Member
Joined
10 Apr 2013
Messages
1,938
At the moment the plan is a new walkway under bridge (open by this weekend), replace railway bridge adding new spans (Feb 2026) open Botley Road(Aug 2026?) then redevelopment of station up to 2029, which should include a new Western entrance and 5th platform, but don't hold your breath as the money may have run out by then.

Thanks for the update.

The new bridge & walkway underneath it are very welcome. But it looks like the railway will not really gain very much at all from the pared-down scheme as it stands. Jam tomorrow.
And at a cost of huge disruption in Oxford.

Still I guess the station redevelopment & expansion will be easier & cheaper with the new bridge in place if the money can be found in future.

Let's hope the present platforms can cope with the extra trains off East West Rail.
 
Last edited:

Nicholas43

Member
Joined
16 Jun 2011
Messages
646
Location
Radley
The presentation to councillors in July 2025 (available on Network Rail's Oxfordshire Connect webpages) included this (reformatted for legibility, I hope):
Future works to enable East West Rail
These are expected to include the provision of new Platform 4/5 and a Western Entrance required to support increased train services and passenger numbers.
Construction of remaining rail: scope paused to allow full focus on re-opening Botley Road as early as possible.
Works [i.e. planning?] progressing well to re-phase future rail works.
Key areas of focus:
• Validation of value for money following historic cost increase (associated with Botley Road), whilst maintaining core functionality.
• Validation of programme and price ahead of securing funding. [my italics]
• Increasing delivery certainty – undertaking additional surveys and progressing key areas of design.
Indicative Schedule - subject to funding release:
2025 to mid 2026:
• Increase delivery confidence
• Validate scope, price and programme
• Secure funding
2026 to 2029:
• Onboard contractor
• Complete Western Entrance design
• Construct Platform 4/5, Western Entrance and associated highways works.
It seems that we will have to be patient.
 

WilloughbyGC

Member
Joined
18 Oct 2017
Messages
19
All up a fairly catastrophic case study in rail/road/utilities project management. Years late, staggering levels of local disruption, and so overbudget that the whole purpose of the project - a fifth platform and western entrance to relieve current congestion (not just future EWR services as the NR spin suggests) may now never happen. Its no wonder that Treasury is sceptical of such 'enhancements'.
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,610
What a cluster. All that and no second entrance or additional platform / capacity. Laughable.

Really does feel like a big bang project should take its place (Cowley, wires to Didcot, two new through platforms inc main rebuild) - if there was ambition enough.

It feels like this type of development gets successfully completed in Cambridge.
 

Mikey C

Established Member
Joined
11 Feb 2013
Messages
8,240
All up a fairly catastrophic case study in rail/road/utilities project management. Years late, staggering levels of local disruption, and so overbudget that the whole purpose of the project - a fifth platform and western entrance to relieve current congestion (not just future EWR services as the NR spin suggests) may now never happen. Its no wonder that Treasury is sceptical of such 'enhancements'.
It's a mini HS2...
 

Xavi

Member
Joined
17 Apr 2012
Messages
854
Some people need to remember the facts before criticising the project team.

During the excavation, they uncovered previously undocumented water mains, a large inverted brick drainage structure, and numerous unknown utility cables. These weren’t in any plans.

The team had to:

• Divert a critical trunk water main that supplies much of Oxford.

• Coordinate with Thames Water on design approvals and connection points, which caused delays.

• Work around environmental constraints and structural weaknesses near Osney Bridge.

These are not failures—they're unforeseen engineering challenges. And the people managing them are doing so under intense public scrutiny, political pressure, and logistical complexity.

Yes, the timeline has shifted to June 2026. But that’s because they’re prioritising safety, reliability, and long-term resilience. Criticising the delivery team doesn’t help—it demoralises the very people working to fix the problem.
 

BlueLeanie

On Moderation
Joined
21 Jul 2023
Messages
723
Location
Haddenham
During the excavation, they uncovered previously undocumented water mains, a large inverted brick drainage structure, and numerous unknown utility cables. These weren’t in any plans.

I believe that they were all documented on plans that weren't made available to Network Rail.

Indeed over 100 years ago Oxford Council refused to allow GWR to widen and deepen the the bridge due to a large brick sewer just under the surface.

Likewise the University had their power station just off Mill Lane, and the cables are all documented on University records.
 

BrianW

Established Member
Joined
22 Mar 2017
Messages
2,131
Some people need to remember the facts before criticising the project team.

During the excavation, they uncovered previously undocumented water mains, a large inverted brick drainage structure, and numerous unknown utility cables. These weren’t in any plans.

The team had to:

• Divert a critical trunk water main that supplies much of Oxford.

• Coordinate with Thames Water on design approvals and connection points, which caused delays.

• Work around environmental constraints and structural weaknesses near Osney Bridge.

These are not failures—they're unforeseen engineering challenges. And the people managing them are doing so under intense public scrutiny, political pressure, and logistical complexity.

Yes, the timeline has shifted to June 2026. But that’s because they’re prioritising safety, reliability, and long-term resilience. Criticising the delivery team doesn’t help—it demoralises the very people working to fix the problem.
Does your understanding of the 'project team' not include those who did not commission or carry out a fuller site investigation. Were no lessons learned from the changes made on the GW Electrification consequent upon such, including the cancellation of wiring to Oxford?? The things you list as 'the team had to ...' could have been considered earlier, and some might think should have, and would have given good project management.
I believe that they were all documented on plans that weren't made available to Network Rail.

Indeed over 100 years ago Oxford Council refused to allow GWR to widen and deepen the the bridge due to a large brick sewer just under the surface.

Likewise the University had their power station just off Mill Lane, and the cables are all documented on University records.
... as this posting seems to support.
 

Xavi

Member
Joined
17 Apr 2012
Messages
854
Does your understanding of the 'project team' not include those who did not commission or carry out a fuller site investigation. Were no lessons learned from the changes made on the GW Electrification consequent upon such, including the cancellation of wiring to Oxford?? The things you list as 'the team had to ...' could have been considered earlier, and some might think should have, and would have given good project management.

... as this posting seems to support.
Not as simple to trace all underground assets as you appear to believe.

== Doublepost prevention - post automatically merged: ==

I believe that they were all documented on plans that weren't made available to Network Rail.

Indeed over 100 years ago Oxford Council refused to allow GWR to widen and deepen the the bridge due to a large brick sewer just under the surface.

Likewise the University had their power station just off Mill Lane, and the cables are all documented on University records.
Indeed. Not made available.
 

SynthD

Established Member
Joined
4 Apr 2020
Messages
2,019
Location
UK
Really does feel like a big bang project should take its place (Cowley, wires to Didcot, two new through platforms inc main rebuild) - if there was ambition enough.
That sounds like the future plan specified, plus Cowley. It’s not a new idea, it’s in that NR unfunded-dreams holding area.
I believe that they were all documented on plans that weren't made available to Network Rail.
Are those plans available to us now?
 

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
Each of these utilities belongs to a different private company who will use their own contractors and may well insist that their guys have the site to themselves for H&S reasons, They will also turn up when it suits them, not NR
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,610
That sounds like the future plan specified, plus Cowley. It’s not a new idea, it’s in that NR unfunded-dreams holding area.

Are those plans available to us now?
Yes but I meant now folding in p5 which would have come from this project.

Also wires were not part of it. But a full master plan could cover off all of these pieces.
 

74A

Member
Joined
27 Aug 2015
Messages
772
Walkway seems to be open this morning. Passed over the bridge and people were walking through.
 

Nicholas43

Member
Joined
16 Jun 2011
Messages
646
Location
Radley
Walkway seems to be open this morning. Passed over the bridge and people were walking through.
Welcome news: thanks for the update.
Maybe this thread should be renamed 'Botley Road, Oxford, highway improvements and utilities diversions'? With a separate speculative thread about a hoped-for new platform 5, new west entrance, and new bridge over the Sheepwash channel?
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,252
Welcome news: thanks for the update.
Maybe this thread should be renamed 'Botley Road, Oxford, highway improvements and utilities diversions'? With a separate speculative thread about a hoped-for new platform 5, new west entrance, and new bridge over the Sheepwash channel?
I think that would be mistaken. The Platform 5 works have always been discussed in this thread, and who’s to say P5 is speculation? Some members being pessimistic doesn’t make something cancelled. The track changes south of Botley Rd for P5 were completed a while ago and are covered in this thread?
 

gallafent

Member
Joined
23 Dec 2010
Messages
549
What a cluster. All that and no second entrance or additional platform / capacity. Laughable.

Really does feel like a big bang project should take its place (Cowley, wires to Didcot, two new through platforms inc main rebuild) - if there was ambition enough.

It feels like this type of development gets successfully completed in Cambridge.
This. It's just abject. The dumping / "rescheduling" of the western entrance (which would have been / will eventually be, we all hope) one of the main benefits of the whole thing, especially for everyone approaching the station from the west, but for all users in fact, by reducing congestion in the existing facilities (thank goodness for the new entrance by platforms 1 and 2, at least!), has been very very quiet, unsurprisingly.

I was just searching for the original press releases which I remember in particular talked about a new improved project management approach (I hesitate to use the word "agile" here) which was employed in the first attempt at this project, before the more recent "reset". I wasn't able to find any such resources. I wonder if anyone here has better recollection / knowledge / documentation that talks about that project management approach, and I wonder if it has been abandoned with extreme prejudice by NR, as it clearly deserves to have been.

Looking at the internet archive for the project from less than three years ago is quite interesting:

Key benefits​

  • New platform with improved passenger facilities to significantly improve station capacity from 2024.
  • New secondary station entrance on the western side of the railway to improve accessibility and passenger experience.
  • Replacement and upgrade of Botley Road bridge, with addition of 4-metre cycle/footway on each side to encourage walking and cycling.
  • Additional height clearance of new bridge will mean standard size double-decker buses will be able to pass underneath for the first time.
  • Realignment of Roger Dudman Way to create safer road layout for junctions with Botley Road.
  • Closure of level crossings at Yarnton Lane and Sandy Lane, as well as creation of three high-speed crossovers at Oxford North Junction. This will:
    1. Improve safety of the line
    2. Create capacity for additional Oxford to Birmingham passenger services
    3. Reduce journey times by up to two minutes
    4. Increase in capacity to accommodate an additional 12 freight trains per day

Look at the top two "key benefits". Grim.
 
Last edited:

quantinghome

Established Member
Joined
1 Jun 2013
Messages
2,856
Not as simple to trace all underground assets as you appear to believe.
Yes, it costs money to do a thorough utilities search, and even more money to do GPR and intrusive site investigation. But as this project shows, and as a competent project team should understand, you always pay for a high quality site investigation - whether you do one or not.
 

Brush 4

Member
Joined
25 Nov 2018
Messages
715
Why would there be different quality investigations? It has to be 100% or it's pointless.
 

geordieblue

Member
Joined
11 Jan 2020
Messages
787
Location
Leeds
Some people need to remember the facts before criticising the project team.

During the excavation, they uncovered previously undocumented water mains, a large inverted brick drainage structure, and numerous unknown utility cables. These weren’t in any plans.

The team had to:

• Divert a critical trunk water main that supplies much of Oxford.

• Coordinate with Thames Water on design approvals and connection points, which caused delays.

• Work around environmental constraints and structural weaknesses near Osney Bridge.

These are not failures—they're unforeseen engineering challenges. And the people managing them are doing so under intense public scrutiny, political pressure, and logistical complexity.

Yes, the timeline has shifted to June 2026. But that’s because they’re prioritising safety, reliability, and long-term resilience. Criticising the delivery team doesn’t help—it demoralises the very people working to fix the problem.
Is this AI written?
 

Xavi

Member
Joined
17 Apr 2012
Messages
854
Is this AI written?
No. I happen to know the facts. It’s not one of my projects though.

== Doublepost prevention - post automatically merged: ==

Yes, it costs money to do a thorough utilities search, and even more money to do GPR and intrusive site investigation. But as this project shows, and as a competent project team should understand, you always pay for a high quality site investigation - whether you do one or not.
Intrusive surveys are for predominantly for ground conditions not utilities on civil engineering projects.
 
Last edited:

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,578
No. I happen to know the facts. It’s not one of my projects though.
I assume the question came from the use of em-dashes, oxford commas and bullet points all in small number of words. Em-dashes in particular are difficult to type, and the forum software doesn't generate them for you.
 

Xavi

Member
Joined
17 Apr 2012
Messages
854
I assume the question came from the use of em-dashes, oxford commas and bullet points all in small number of words. Em-dashes in particular are difficult to type, and the forum software doesn't generate them for you.
Interesting you should notice that, I’ve got into the Alt 0151 habit this year. Once I realised how much more professional it looks it stuck. As for Oxford commas that’s just my preferred grammar. Appropriate for this thread too!
 