Because of the change to class 350s from class 185s, TPE has extended to 1745 Lancaster to Manchester Airport to start from Oxenholme to start at 1731 (Mon-Fri). It arrives at platform 2 and departs from platform 1. It has a long wait at Oxenholme. It cannot use the Windermere platform 3 since it is not electrified. Nor does it use the Oxenholme sidings. Instead it seems to travel to Tebay to wait and crossover. Perhaps the track and signalling at Oxenholme leaves no alternative. Anyone knows? .
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Leylandlad

Member
Joined
1 Dec 2013
Messages
118
Because of the change to class 350s from class 185s, TPE has extended to 1745 Lancaster to Manchester Airport to start from Oxenholme to start at 1731 (Mon-Fri). It arrives at platform 2 and departs from platform 1. It has a long wait at Oxenholme. It cannot use the Windermere platform 3 since it is not electrified. Nor does it use the Oxenholme sidings. Instead it seems to travel to Tebay to wait and crossover. Perhaps the track and signalling at Oxenholme leaves no alternative. Anyone knows? .

Presume its a signalling issue. The trackwork is there to do it otherwise.

ie Southbound off the Windermere line first joins the down main, then crosses onto the up main.

Trains have run south off platform 2 during engineering works.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,633
Location
Nottingham
Maybe having it turn back on the main line or to/from Oxenholme sidings conflicts with something passing through?
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,670
Would need to look at some signalling plans but there may not be a shunt signal allowing travel back into 1 from the crossover. It is probably capacity as well as you would be sitting on the up line whilst changing ends, doesn't cause an issue within Tebay.
 
Last edited:

driver9000

Established Member
Joined
13 Jan 2008
Messages
4,558
The train can't start back from platform 2 at Oxenholme because there is no main aspect to start the train from (passenger trains can't be started from shunting signal). To access the Up Goods loop at Oxenholme would require a double shunt move from Platform 2 to a shunt signal on the Up Main and then back into the loop as there is no direct access to the Up Goods loop nor is there access from the Down Goods loop direct to platform 1. Obviously a move like this takes time and clogs up the main lines so sending the train to Tebay during its long layover is the preferable move.
 

jfollows

Established Member
Joined
26 Feb 2011
Messages
10,096
Location
Wilmslow
CE49 shunting signal on platform 2, see attachment
 

Attachments

  • Oxenholme.jpg
    Oxenholme.jpg
    82.2 KB · Views: 87

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,670
Confirms my thought on not being able to get back into 1. Plans afoot for a bit of re-modelling at Oxenholme anyway, moving the down to up crossover back towards the station and some other little bits.
 

jfollows

Established Member
Joined
26 Feb 2011
Messages
10,096
Location
Wilmslow
Just for completeness, my earlier diagram only shows signals in the UP direction, this attachment shows the DOWN direction signals.
 

Attachments

  • Oxenhome down signals.jpg
    Oxenhome down signals.jpg
    64.5 KB · Views: 55