ORR has published quarterly report covering Jan-March 2025

Lots of data split by operator :

numbers of trains planned,
percentages on time (Avanti was pathetic 39%), nationally only 68%
percentages cancelled (about 1 in 30 trains) although Northern was nearer 1 in 12 cancelled including P-coded,
Elizabeth line cancelled 5% too


Lots of data to digest and comment on.

Much of the data is also on tables on ORR website, so although they compare to last year, it is possible to compare to earlier periods (eg 2019, pre Covid), although I haven't yet attempted this as it is time consuming and really needs to be done on desktop screen for easy read of spreadsheets
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
10,962
Location
London
Broadly the figures haven't changed much and I noted that on time is generally going to be replaced by "time to 3".

Elizabeth line will always be high on the cancellations because trains are often outright cancelled instead of running 20 late as a metro operation. During the period in question, there was also a driver RDW/overtime ban which led to more cancellations and P-coding.
 

Llandudno

Established Member
Joined
25 Dec 2014
Messages
2,741
Location
Matlock
Looking forward to significant improvements with nationalisation…..! LOL!
 

Wyrleybart

Established Member
Joined
29 Mar 2020
Messages
2,606
Location
South Staffordshire
Broadly the figures haven't changed much and I noted that on time is generally going to be replaced by "time to 3".

Elizabeth line will always be high on the cancellations because trains are often outright cancelled instead of running 20 late as a metro operation. During the period in question, there was also a driver RDW/overtime ban which led to more cancellations and P-coding.
With respect though, other companies have RD "bans", or do not engage in RDW, neither should large scale RDW be used to sticking plaster over poor resource management. If train crew are permanently unfit for work then replacements should be recruited and trained.
 
Status
Not open for further replies.

Top