OLE: Who is responsible

Status
Not open for further replies.

Allanw

Member
Joined
23 Aug 2017
Messages
6
Who is responsible for isolating Live Overhead Electrical Equipment, [OLE]. Is it the Nominated Person?

I have only ever worked in Conductor Rail areas.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Johncleesefan

Member
Joined
4 Sep 2013
Messages
729
I believe it's isolated by the ECO and then a NP is placed in charge similar to juice rail iso
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,523
ECO? NP? iso?



ECO - Electric Control (Room) Operator

Works in the electrical control, responsible for safely taking isolations, remote switching, turning power off in an emergency. Some of the newer Route Operations Centres include the electrical control within - Didcot for example.

NP - Nomimated Person

Works in a possession/worksite; responsible for requesting an isolation, placing earths etc.
 