NW platform extensions

Status
Not open for further replies.

coxxy

Member
Joined
16 Aug 2013
Messages
375
Any one have any ideas what has happened with the platfform extensions at Newton Le Willows? Just appears to have stopped completely.

Also the airport line? Mauldeth road, East didsbury and gatley? They appear to have been finished for months, but still not opened.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

terryc

Member
Joined
6 Jan 2013
Messages
95
Any one have any ideas what has happened with the platfform extensions at Newton Le Willows? Just appears to have stopped completely.
Work due to restart this month. Apparently delay was due to if the new Parkside development was going to have rail access, the down platform could have fouled the trackwork. Network Rail have since stated that would not be the case, even if rail connection is made in the future.
 

terryc

Member
Joined
6 Jan 2013
Messages
95
Building work on Platform 1 extension looks complete, but not yet 'open' (as of Wednesday)
Platform 2 building work not complete but is still ongoing.
 

EZJ

On Moderation
Joined
20 Jun 2022
Messages
198
Location
Shoreham
Airport line platforms should've opened over this weekend, unbelievably they still will not facilitate a 6 car unit, rear coach will still not open doors according to the safety bulletins we've received.
 

TheGrew

Member
Joined
31 Jul 2012
Messages
511
A Newton-le-Willows councilor has just posted that the extension has been completed. Now it just needs software mods for the 802s to disable SDO both there and Lea Green.
May be an image of train and railway
 

coxxy

Member
Joined
16 Aug 2013
Messages
375
A Newton-le-Willows councilor has just posted that the extension has been completed. Now it just needs software mods for the 802s to disable SDO both there and Lea Green.
May be an image of train and railway
Will still need CASDO for the 185's though - which still won't be fully accommodating a 6 car.
 