Bebside opening date Sunday 19th October
www.northumberland.gov.uk
The fourth station to be completed on the Northumberland Line will open on Sunday, October 19th.
Since the opening of the line in December 2024 the project has seen big benefits not just in terms of travel, but also investment, educational and job opportunities, as well as enhanced public transport connectivity across the wider region.
In its first eight months of service alone, with stations open in Ashington, Seaton Delaval and Newsham, there were well over 500,000 passenger journeys.
Now Bebside Station in Blyth will remove its barriers and welcome passengers from Sunday, October 19th, allowing people to travel to Newcastle in just 29 minutes.
The final remaining two stations at Bedlington and Northumberland Park in North Tyneside are scheduled to open in early 2026.