Newton le Willows Platform Extensions

Status
Not open for further replies.

terryc

Member
Joined
6 Jan 2013
Messages
95
Despite being started months ago, both platform extensions to the east of the station appear to have stalled. The platform edges have been completed, but the actual platform tops are unfinished, and are therefore still out of use. Has anyone any idea as to the cause of delay?
Many Thanks
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

coxxy

Member
Joined
16 Aug 2013
Messages
375
Same on the airport line.

The progress has been excruciatingly slow across the board....
 

danbarjon

Member
Joined
6 Feb 2022
Messages
327
Location
West Lancashire
Lea Green seems to be done and I'm going to test it today, however it appears that TPE still don't release the reach 2 coaches doors
 

TheGrew

Member
Joined
31 Jul 2012
Messages
511
Despite being started months ago, both platform extensions to the east of the station appear to have stalled. The platform edges have been completed, but the actual platform tops are unfinished, and are therefore still out of use. Has anyone any idea as to the cause of delay?
Many Thanks
@The Planner commented on another thread that work had been paused because of a potential need to consider new sidings for the Parkside Development. I asked a local counselor to confirm with Network Rail and apparently, they did.
 
Status
Not open for further replies.