Just currently showing as running late due to a late running train being infront of it, but there’s nothing currently infront of it, nor anything obvious delaying its previous journey (2T68).
 

1D54

Established Member
Joined
1 Jun 2019
Messages
1,480
Massive fire on an industrial estate at Newark Northgate yesterday afternoon at 15:00 so may be something to do with the delays.
 
Joined
15 Apr 2020
Messages
409
Location
Wakefield
Track circuit failure between Newark East Junction and Collingham station. 2T67 was the first train affected so had to examine the line and certainly took his time doing so.
 

LowLevel

Established Member
Joined
26 Oct 2013
Messages
8,926
The signalling system between Newark and Lincoln on the former Midland Railway route is life expired and track circuit and level crossing failures are very common. It's meant to be resignalled soon but seems to be on hold at the moment.

The signalling system in place dates from I believe 1967 so is pretty ancient for power signalling.
 