Just reading the thread about 60m refurb for 321's

Typically how much does a new fleet cost compared to refurbs. Our fleet has had a couple of refurbs/refreshes. At what point is a new fleet financially better or is it more to do with the practicalities of old units vs new.

Cheers in advance.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Joined
10 Mar 2015
Messages
771
I think, and this is just I think, I heard the 321 renatus refurb will cost about 1/3 of the cost of a new fleet. I think.
 

Dave1987

On Moderation
Joined
20 Oct 2012
Messages
4,563
From what I gather the rough going rate for new trains is about £2.5m per coach. So a 4 car train would cost about £10m ish.
 

Yew

Established Member
Joined
12 Mar 2011
Messages
7,214
Location
UK
Of course. This also depends on the scope of the refurbishment. Replacing seat covers is cheaper than a complete interior redesign :)
 

The Ham

Veteran Member
Joined
6 Jul 2012
Messages
12,036
From what I gather the rough going rate for new trains is about £2.5m per coach. So a 4 car train would cost about £10m ish.

Thought it was about £1.5m?

It depends, a basic commuter EMU (no loos) is going to cost a lot less than a long distance train with lots of facilities.

Of course the purchase price is only one element as the new Desiro Cities are reported to have maintenance costs of somewhere around 1/3 less than the original Desiros as they have been designed so that maintenance is as simple as possible.

Also age of the existing trains come into play as the shorter their remaining lifespan the higher the yearly cost. As does the number of units in one of two ways; either lots of units will tend to be cheaper to do than only a few. Alternatively if there are only a few units of several different classes of units then it could be better to get a more uniform fleet by getting new units and save costs that way.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,025
Location
St Albans
It depends, a basic commuter EMU (no loos) is going to cost a lot less than a long distance train with lots of facilities.

Of course the purchase price is only one element as the new Desiro Cities are reported to have maintenance costs of somewhere around 1/3 less than the original Desiros as they have been designed so that maintenance is as simple as possible.

Also age of the existing trains come into play as the shorter their remaining lifespan the higher the yearly cost. As does the number of units in one of two ways; either lots of units will tend to be cheaper to do than only a few. Alternatively if there are only a few units of several different classes of units then it could be better to get a more uniform fleet by getting new units and save costs that way.

Also the distribution of candidates for refurbishment affects any diverse requirements, hence the RoSCos enthusiasm to get each class in as few TOCs' fleets as possible.
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,856
Location
west yorkshire
With Thyristors and GTO's in traction packages being old technology and spares becoming a problem 're-tractioning may have to be factored in.
Diddnt I read somewhere there are only a few thyristors for class 91s left on the planet.
K
 

ComUtoR

Established Member
Joined
13 Dec 2013
Messages
9,562
Location
UK
Hmm.

1/3 is still pretty high. We have had a new traction package too as well as more than one refresh and refurb. We are now getting another refurb. New units mean new tech. TMS, TPWS Mk4, Mitrac, SDO etc. There is also a benefit to the passenger too. Aircon, increased seating capacity, WiFi as well as being compliant with all current regulations. Retro fitting must also form some of the fleet running costs ?
 

Wivenswold

Established Member
Joined
24 Jul 2012
Messages
1,570
Location
Essex
You could always do both! Huge refurb then replace them with brand new trains 5 years later. Look no further than the 307s and 309s refurbished in the mid-eighties only to be replaced by 321s. Or the D-stock on the District Line in London.
 
Joined
27 Feb 2007
Messages
276
1/3 is still pretty high

Surely the other benefit of a refurb is time taken? Even a thorough refurb would presumably take much less time than building, testing, driver training on a new unit (assuming that you can't replace the old unit with an identical new build - and why would you replace like for like if the old unit is old enough to be in the bracket for replacement?).
 

al.currie93

Member
Joined
27 Jun 2013
Messages
381
From what I gather the rough going rate for new trains is about £2.5m per coach. So a 4 car train would cost about £10m ish.

Thought it was about £1.5m?

Indeed £1.4 to £1.5m for recent Bombardier orders

£1.4 million to £1.5 million seems very low to me, what Bombardier order was this? To give some other prices (all adjusted to 2015 values):

- Class 800 at £2.8 million per carriage

- Class 801 at £2.4 million per carriage

- Class 185 at £2.25 million per carriage

- Class 350 at £2 million per carriage

- Class 68 at £2.52 million per locomotive (for reference)

Locomotive hauled coaches are generally less than this - the IME gave a figure of £1 million per coach in a recent article - unless they are of a very high specification or very bespoke like the Caledonian Sleeper coaches.

Surely the other benefit of a refurb is time taken? Even a thorough refurb would presumably take much less time than building, testing, driver training on a new unit (assuming that you can't replace the old unit with an identical new build - and why would you replace like for like if the old unit is old enough to be in the bracket for replacement?).

This is a good point - the other costs for generally introducing a new train are usually overlooked.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,248
£1.4 million to £1.5 million seems very low to me, what Bombardier order was this? To give some other prices (all adjusted to 2015 values):

- Class 800 at £2.8 million per carriage

- Class 801 at £2.4 million per carriage

- Class 185 at £2.25 million per carriage

- Class 350 at £2 million per carriage

- Class 68 at £2.52 million per locomotive (for reference)

Locomotive hauled coaches are generally less than this - the IME gave a figure of £1 million per coach in a recent article - unless they are of a very high specification or very bespoke like the Caledonian Sleeper coaches.



This is a good point - the other costs for generally introducing a new train are usually overlooked.

You are comparing Apples and Oranges as some rolling stock like 800s 350s 185s on your list above had servicing and maintenance included for a very long period (upto 27 years in some cases!).

How about a current one 387/2 (first 10 units being tested now).

27x 4 car units for £145.2m so £1.344m per car

http://www.railwaygazette.com/news/...w/gatwick-express-class-3872-emu-on-test.html

387/1

29x 4 car units for £180m so £1.551m per car

http://www.railwaygazette.com/news/...-to-supply-trains-for-thameslink-cascade.html

377/6

26x 5 car units for £188.1m so £1.452m per car

http://www.railnews.co.uk/news/2011/12/28-boost-for-derby-as-bombardier.html


Edit to Add:
Class 700 £1.4035 per car (1.6bn/1140 cars)

Class 707 £1.40m per car (£210m / 150 cars)

Class 710 £1.44m per car (£260m /180 cars)

Edit to Add (2nd time)
Angel (the owning ROSCO) put the capital cost of the 350 /3 and /4 order as £133m for 80 cars so £1.663 m per car
https://www.angeltrains.co.uk/Products-Services#million4

--- old post above --- --- new post below ---
Surely the other benefit of a refurb is time taken? Even a thorough refurb would presumably take much less time than building, testing, driver training on a new unit (assuming that you can't replace the old unit with an identical new build - and why would you replace like for like if the old unit is old enough to be in the bracket for replacement?).

Siemens and Bombardier can build and deliver new units at twice the rate Wabtec etc can refurb stuff. 2 Class 700 cars come off the production line a day at peak rate and that is not total factory capacity...

If a franchise needs to add capacity as well then new looks very attractive at the moment.
 